Information

  • Audit Title

  • Document No.

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Manufacturing progress status

  • Are the vessels in production clearly identifiable?

  • Which vessels were seen in production and at what stage were they at?

  • Details of inspection.

  • Result of inspection.

  • Are there any areas of concern?

Have current milestone dates been met?

  • Are the proposed dates on target?

Have there been any validation audits by a third party?

  • What was the outcome of the validation audit by the third party?

  • Have there been any Non Conformances reported?

  • Are there any outstanding issues?

Can the design requirements be provided for verification?

  • Client provided project overview and design requirement documentation sighted and approved?

Can the design specifications be provided for verification?

  • Does the manufacturer have documentary evidence of compliance to the relevant standards?

  • Inner vessel, compliance to: BS EN 13530 parts 1, 2 and 3: 2002?

  • Inner vessel, compliance to: ADR chapter 6.7.4 Tank Instruction Code T75?

  • Inner vessel, compliance to: ISO 1496-3, amended 2006?

  • Inner vessel, compliance to: IMDG/RID/UIC and also ' The Carriage of Dangerous Goods by Road Regulations', chapter 6.7: 2009 as amended and associated Health and Safety commission Approved Requirements?

  • Pipework complies to ASME B31.3?

  • Cryogenic valves and SSOV's, stainless steel to BS 6364:1984, BS EN 1626: 1999, BS EN 12567: 2000' or equivalent?

  • Cryogenic safety valves to BS EN 13648 parts 1 and 3: 2002, or equivalent?

Can the design calculations be provided for verification?

  • The design calculations have been verified?

Can we verify the weld procedure qualifications are approved?

  • Does the manufacturer have documentary evidence of compliance to the relevant standards?

  • Automated welding operators to EN 1418: 1997?

  • Welding procedures for metallic materials to EN 288 parts 3 and 4: 1992?

  • Pre-production weld tests to EN 288-8: 1992?

Can we verify the welder qualification records and approvals?

  • Does the manufacturer have documentary evidence of compliance to the relevant standards?

  • Automated welding operators to EN 1418: 1997?

  • Approval testing of welders to EN 287 parts 1 and 2: 1992?

Can the material certifications be provided for verification?

  • Does the manufacturer have certificates and supporting documentation for all materials and consumables?

Stage 1: Sign off.

  • For QEM Solutions.

  • For manufacturer Quality Control.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.