Information
-
Document No.
-
Audit Title
-
Site:
-
Department:
- CONTRACTOR
- MAINTENANCE
- OPERATIONS
- OUTAGE
- ENGINEERING
- TECH TRAINING
- LEADERSHIP
- SAFETY
-
Conducted on:
-
Prepared by:
-
Location:
-
Paired Observer:
Arc Flash & Energized Components: TVA-TSP-18.1021, TVA-TSP-18.1022
-
Have all employees performing any work on/with 480Volt through 500kV electrical power circuits completed required Arc Flash Hazard Training?
-
Comment:
-
Has a JSA been developed and used for work on 480V - 500kV electrical power circuits?
-
Comment:
-
Add media
-
Has a documented Pre-Job Brief been conducted with all responsible parties of electrical equipment?
-
Comment:
-
Add media
-
Is equipment being worked on adequately labeled in regards to Arc Flash information? (I.e. warning signs, calorie ratings, etc.)
-
Comment:
-
Add media
-
Has Arc Flash PPE been inspected for defects or damage?
-
Comment:
-
Add media
-
Has the proper Arc Flash Boundary been set up according to know arc flash potential?
-
Comment:
-
Add media
-
Have Live-Dead-Live checks been performed per TVA-TSP-18.1021 or Appendix G of TVA-TSP-18.1022? AC and DC voltage may need to be verified.
-
Comment:
-
Add media
-
Have requirements been met for qualified employees when working on/or near energized electrical equipment?
-
Comment:
-
Add media
-
Are 2 Qualified Employees present while work is performed on exposed energized electrical circuits per TVA-TSP-18.1021?
-
Comment:
-
Add media
-
Has it been determined that the work on electrical circuits & equipment can be done in a safe manner and is understood by each involved person?
-
Comment:
-
Add media
-
Have minimum approach distances to exposed energized conductors/parts been established and communicated?
-
Comment:
-
Add media
-
If necessary,have detailed temporary grounding plans been developed and approved by the applicable manager? (480Volt and Up)
-
Comment:
-
Add media
-
Are CPR Trained personnel readily available?
-
Comment:
-
Add media