Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Spiire Reference Number
-
General Construction Audit
-
Site conditions
-
Weather
- Sunny
- Overcast
- Rain Heavy
- Rain Light
- Windy
- Sunny and windy
- Rain and windy
OH&S
-
PPE used as SMP & site boards?
-
Barriers & Signs in accordance with contractors T.M.P/P.M.P?
-
Traffic control measures in place as required?
-
Are trenches and excavations in accordance with Worksafe practices?
-
Is the site fencing and signage to a satisfactory level?
-
Excavation safety in accordance with contractors P.M.P?
-
Are known no-go zones identified?
-
Are machinery operating outside no go zones?
-
Have OH&S issues previously identified been rectified?
SMP & EMP
-
Are EMP measures in place as per the EMP plan
-
Is dust suppression in place
-
Is entry and exit point as per contractors TMP
-
Is fuel and spill kit area being used
Site Establishment
-
Initial survey control completed? Ie. pegging, TBM's etc.
Stripping of Topsoil
Sewer Reticulation
-
Has the sewer reticulation commenced?
-
Commencement date
-
Contractor on programme?
-
Testing undertaken and passed?
- Ovality
- Infiltration
- Pressure
- Vacuum
- Compaction
- None
-
Asset recording completed and relevant contractor documentation received?
-
Construction Verification Information submitted?
-
Scheduled commencement date
-
Pre-construction documents lodged with relevant water authority?
Stormwater Drainage
-
Has the stormwater drainage commenced?
-
Enter works complete
-
Enter section being worked on and inspected
-
Contractor on programme?
-
Has the bedding material been installed as per authority specification?
- Whittlesea City Council
- Wyndham City Council
- GAA Standards
- Vicroads
- Moreland City Council
- City of Melbourne
- Other
-
Specify
-
Is pipe jointing as per authority requirements
-
Is pipe type & diameter as specified on drainage longitudinal sections
-
Drainage pipe backfilled as specified in the drainage longitudinal sections
-
Are drainage pits constructed as documented in drainage pit schedule
-
Have the house drains and property inlets been constructed?
-
Final survey completed and submitted to Council?
Water Reticulation
-
Has the water reticulation commenced?
-
Commencement date
-
Contractor on programme?
-
Have the mains to meters been completed?
-
Testing undertaken and passed?
- Flushing of property connections
- Swabbing
- Pressure
- Water quality
- None
-
Has connection and asset recording been completed and relevant documents received?
-
Construction verification information lodged with relevant authority?
-
Scheduled commencement date
-
Pre-construction documents lodged with relevant water authority?
Road Pavement Construction
-
Has the road pavement commenced?
-
Commencement date
-
Has all the pavement been excavated to design subgrade?
-
Enter extent complete
-
Has the subgrade passed local authority proof roll?
-
Were subgrade improvement works necessary?
-
Enter extent of subgrade improvement works required
-
Has the capping layer been completed if required?
-
Enter extent of works complete
-
Have all the AG drains been installed as specified by authority standards
-
Have the conduits for road crossings been installed?
-
Enter extent of works complete
-
Has the sub-base pavement been constructed to beneath kerb & channel?
-
Enter extent of works complete
-
Has the Kerb & Channel been constructed?
-
Enter chainages/areas of works complete
-
Has the pavement base been constructed?
-
Enter chainages of complete works
-
Has the prime been completed?
-
Has the base course asphalt been laid?
-
Enter extents of works complete
-
Has the final wearing course asphalt been laid?
-
Enter extents of works complete
-
Contractor on programme?
-
Scheduled commencement date
Structural
-
Are there any structural elements?
- Culverts
- Retaining Walls
- Specially Designed Pits
- Other
-
Have the culverts commenced?
-
Commencement date
-
Contractor on programme?
-
Has the excavation been completed?
-
Is the foundation completed and as per design?
-
Is the blinding layer completed?
-
Has the base slab been completed?
-
Have the culverts been delivered? And are they as per design specifications?
-
Have the culverts been installed correctly
-
Are there link slabs? Is so, have they been installed correctly?
-
Has the mass concrete over culverts been poured?
-
Has the backfill over culverts been completed?
-
Scheduled commencement date
-
Have the Retaining Walls commenced?
-
Commencement date
-
Contractor on programme?
-
Has the excavation been completed?
-
Is the foundation completed and as per design?
-
Is the blinding layer completed?
-
Has the base slab been completed?
-
Has the retaining wall been completed and as per design?
-
Scheduled commencement date
-
Have the Specially Designed Pits commenced?
-
Commencement date
-
Contractor on programme?
-
Scheduled commencement date
-
Enter description of other works
-
Has the Other works commenced?
-
Commencement date
-
Contractor on programme?
-
Scheduled commencement date
Electrical works
-
Have the electrical works commenced?
-
Commencement date
-
Electrical pits concrete encased?
-
Pegging completed? (Required for audit)
-
Audit date
-
Has the final audit passed?
-
NOTE: Landscaping works not to commence yet!!
-
Scheduled date
-
Contractor on programme?
-
Scheduled commencement date
Communications works
-
Have the communications works commenced?
-
Commencement date
-
As built information received from contractor?
-
Submitted to NBN designer?
-
Submitted to NBN?
-
Contractor on programme?
-
Scheduled commencement date
Traffic Signals
-
Are there traffic signals required on this project?
-
Have the works commenced yet?
-
Commencement date
-
Contractor on programme?
-
Scheduled commencement date
Construction of footpath and crossings
-
Has the construction of footpaths and crossings commenced?
-
Contractor on programme?
-
Scheduled commencement date
Grade lots/topsoil
-
Has the grading/topsoiling commenced?
-
Commencement date
-
Contractor on programme?
-
Scheduled commencement date
Linemarking and signage
-
Has the linemarking and signage commenced?
-
Commencement date
-
Scheduled commencement date
Auxiliary Works
-
Are there auxiliary works associated with the project?
-
Enter extent/description of auxiliary works
Key action items completed since last site meeting
-
Enter status of key actions
Incidentals
-
Select summary of plant on site
- Bulldozer
- Excavator
- Front end loader
- Grader
- Roller - Padfoot
- Roller - Smooth Drum
- Scraper
- Skidsteer
- Stabiliser
- Watercart
- Other
-
Enter additional plant
-
Enter summary of works ongoing
-
additional comments
-
Please sign off once audit is completed
-
Add photos