High Hazard Lifts: TVA-TSP-18.802
-
Has a designated Crane Coordinator been selected for this lift?
-
Add media
-
Has the selected Crane Coordinator completed all required training for this designation?
-
Add media
-
Crane Operator, Rigger, and Signal Person all have completed appropriate training?
-
Add media
-
Have the Crane Coordinator, Crane Operator, Rigger, and Signal Person reviewed the lift plan?
-
Add media
-
Is the High Hazard Lift Plan documented on TVA form 17671?
-
Add media
-
Have items such as: load, stresses, support structures, lift, and swing paths been evaluated?
-
Add media
-
Has e mobile crane been verified by a 2nd party and documented?
-
Add media
-
Has the load drop zone been clearly identified and properly barricaded?
-
Add media
-
Has the rigging been inspected and is suitable for use?
-
Add media
-
Hand Signals will be used to communicate with the Crane Operator?
-
Add media
-
If using electronic communications of crane signals, electronic communication has been tested before operations begin?
-