Title Page
-
Document Reference
-
Conducted on
-
Prepared by
GHELAMCO
-
Name/Signature:
-
Date:
Curtain Wall Handover
Brackets
-
Check bracket is free of defects/damages.
-
Check if brackets are installed as per drawing. <br>Correct bolts and washers, line & level within acceptable tolerances, serrated washers engaged correctly with base brackets serration, use of correct shims)
-
Top M12 anchor bolts to be checked with torque ....Nm & sprayed.
-
Bottom M16 anchor bolts to be checked with torque Nm & sprayed.
Curtain Wall
-
Check the mullion and transom has been installed as per drawing.
-
Check aluminium flashing is installed.
-
Check EPDM is applied as per drawings & bonded as per manufactures standards.
-
Check rockwool has been installed as per drawing & adequately compressed into the opening.
-
Check the glass has been installed in the correct orientation. From inside: Kite mark bottom left.
-
Check glass for damages/scratches/dents.
-
Check if the pressure plates, screws and caps are installed as per drawing .
-
Check sealant is applied continuously & without damages/defects.
-
Is the CW protected as per RAMS.