Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Roof Works - Rail Setout
Rail Setout
-
All rail and supports installed as per Clenergy installation guidelines? ** Upload supporting photo
-
Panel layout installed as per design? ** Upload supporting photo
Panel Works
-
All solar DC cabling tied to rail and clipped to panels? ** Upload supporting photo
-
Point of Disconnection - Labels applied and MC4's accessible / within 150mm from panel edge? ** Upload supporting photo
Roof Electrical Testing
-
What is the Panel VOC (see value on back label of panel)
-
What is the Panel ISC (see value on back label of panel)
-
Photo of back label of panel
-
Test VOC for string 1
-
Test VOC for string 2
-
Test VOC for string 3
-
Test VOC for string 4
-
Finished product photo of arrays (instagram worthy shot)
Inverter
-
Inverter installed as per manufacturers specifications
Inverter Electrical Testing
-
Earth continuity and resistance between inverter / array earth to earth electrode.
MPPT
-
Check polarity between positive and negative
-
String VOC =
-
Megger at 500V DC - Positive to earth =
-
Megger at 500V DC - Negative to earth =
Commissioning
-
Set grid profile to Australia NSW Region A (or 1) profile
-
Confirm CT measurement direction is correct (arrow points towards the house loads). In monitoring make sure the load graph is not following the solar production.
-
Inverter Operational Mode Checks
-
Confirm anti-islanding protection works - Turn off AC circuit breaker "Main Switch (Inverter Supply)" and confirm inverter shuts down within 2 seconds.
MPPT
-
Voltage =
-
Current =
Customer Satisfaction
-
The customer is satisfied with the works that were undertaken by Solar Share Project Pty Ltd and that the finished product and site conditions post installation works are tidy and acceptable.
-
The customer may add any notes or conditions below: