Information

  • Property Address

  • Suburb

  • Works Conducted on

  • Scope of Work performed?

  • Prepared by

  • Works Performed By?

  • PID

  • Title Reference number

Pre-Works Photos

  • Photos of property prior to works being performed

TasWater Endorsed Plans & CCW (Certificate of Certifiable Work)

  • Upload photo/s of the TasWater Endorsed Plans used to perform the customer connection

  • Upload photo/s of CCW (Certificate of Certifiable Work) *where applicable

Safety

Safety

  • Traffic Management /control needed?

  • Any Hazards on site have been added to SWMS spreadsheet & SWMS completed?

Fire Service Connection Details (RA)

Fire Service Connection information for Revenue Assurance

  • Was a Fire Service installed?

  • Fire Service Details

  • What size is the new Fire Service Connection size?

  • What size is the Bypass Meter size?

  • How was the Fire service installed?

  • Bypass meter serial number

  • Bypass meter radio number

  • Clear close-up photo showing the Bypass meter serial number & meter reading

  • Clear close-up photo showing the Bypass meter radio number

  • Date the Fire service was installed

  • Serviced Property (e.g. unit 1 or Lot 1) - Fire Service

  • Description of land at time of Connection - Fire Service

Domestic Meter Assembly Details (RA)

Domestic Meter Assembly information for Revenue Assurance

  • Was a domestic meter assembly installed?

  • Domestic Meter Details

  • What size is the Domestic meter?

  • What size is the New Water Connection?

  • How was the Domestic Meter situated?

  • Domestic meter serial number

  • Domestic meter radio number

  • Clear close-up photo showing the Domestic meter serial number & meter reading

  • Clear close-up photo showing the Domestic meter radio number

  • Date of Domestic meter install

  • Serviced Property (e.g. unit 1 or Lot 1) - Domestic

  • Description of land at time of Connection - Domestic

  • Is meter installation Complete?

Water Connection on TasWater Infrastructure photos & location details

Water connection photos

  • Was a new water connection installed?

  • Photos showing the excavation works

  • Photo showing TasWater Mains

  • Photo showing the TPFNR installation

  • Photos showing pipework installation

  • Photos showing the meter assembly

Reinstatement of Connection Works photos

  • Photos showing backfill

  • Photos showing the installation of metallic detector tape

  • Photos showing reinstatement of excavation area

  • Photos showing the meter assembly

Location of new meter assembly

  • The measurements from the property boundaries (e.g. 5mtrs from left boundary & 500mm from front boundary

  • The length (in metres) of the connecting pipework from the mains connection point

  • The depth (in millimetres) of the pipe work at the connection point and termination of the meter assembly

  • Northerly bearing for plan

  • Was the existing water connection upgraded?

  • Was the existing connection downsized?

  • Was the existing connection used to install new meter assembly?

  • Photos showing existing connection used for the meter installation

Reinstatement of Connection Works photos

  • Photos showing backfill

  • Photos showing reinstatement of excavation area

  • Photos showing the meter assembly

Location of new meter assembly

  • The measurements from the property boundaries (e.g. 5mtrs from left boundary & 500mm from front boundary

  • The length (in metres) of the connecting pipework from the mains connection point

  • The depth (in millimetres) of the pipe work at the connection point and termination of the meter assembly

  • Northerly bearing for plan

  • Photos showing the excavation works

  • Photos showing pipework installation

  • Photos showing the downsize

Location of new meter assembly and water works performed

  • The measurements from the property boundaries (e.g. 5mtrs from left boundary & 500mm from front boundary)

  • The length (in metres) of the connecting pipework from the mains connection point.

  • The depth (in millimetres) of the pipe work at the connection point.

  • Northerly bearing for plan

  • Photos showing the excavation works

  • Photos showing the existing TPFNR

  • Photos showing the installation of the pipework

Reinstatement of Connection Works photos

  • Photos showing backfill

  • Photos showing the installation of metallic detector tape

  • Photos showing reinstatement of excavation area

  • Photos showing the meter assembly

Location of new meter assembly

  • The measurements from the property boundaries (e.g. 5mtrs from left boundary & 500mm from front boundary

  • The length (in metres) of the connecting pipework from the mains connection point

  • The depth (in millimetres) of the pipe work at the connection point and termination of the meter assembly

  • Northerly bearing for plan

Details of Existing Water Connection/Meter Details (RA)

Details of Existing Water Connection/Meter Details information for Revenue Assurance

  • Was an existing water connection capped & sealed?

  • How many existing water connections were capped and sealed?

  • Disconnected Service details

  • What size is the existing water connection that was disconnected?

  • What size was the existing Meter that was removed?

  • Meter serial number

  • Clear close-up photo showing the meter serial number & meter reading

  • Clear close-up photo showing the meter radio number

  • Date of meter removal

  • Serviced Property (e.g. unit 1 or Lot 1)

  • Description of property at time of works being performed?

  • Disconnected Service details no.1

  • What size is the existing water connection that was disconnected?

  • What size was the existing Meter that was removed?

  • Meter serial number

  • Clear close-up photo showing the meter serial number & meter reading

  • Clear close-up photo showing the meter radio number

  • Date of meter removal

  • Serviced Property (e.g. unit 1 or Lot 1)

  • Description of property at time of works being performed?

  • Disconnected Service details no.2

  • What size is the existing water connection that was disconnected?

  • What size was the existing Meter that was removed?

