QUESTIONS
-
1. CDM - F1O and Statutory notices displayed?
-
2. Is the Principal Contractor prohibiting unathorised access to site with suitable double clipped Heras Panels; Timber Hoarding; Gates kept closed?
-
3. Is an accurate CPP in Place? Is it being formally reviewed on a regular basis?
-
4. Is the Principal Contractor providing suitable inductions?
-
5. Do all operatives have the correct competence / cards for the works being carried out? (CSCS, CPCS etc.)
-
6. Have RAMs been produced for all sub-contractor activities on site? Are they current and have all operatives been briefed on the safe systems and signed relevant briefing registers?
-
7. Are Face Fit Test Records held on site and up to date?
-
8. Are COSHH, Noise and Vibration assessments / details in place as required?
-
9. Are daily exposures to HAVS being recorded?
-
10. Are suitable manual handling arrangements in place / in line with manual handling assessments?
-
11.Has a documented Fire Risk Assessment been undertaken? Is the fire plan displayed?
-
12. Are fire drills practised regularly? (date of last drill)
-
13. Is there suitable means to raise an alarm? Is fire fighting equipment appropriate, visible and easily located?
-
14. Are there a sufficient number of trained first aiders?
-
15. Are sufficient first aid provisions provided? (Defibrillator; Eye Wash; First Aid kits)
-
16. Temporary Works - Are Temporary Works designs in place? Is there a Temporary Works register? Is the Register populated and up to date? Are Temporary Works being managed/is there a Temporary works co-ordinator on site?
-
17. Are permits to work in place? (dig/break ground, hot works, general work permit, confined space etc) Are they issued at the place of work by trained persons?
-
18. Are Thorough Examination Certificates held on site for mobile plant, lifting equipment etc.?
-
19. Are general plant and equipment (PUWER) and lifting equipment (LOLER) Inspections being undertaken and recorded at suitable intervals?
-
21. Are there suitable clean welfare facilities in place compliant with Schedule 2 of the CDM Regulations 2015?
-
22. Is the site aesthetically neat in appearance? Are there any issues likely to affect neighbouring residents or members of the public?
-
23. Are work areas tidy in appearance with suitable storage and housekeeping measures in place?
-
24. Are storage areas acceptable? (Bucket changing areas; Sealed spoil bunds; Covered materials)
-
25. Are all fuel cans located in the store container? Are the correct refueling practices being observed (including gloves and goggles)?
-
26. Is access suitable with sufficient clear walkways, these must be segregated from moving plant. (All walkway barriers must be clipped together)
-
28. Are plant exclusion zones being implemented on site ?
-
29. Are keys removed from the ignition on all items of plant?
-
30. Are excavation barriers in place? Are they set back from the edge and clipped / interlinked? Are they clipped together.?
-
31. Are cable avoidance tools held on site, are they calibrated and being used? (CAT & Genny)
-
32. Is correct PPE and RPE being worn and safe to use?
-
33. Is work at height access equipment suitable and being used correctly (mobile towers, ladders, step ladders, Hop Ups 600mm x 600mm)
-
34. Is the scaffolding safe and compliant?
-
27. Are Loading Bay gates kept closed when loaded with materials?
-
35. Are scaffold designs / compliance sheets held on site? Are handover certificates in place and mandatory inspections being carried out?
-
36. Is construction dust being suitably controlled?
-
37. Environmental: Are there any concerns regarding waste control and environmental protection (inc. pollution, contamination, wildlife, energy usage etc)
-
43. Is the site manager recording weekly site inspections?
-
38. Is Asbestos present and the correct survey in place, are operatives asbestos aware?
-
39. If applicable is an asbestos removal plan in place? is the ASB notice printed and held on site?
-
40. Is demolition work being carried out safely?
-
41. Are all demolitions operatives in possession of CCDO cards?
-
42. Is the Section 80 demolition notice held on site?