Title Page
-
Site conducted
-
Conducted on
-
Location
Untitled Page
Wet plant areas
-
LTHW pressurisation unit pressure
-
Cold water booster set checks
-
Chilled water pressurisation unit pressure
-
Air handling units 4-5-6-7-10 Operation
-
Constant temperature pumps 1-2-3-4-5-6 operation
-
Variable Temperature pumps 7-8 operation
-
chiller pumps 1-2 operation
CHP Unit
-
Oil level checks
-
Total power generation (KWH)
-
Total run hours
Chlorine dioxide unit
-
Check operation of chlorine dioxide unit
-
Wetside chlorine dioxide unit
-
Dryside chlorine dioxide unit
Dry plant areas
-
Air handling units 1-2-3-9-11 Operation
-
Ground floor toilet extract operation
-
First floor toilet extract operation
-
Cold water booster set checks
Boiler Temperatures
-
Boiler 1 Temperature
-
Boiler 2 Temperature
-
Boiler 3 Temperature
-
Boiler 4 Temperature
Daily Water Temperature Checks
-
Wetside Calorifier Number 1
-
Wetside Calorifier number 2
-
Dryside Calorifier number 1
-
Dryside Calorifier number 2
-
Wetside cold water storage temperature
-
Dryside cold water storage temperature
-
Mains water temperature from plantroom checks
Reactive works
-
Check the CAL for reactive works
-
Check the BMS for faults and rectify