EARTHWORKS TRIM AND COMPACT ITP
Lots can include areas for Clearing and Grubbing, Sub-grade Trimming and Compacting and compacting around structures. -
Lot number
-
Chainage, Carriageway
-
Describe the weather conditions during the trim and compact duration.
-
Specified compaction
- 95% Standard
- 98% Standard
- 100% Standard
- 95% Modified
- 98% Modified
- 100% Modified
-
Is this layer a Hold Point or Witness Point which requires Client Signoff?
-
Plan for notice to be given to the client for their involvement. There is a Client Signoff field at the bottom of this ITP.
-
Add a photo
-
Does the embankment position conform to the plan and set out?
-
Attach copy of Survey verification if available.
-
Compaction Test Results (attach test reports)
Compaction Result
-
Test reference, e.g. Exact chainage, CL offset.
-
Compaction test result %
-
Pass?
-
Has the Lot passed the Proof Roll? A Proof Roll confirms the area has been compacted consistently and there are no isolated soft spots.
-
Lot Passed
-
If the Lot failed, prepare a NCR.
-
If a HP or WP, Client Signoff
-
Contractor Signoff