Information
-
Client / Site
-
Store Name & No.
-
Contract Number
-
Space Engineering Services - Project Manager
-
Tesco - SDM
-
Tesco - Main Contractor (Company)
-
Conducted on
Refrigeration Contract Finalisation Form
EQUIPMENT SUMMARY
-
PLANT MANUFACTURER
- SPACE ENGINEERING
- CONDENSING UNITS
- N/A
-
CONDENSER / GAS COOLER MANUFACTURER
- SEARLE
- RIVACOLD
- COOLERS & CONDENSERS
- N/A
-
CABINET MANUFACTURER(S)
- TEKSO
- KAPLANLAR
- VERCO
- N/A
-
EVAPORATOR MANUFACTURER(S)
- SEARLE
- RIVACOLD
- N/A
-
CONTROL / ALARM MANUFACTURER(S)
- DANFOSS
- CAREL
- N/A
-
LEAK DETECTION MANUFACTURER(S)
- DANFOSS
- CPC
- N/A
-
A/C MANUFACTURER
- MITSUBISHI HEAVY INDUSTRIES
- DAKIN
- SANYO
- MITSUBISHI ELECTRIC
- N/A
CABINETS & SALES FLOOR
-
CABINET INSTALLATION COMPLETE AS PER LATEST RETAIL LAYOUT & EXP SPECIFICATION? (INC PHOTOS)
-
NO WATER LEAKS PRESENT AND ABOVE FLOOR DRAINS TESTED TO CLIENT SPEC?
-
PUMP LOCATION MARKED AT BASE OF CABINET? (INC PHOTOS)
-
ALL CABINET NIGHTBLINDS & DOORS OPERATION TESTED AND LEFT FULLY OPERATIONAL?
COLDROOMS
-
CHILLER INSTALLATION COMPLETE AS PER LATEST RETAIL LAYOUT & EXP SPECIFICATION?
-
EVAPORATOR (CLEAR OF ICE)
-
CONTROL PANEL
-
DRAINAGE INSTALLATION / CONDENSATE PUMP (EARTH BONDED)
-
STRIP CURTAINS
-
FROZEN FOOD INSTALLATION COMPLETE AS PER LATEST LAYOUT & EXP SPECIFICATION?
-
EVAPORATOR (CLEAR OF ICE)
-
CONTROL PANEL
-
DRAINAGE INSTALLATION / CONDENSATE PUMP (EARTH BONDED)
-
RACKING
-
STRIP CURTAINS
REFRIGERATION PLANT
-
PLANT INSTALLATION AS PER LATEST LAYOUT & PLANNING DRAWINGS? (INC PHOTOS)
-
REFRIGERANT & OIL LEVELS VISIBLY CHECKED NO ALARMS PRESENT? (INC PHOTOS)
-
SAFE & SUITABLE WORKING ACCESS / LIGHTING PROVIDED? (IF NO THEN DETAIL WHO IS RESPONSIBLE)
-
PANEL / ACCESS KEYS SUPPLIED?
AIR CONDITIONING
-
A/C INSTALLATION IS COMPLETE AS PER PLANNING DRAWING & EXP SPECIFICATION? (INC PHOTOS)
-
SALES FLOOR / CASH OFFICE A/C FULLY OPERATIONAL? CONTROLS SET TO SPEC? (INC PHOTOS)
EXTRACT / VENTILATION
-
VENTILATION INSTALLATION COMPLETED BY SPACE ENGINEERING?
-
EMERGENCY CO2 EXTRACT INSTALLED AS PER DESIGN / SPECIFICATION & FULLY OPERATIONAL? (INC PHOTOS)
-
BAKERY VENTILATION INSTALLED AS PER DESIGN / SPECIFICATION & FULLY OPERATIONAL? (INC PHOTOS)
-
BULK STORE / BASEMENT VENTILATION INSTALLED AS PER DESIGN / SPECIFICATION & FULLY OPERATIONAL? (INC PHOTOS)
-
TOILET / BIN STORE VENTILATION INSTALLED AS PER DESIGN / SPECIFICATION & FULLY OPERATIONAL? (INC PHOTOS)
-
CASH OFFICE VENTILATION INSTALLED AS PER DESIGN / SPECIFICATION & FULLY OPERATIONAL? (INC PHOTOS)
-
NAME OF VENTILATION CONTRACTOR
ALARM / LEAK DETECTION
-
CO2 OR HFC INSTALLATION?
-
LEAK DETECTION INSTALLATION / SENSOR LOCATION COMPLETE AS PER LATEST DESIGN & EXP SPECIFICATION? (INC PHOTOS)
-
ALL STROBES / ALARMS TESTED AND FULLY OPERATIONAL?
-
ALL LEAK DETECTION HANDOVER CERTIFICATES COMPLETE AMD SIGNED BY STORE MANAGER?
-
LEAK DETECTION INSTALLATION COMPLETE AS PER LATEST DESIGN & EXP SPECIFICATION? (INC PHOTOS)
COMMISSIONING / SYSTEM LABELLING / O&M MANUALS
-
ALL PLANT, CABINETS, COLDROOMS & A/C HAVE BEEN SET / COMMISSIONED TO LATEST EXP SPECIFICATION?
-
ALL CABINETS, PLANT, COLDSTORES, LEAK DETECTION AND CONTROLS HAVE BEEN CLEARLY LABELLED AS PER SPECIFICATION? (INC PHOTOS)
-
ALL ALARM MONITORING EQUIPMENT IS FULLY COMMUNICATING LOCALLY? (INC PHOTO)
-
ALL ALARM / MONITORING EQUIPMENT IS FULLY COMMUNICATING REMOTELY WITH IMS?
-
HAVE IMS CONFIRMED THE COMPLETION DATE?
-
IS THE CONFIRMED DATE PRIOR TO STOCK DELIVERY?
-
HAS THE SDM / STORE MANAGER AND INCUMBENT CONTRACTOR BEEN MADE AWARE OF THE REMOTE ALARM STATUS?
-
HAS THE SDM / STORE MANAGER AND INCUMBENT CONTRACTOR BEEN MADE AWARE OF THE REMOTE ALARM STATUS?
-
PED LABLE TIE WRAPPED TO PIPEWORK AS IT LEAVES PACK? (INC PHOTO)
-
GAS CYLINDERS COLLECTED?
-
SCHEDULED COLLECTION DATE?
HANDOVER SIGNOFF
-
SPACE ENGINEERING PROJECT MANAGER
-
INCUMBENT REFRIGERATION CONTRACTOR
-
TESCO SDM (STORE DEVELOPMENT MANAGER)
-
TESCO MAINTENANCE
-
TESCO STORE MANAGER