Title Page

  • Conducted on?

  • Location:
  • Prepared by:

  • WO#

  • Service Territories

  • Inspection company:

Contractor/Crews:

Contractor/Crew

  • Contractor

  • Crew Leader

  • Crew Member:

  • Crew Member:

  • Crew Member

  • Crew member:

  • Crew Member:

Safety:

  • Are you inspecting safety today?

  • Is there a Crew Job Plan on Site?

  • Ask the Foreman why not.

  • OQ's checked?

  • Are everyone's OQ's up to date?

  • Tell us who is not up to date.

  • How was this issue resolved?

  • Proper span of control?

  • Traffic pattern set up properly?

  • What is missing?

  • Wheel chocks being used?

  • Is the job site set up properly?

  • Is PPE being worn?

  • What is missing?

  • Was crew excavating properly?

  • Please explain.

  • Is a spotter being used while excavating?

  • Please explain what the crew was doing that a spotter could not be used.

  • Are all bell holes / trench, coned off or being monitored for the safety of the public?

  • Fire extinguisher present when needed?

  • FR clothing worn when needed?

  • Is a CGI being used when needed ?

  • CGI Calibrated?

  • O2 Monitor being used?

  • O2 Monitor Calibrated?

  • Other Equipment Calibrated?

Excavation

  • Was excavation inspected today?

  • Competent Person Onsite?

  • Excavation Check List Completed?

  • Tabulated Data?

  • Was Shoring required?

  • Was shoring used?

Paperwork:

  • Work order packet onsite?

  • Did you ask the foreman why no packet is onsite.

  • What was the answer?

  • Were all forms completed correctly?

  • Were current gas construction standards available for viewing?

  • Where is the Gas Construction Standards book?

  • Did the crew get a standards book?

  • If no, then ask and write down why the foreman did not have one.

  • Work packet available to inspector within 24 hours?

  • One Call Ticket onsite?

  • Ask why the one call is not onsite.

  • All Permits Available?

Mains:

  • Are construction drawing on site and readily available?

  • Was 36” of cover achieved?

  • Proper Butt fuse process completed?

  • Were all existing utilities spotted?

  • Was 12” of separation from other utilities achieved?

  • Was main line valves installed and labeled properly?

  • Please explain.

  • Was pipe and fittings installed correctly?

  • Please explain.

  • Was proper sand bedding installed?

  • Was the ditch free of rock and debris?

  • Was proper padding installed?

  • Was tracer wire installed?

  • Please explain why no tracer wire was installed.

  • Was the ditch backfilled and compacted correctly?

  • Please explain.

  • Was caution tape installed correctly?

  • Was anode(s) installed correctly?

Casing:

  • Is a casing being used for mains or services?

  • Is the tracer wire cad welded to the casing?

  • Are insulators or centering cradles being installed?

  • Are end seals being installed?

  • Is a test station being installed?

Pigging:

  • Is main being pigged?

  • Are all pigs numbered?

  • Are all pigs accounted for?

  • How many pigs are lost?

  • Did pigs come out clean and dry?

Pressure Testing Mains:

  • Are pressure test forms on site?

  • Tell us why the foreman did not have a pressure test form.

  • Is a air cooler being used (if using air compressor) for pressure testing?

  • Are pressure gauges calibrated?

  • Is pipe temperature being monitored?

  • Was pressure test completed successfully?

  • What caused the pressure test to fail?

  • Is pressure test forms all filled out correctly?

Purging Mains:

  • Is a approved purge plan on site?

  • Is purge stack(‘s) installed properly?

  • Is the Purge Stack grounded properly?

  • Is nitrogen being injected properly?

  • Is CGI calibrated?

  • Is a CGI being used to monitor?

  • Was the purge successfully completed?

  • What went wrong.

Boring:

  • Is a HDD being used?

  • Is boring form on site and filled out?

  • Are all existing utilities exposed?

  • Please explain why existing utilites were not exposed?

  • Is there 12” of separation from drill head and the existing utility?

  • How close was the drill head from the existing utility?

  • Has drill head stopped rotation while crossing existing utility?

  • Explain why the drill head did not stop?

  • Was a weak link used for pull back?

  • Was the pipe examined at exit pit for damage?

Material integrity:

  • Is the proper material being used for the job?

  • Any damage to pipe?

  • Tell us what is damaged?

  • Any damage to fittings?

  • Please explain what fittings were damaged?

End Page:

  • Work Completed in accordance to all permits?

  • Inspectors Summary

  • Pictures

  • Inspector:

  • Inspector Signature:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.