  • Meter serial number

  • Clear close-up photo showing the meter serial number & meter reading

  • Clear close-up photo showing the meter radio number

  • Date of meter removal

  • Serviced Property (e.g. unit 1 or Lot 1)

  • Description of property at time of works being performed?

  • Disconnected Service details no.1

  • What size is the existing water connection that was disconnected?

  • What size was the existing Meter that was removed?

  • Meter serial number

  • Clear close-up photo showing the meter serial number & meter reading

  • Clear close-up photo showing the meter radio number

  • Date of meter removal

  • Serviced Property (e.g. unit 1 or Lot 1)

  • Description of property at time of works being performed?

  • Disconnected Service details no.2

  • What size is the existing water connection that was disconnected?

  • What size was the existing Meter that was removed?

  • Meter serial number

  • Clear close-up photo showing the meter serial number & meter reading

  • Clear close-up photo showing the meter radio number

  • Date of meter removal

  • Serviced Property (e.g. unit 1 or Lot 1)

  • Description of property at time of works being performed?

  • Disconnected Service details no.3

  • What size is the existing water connection that was disconnected?

  • What size was the existing Meter that was removed?

  • Meter serial number

  • Clear close-up photo showing the meter serial number & meter reading

  • Clear close-up photo showing the meter radio number

  • Date of meter removal

  • Serviced Property (e.g. unit 1 or Lot 1)

  • Description of property at time of works being performed?

  • Disconnected Service details no.4

  • What size is the existing water connection that was disconnected?

  • What size was the existing Meter that was removed?

  • Meter serial number

  • Clear close-up photo showing the meter serial number & meter reading

  • Clear close-up photo showing the meter radio number

  • Date of meter removal

  • Serviced Property (e.g. unit 1 or Lot 1)

  • Description of property at time of works being performed?

  • Disconnected Service details no.1

  • What size is the existing water connection that was disconnected?

  • What size was the existing Meter that was removed?

  • Meter serial number

  • Clear close-up photo showing the meter serial number & meter reading

  • Clear close-up photo showing the meter radio number

  • Date of meter removal

  • Serviced Property (e.g. unit 1 or Lot 1)

  • Description of property at time of works being performed?

  • Disconnected Service details no.2

  • What size is the existing water connection that was disconnected?

  • What size was the existing Meter that was removed?

  • Meter serial number

  • Clear close-up photo showing the meter serial number & meter reading

  • Clear close-up photo showing the meter radio number

  • Date of meter removal

  • Serviced Property (e.g. unit 1 or Lot 1)

  • Description of property at time of works being performed?

  • Disconnected Service details no.3

  • What size is the existing water connection that was disconnected?

  • What size was the existing Meter that was removed?

  • Meter serial number

  • Clear close-up photo showing the meter serial number & meter reading

  • Clear close-up photo showing the meter radio number

  • Date of meter removal

  • Serviced Property (e.g. unit 1 or Lot 1)

  • Description of property at time of works being performed?

Disconnection of Existing Water Connection photos & location details

Disconnection of Existing Water Connection photos

  • Was a water disconnection performed?

  • Was the pipe work removed?

  • Photo showing the existing connection

  • Photo showing the cap and seal of existing connection

  • Photos showing backfill

  • Photos showing reinstatement of excavation area

Location of Disconnected Water Connection

  • The measurements from the property boundaries to disconnection point on TasWater main.

  • Northerly bearing

New Fire Plug installation photos & location details

New Fire Plug installation photos

  • Was a new fire plug installed?

  • Photos showing the excavation works

  • Photos showing the installation of a new fire plug

  • Photos showing the backfill of excavation works

  • Photos showing reinstatement

  • Photos showing fire plug road markings

  • Has a flow test been completed?

  • If you don't have flow testing equipment, please contact TasWater on 13 6992 to arrange a flow test and send a copy of the flow test results with the completion sheet pack.

  • Please upload load a copy of the flow test results.

Fire Plug Location Details

  • The measurements from the property boundaries

  • The measurements from the nearest public road

  • The length (in metres) of the connecting pipework from the mains connection point to the fire plug

  • The depth (in millimetres) of the pipe work at the connection point and termination of the fire plug

  • Northerly bearing for plan

New Fire Hydrant Installation photos & location details

New Fire Hydrant Installation photos

  • Was a new hydrant installed?

  • Photos showing the excavation works

  • Photos showing the installation of a new hydrant

  • Photos showing the backfill of excavation works

  • Photos showing reinstatement

  • Photos showing hydrant road markings

Location of New Fire Hydrant

  • The measurements from the property boundaries

  • The measurements from the nearest public road

  • The length (in metres) of the connecting pipework from the mains connection point to the hydrant

  • The depth (in millimetres) of the pipe work at the connection point and termination of the hydrant

  • Northerly bearing for plan

  • Has a flow test been completed?

  • If you don't have flow testing equipment, please contact TasWater on 13 6992 to arrange a flow test and send a copy of the flow test results with the completion sheet pack.

  • Please upload load a copy of the flow test results.

AsCons

  • Upload photo/s of map showing the locations on works performed, including water disconnections and connection work.

  • Upload a photo/s of the completed Fire Domestic Water Disconnection & Connection Completion Form

Panel Member Sign off of Works Completed

  • Full name of Panel Member onsite Supervisor (type full name and sign)

  • Full name of Panel Member onsite Plumber (type full name and sign)

  • Comments

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.