Site Set Up

  • Is access to the site clearly signposted with site warning signage displayed? Directions, Company Sign, Warning Board

  • Does the site notice board have relevant safety information displayed, F10, Insurance, HSE Poster, Emergency Contacts, Fire Plan

  • Has office and welfare been established and is it suitable and sufficient for the on-going works; Toilets, Washing facility (Bowl), Hot water, Hand Towels, soap

  • Rest Room/Canteen/ Drying Room; Table, Chair, Kettle, Microwave, Drinking water & cup

  • Are office, toilet and welfare facilities clean, tidy and free from stored materials?

  • Has the electrics in the cabins been checked by a qualified electrician and a certificate of handover on site

  • Is the construction phase health and safety plan available, and specific to site

  • Are method statements and risk assessments in place and are method statements acceptable.

  • Are inductions being carried out prior to work commencement and records kept regarding attendance and competence.

  • Does the safety advisor require an induction and if so has one been given

  • Is the first aid box available and sited correctly and fully stocked

  • First Aid & Accident Management; First Aider on site, FAW certificate, Accident Book, Accident process, First aid Cover

  • Are appropriate levels of consultation being implemented i.e. Safety forums and tool-box talks and are records being kept. Toolbox talk with last month

  • Is the soil report on site

  • Is there an asbestos report on site

  • Is the site complying with any planning requirements

  • Is boundary fencing / security in place and secure preventing unauthorized access?

  • Fire safety; Fire Plan in file or displayed, Emergency Signage, Emergency Lighting, Fire Extinguisher, Assembly point<br>

  • Are the statutory /other registers being completed regularly and correctly e.g. in the last 7 days i.e. Scaffold, excavation, PUWER & LOLER.

  • Site deliveries; Safe unloading area, Method of unloading, Traffic control

  • Are appropriate permits to work being issued, controlled and cancelled?

  • Are site safety inspections being carried out as required and closed out by visiting management.

  • Are COSHH assessments available where necessary.

  • Are all sub-contractors approved

  • Have all sub-contractors’ RAMS been reviewed and assessed as sufficient to continue onsite

  • Is the Site Attendance record being maintained

  • Is there existing drawings or Pre-construction information on site

  • Have suitable signs and barriers been erected.

  • Have all services been identified and isolated

  • Has liaison with neighbours, affected by the works been implemented and is it being carried through.

  • Are unauthorized persons and general public segregated from the works

  • Is the traffic management plan being followed

  • Is the site waste management plan in place and up to date

Training

  • Do all operatives have CSCS cards

  • Do all plant Operators have CPCS cards

  • Has the Site Manager a SMSTS certificate of training

  • Do operatives have suitable training for activities taking place; abrasive wheels, manual handling

Safe Digging Proceedure

  • CAT used prior to excavating (CAT and Genny as required)

  • Permit to dig in place signed and dated by site manager

  • Have all known and located utilities been marked and found by hand

  • Is there a safe means of access (correct ladder or stepped sides)

  • Has the excavation been assessed by a competent person and properly supported or sides reduced by battering if likelihood of collapse

  • Is the area completely confined by barriers to prevent unauthorised access

  • If overhead lines present are there correct warning barriers and signage in place to GS6

  • Are materials stored at an adequate distance from edge of trench

  • Bucket changing area in place and being used for all machines

  • Is the excavator suitable for excavating and lifting

  • Have suitable barriers been put in place to prevent falls

Vibration

  • Is the equipment in use regularly maintained as per the-manufacturers data, is the site able to confirm this

  • Is the daily record sheets up to date and contain the correct information

  • Is there a chart displayed to inform the operatives of the vibration usage times

  • Has all the equipment being used been identified to the operative stating the maximum trigger times not to be exceeded

Confined Space access equipment

  • No damage to the rescue equipment

  • Equipment certificate of test in date

  • Equipment in use meets the lift requirement (harness fitted correctly, correct type of harness, lanyard connected to the hoist)

  • Tripod correctly positioned, winch locked in place correctly, top man able to operate equipment.

