Pumps
-
Pump 1 present
-
Any faults present (mechanical seal failure / vibration / over temp) etc.
-
Fault details
-
No. Of starts
-
Run hours
-
Pump runs in local manual
-
Flushing valve working
-
Pump flow rate
-
Discharge pressure
-
12 monthly inspection, removal from Well for Pump and Ancillary Equipment.
-
Measure clearance between Impeller and Wear Ring and record measurements and Impeller condition. Replace as required.
-
Pump housing in good condition.
-
Take lubricant sample (have sample sent for analysis) change lubricant.
-
Check Flushing Valve (water in oil, oil in diaphragm) check oil level, top up as required. Check mounting bolts.
-
Check pump housing bolts.
-
Inspect sacrificial Anode for corrosion, replace if required.
-
Pump 2 present
-
Any faults present (mechanical seal failure / vibration / over temp) etc.
-
Fault details
-
No. Of starts
-
Run hours
-
Pump runs in local manual
-
Flushing valve working
-
Pump flow rate
-
Discharge pressure
-
12 monthly inspection, removal from Well for Pump and Ancillary Equipment.
-
Measure clearance between Impeller and Wear Ring and record measurements and Impeller condition. Replace as required.
-
Pump housing in good condition.
-
Take lubricant sample (have sample sent for analysis) change lubricant.
-
Check Flushing Valve (water in oil, oil in diaphragm) check oil level, top up as required. Check mounting bolts.
-
Check pump housing bolts.
-
Inspect sacrificial Anode for corrosion, replace if required.
-
Pump 3 present
-
Any faults present (mechanical seal failure / vibration / over temp) etc.
-
Fault details
-
No. Of starts
-
Run hours
-
Pump runs in local manual
-
Flushing valve working
-
Pump flow rate
-
Discharge pressure
-
12 monthly inspection, removal from Well for Pump and Ancillary Equipment.
-
Measure clearance between Impeller and Wear Ring and record measurements and Impeller condition. Replace as required.
-
Pump housing in good condition.
-
Take lubricant sample (have sample sent for analysis) change lubricant.
-
Check Flushing Valve (water in oil, oil in diaphragm) check oil level, top up as required. Check mounting bolts.
-
Check pump housing bolts.
-
Inspect sacrificial Anode for corrosion, replace if required.
-
Pump 4 present
-
Any faults present (mechanical seal failure / vibration / over temp) etc.
-
Fault details
-
No. Of starts
-
Run hours
-
Pump runs in local manual
-
Flushing valve working
-
Pump flow rate
-
Discharge pressure
-
12 monthly inspection, removal from Well for Pump and Ancillary Equipment.
-
Measure clearance between Impeller and Wear Ring and record measurements and Impeller condition. Replace as required.
-
Pump housing in good condition.
-
Take lubricant sample (have sample sent for analysis) change lubricant.
-
Check Flushing Valve (water in oil, oil in diaphragm) check oil level, top up as required. Check mounting bolts.
-
Check pump housing bolts.
-
Inspect sacrificial Anode for corrosion, replace if required.
Wet well / Dry well
-
Wet Well in good condition
-
Dry well in good condition
-
Are Ventilation Fans in good working order
-
12 monthly inspections, to be completed in conjunction with E&M Well Cleaning.
-
Pump 1 Inspect lifting chains and shackles for corrosion and damage, check Safety Tags are within inspection date
-
Pump 2 Inspect lifting chains and shackles for corrosion and damage, check Safety Tags are within inspection date
-
Pump 3 Inspect lifting chains and shackles for corrosion and damage, check Safety Tags are within inspection date
-
Pump 4 Inspect lifting chains and shackles for corrosion and damage, check Safety Tags are within inspection date
-
Entry / exit ladder in good condition
-
Platforms in good condition
-
Pipes / Fittings / Couplings / Valves / Penstocks secure and in good condition, report any cracks, leakage, corrosion etc.
Valves
-
Exercise Valves / Penstocks, operating and in good working order
-
Non return valves working.
-
12 monthly inspect, in conjunction with E&M Wet Well Clean
-
Lubricate Valve Stem and associated parts as required.
General
-
Lighting working and sufficient in all areas
-
Doors / gates / locks in good working order
-
Fences undamaged
-
Site surrounds tidy and in safe condition
-
Complete site diary, highlighting work complete
-
Any other issues
-