INFORMATION
-
Document No.
-
Audit Title
-
Swissport ) Tank Farm
-
Conducted on
-
Location : YVR
-
Personnel
Tank Cleaning
-
Empty Tank
-
Dip Tank to verify (at least one Tank)
-
Disable Inlet and Outlet valves
Lock Out
-
Lockout both Inlet and Outlet valves
-
Install blinds both Inlet and Outlet Pipes
-
Open Hatch Cover 1
-
Open Hatch Cover 2
-
Sump Out remaining fuel
-
Vent Tank overnight
Confined Space and PPE
-
Monitor Reading level for Tank
-
Confined Space Respirator
-
Goggles
-
Gloves
-
Hard Hat
-
Harness for Confined Space
-
Ear Plugs
-
Water resistant clothing
Tank Cleaning
-
Sump water out of tank
-
Air-Dry tank
-
Make sure no trace of water
Installation
-
Install Hatch 1 with new hardware
-
Install Hatch 2 with new hardware
-
Remove Blinds from Inlet and Outlet Pipes
-
Remove Lock outs from Inlet and Outlet Valves
-
Final walk around to verify everything is in place
Open Valves
-
Open Valves
-
Fill Tank at slow rate and monitor for leaks
-
Monitor tank hourly while filling to check for leaks of the man way areas GPPM 5.3.4 (g)
Supervisor on Shift
-
Select date
-
Name