Confined Space Working In

  • Permit to Work filled out and filed

  • Is all signage and barriers in place as required to prevent unauthorised access

  • Means of communication established and checked if sufficient

  • All operatives carrying correct training cards for the task they are to perform

  • Is the correct procedure for the works being followed as relevant training

  • Is the gang correct size for the works minimum entry operative and top man

  • Is the gas monitoring equipment calibrated and set correctly

  • Has the gas monitor been checked prior to use

Manual Handling Tasks

  • Has the manual handling task been correctly identified (weight, size, sharp edges etc.)

  • Is the task being performed incorrectly after identification (manual handling kerbs when a curb lifter should be used)

  • Is there adequate risk controls in place ( job rotation, trolleys etc.)

  • Has there been training undertaken by the operative in lifting techniques.

Hazardous Chemicals (including fuel oil and grease)

  • Safe Storage location (away from ignition sources, away from storm drains and water courses)

  • Adequate spill containment (bunded area not overfull) and emergency procedure in place in case of fire /injury/spills

  • Safety Data sheets available on site

  • Sufficient correct P.P.E. for the work process being undertaken (asbestos, weed killing refueling )

  • Suitable storage containers (correctly marked with contents)

Personal Protective Equipment (P.P.E.)

  • Are all operatives wearing safety footwear, helmets and hi-viz tops

  • P.P.E. in good condition not altered or damaged reflective bands still highly visible

  • Is sun barrier cream available

  • Appropriate P.P.E. being used for the task being undertaken if additional hazards identified requiring specific P.P.E. (concreting , Tarmac laying)

Respiratory Protection

  • Are suitable masks available and being worn

  • If cutting is there sufficient suppression (local exhaust ventilation / water suppression)

  • Have the operative been face fitted with the type and design of filters being used within the last 12 months

  • Is the respiratory equipment in a serviceable condition ( Undamaged, clean, maintained)

Work Environment

  • Adequate noise control being deployed in areas where any operative will be exposed to greater than 85 dBA

  • Signage in place to warn other operatives or public to keep clear of hazardous operations

  • Housekeeping on the site to the required standard (lack of trip hazards, broken pipes cut steel contained within a protected area)

  • Adequate noise control being deployed in areas where any operative will be exposed to greater than 85 dBA

  • Signage in place to warn other operatives or public to keep clear of hazardous operations

Electrical Hazards

  • Safe electrical leads not damaged, and positioned to avoid trip hazard hazards and damage

  • 110V, or battery only

  • Electrical equipment either double insulated or power source RCD protected and earthed.

Environmental Hazards

  • Hazardous materials adequately contained (cement concrete washout area established ) away from drains and water course

  • Dust suppression system adequate and in use where required

  • Systems in place to prevent pollution or storm water drains and ditches (silt traps or other filtering medium in use)

Chapter 8 Works

  • Advanced signage in place

  • Pedestrian safety in place (barriers away from works or alternative safe routes displayed)

  • Traffic management plan in place agreed with the local authority and correctly implemented

  • Full type 3 P.P.E. worn by all operatives working in/adjacent to the highway

  • Supervisor with correct NSWA card checked the implication of the works prior to start<br>All operatives deployed in the works holding the correct NSWA cards<br>

Site Machinery

  • Have working plant been segregated from other site users

  • All statutory plant checks and inspections in place (12 month thorough examination certificate etc.)

  • All beacons working on active machines

  • Slews fitted with quick hitch mechanism as requested by clients

  • Are seat belts being worn on machinery fitted with them by the operative

  • Machine disabled whilst driver out of seat (keys taken) and left in a safe condition(handbrake applied )

  • Is machinery being driven responsibly (not speeding)

LOLER

  • Are the weekly LOLER check sheets being completed?

  • Is there a suitable Risk Assessment and method statement for lifting including excavators are they being followed?

  • Are moving loads supervised by Competent and trained Slinger / Banksman?

  • Is the Site Supervisor and operator aware of SWL for plant and accessories?

  • Is lifting equipment in good condition with certificates within 12 months available and non return valves or SWL displayed?

  • Are lifting accessories in good condition with certificates within 6 months available and SWL displayed?

  • Are weights available and known to Site Supervisor for materials and equipment, ie. Trench Box’s?

Comments

  • Has a copy of the written report been given to the Site Supervisor or Tempory Supervisor -( Enter Name in comments)

  • STATIC BOX CAN BE USED FOR ISO REFERENCING

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.