Information
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Checklist
-
Mobile Gantry has adequate access around site?
-
Jobsite provided with adequate material staging area?
-
Adequate room for mobile gantry assembly/disassembly?
-
Pre-planning meeting conducted before assembly/disassembly?
-
Competent person supervised assembly/disassembly?
-
Mobile Gantry selected is appropriate for load capacity and reach?
-
Mobile Gantry’s Wire Cable/Chain-fall/Chain Hoist/Slings Etc. has been inspected?
-
Mobile Gantry’s Mast/Beam/Nuts/Bolts/A-Frame Plate/Flat Plate/Casters Inspection?
-
Wheels are locked and in good condition?
-
Mobile Gantry setup on stable surface - Compacted soils, Drained, Firm?
-
Outriggers extended, if applicable?
-
Lift route planned to prevent worker exposure to falling loads?
-
Safety Measures In Place
-
Pre-Planning meeting
-
Non-Conductive tag lines in place (if applicable)?
-
Elevate warning lines, or
-
Barricades, plus
-
A spotter, or
-
Warning device, or
-
Qualified riggers present - Training verified and onsite?
-
Rigging equipment appropriate for load to be lifted?
-
Slings, spreader bars or chains checked for certifications?
-
Rigging inspected?
-
Tag lines attached (if applicable)?
-
Softeners used (if applicable)?
-
Qualified signal person present - training verified/documented (if applicable)?
-
Daily Pre-lift meeting conducted?
-
Competent person performed daily inspection and at each shift change?
-
Mobile Gantry Operator