Information
-
Conducted on
-
Supervisor
-
Construction Manager
-
Address
-
Job Number
-
Construction Type
-
Building Stage
- Site set up/set out
- Site cut
- Underground services
- Slab
- Frame
- Roof
- Fascia Gutter
- External Cladding
- Rough in
- Lock up
- Site clean
- Plaster
- Fix
- Paint
- Tile
- Floor coverings
- Fit out
- House Clean
- appliance install
-
comment
-
Contractor/Supplier on site
-
Photo of site
Site Information & Procedures
-
Are identified site specific hazards mentioned on the site sign eg: overhead power lines, gas lines, open trenches etc (has it been updated) <br>
-
Is the correct signage visibly displayed and details completed (eg. Keep Out sign, Contractor requirements and Builders Site sign with lot number)?<br>
-
Photo
Environment & Sustainability
-
Is mud control ie. crushed rock/recycled mix/mulch, required on site, has an adequate amount been ordered or does it require a top up
-
Are the building spoils separated and into allocated piles. eg: timber, plaster, brick and blow away material in cage/bin
-
Is the site bin/cage provided, accessible and not over flowing <br>
-
Is their adequate silt control on site eg: wash up pit, silt barrier, silt socks/sausages, brick barrier for sand
-
Noise is adequately managed on site minimise impact to neighbours and ensure site comms eg: radios, start times, generators, plant equipment
-
Photo
Site Conditions/Housekeeping
-
Cross over appropriately installed and maintained (if required)
-
Are the driveways, footpaths and nature strips clear of materials
-
Perimeter fencing appropriately installed and maintained (no missing panels/gates closed)
-
Slab back fill completed (Level ground and stable)
-
Clear access to front door, toilet, power board & bin/cage (is their a 1m clear zone around the build)
-
Is the site Trade ready (has the last trade completed all housekeeping so the next trade can complete their task internal & external
-
Is the toilet clean accessible and in correct operating condition with toilet paper
-
Date of last clean
-
Photos of crossover, footpaths, fences, housekeeping
Working at Height
-
Are site fall hazards (eg retaining walls) controlled and identified on site sign or SWMS
-
Photos
Roof Guard Rail and Condition & Access (High Risk)
-
Is there a barricaded drop zone for roof tilers spoils
-
Will the roof work endanger any people below
-
Roof guard railing in place for all roof work
-
Roof guard rail has identified access points with self closing gates minimum 2
-
The balcony guard rail is in place for all balcony works
-
Do all openings above 2m have guard railing eg. windows, balcony openings, internal voids etc.
-
Does the balcony and alfresco have sufficient structural support? (structural posts or accrow props for temp support)
-
Do all works near an open edge have sufficient guard rail height
-
Do stair risers have fall protection in place
-
Photo of - barricaded window frames , balconies, handrail, props where used etc...
Trestles
-
External/internal, are they fully planked, less than 2m in height, have solid stable footings, safe access/egress and a clear fall zone, correct locking pins?<br>
-
Are materials, equipment and personnel on trestles within their rated capacity?<br>
-
Photo - access/egress from trestles, work zone around trestles, not overloaded....
Ladders - Platform ladders recommended to be substituted for step ladders
-
Extension ladders in good condition, no damaged rungs, lean angle is not greater than 1:4 vertical ratio?<br>
-
Ladders secure/tied off/when accessing heights ladders extend 900mm past roof line?<br>
-
All types of ladders must be minimum industrial grade rated at a minimum 120kgs? (encourage the use of platform type ladders were applicable)<br>
-
Step/platform ladder fully open, both stays in good condition and on stable ground<br>
-
Are trades working off step ladders safely eg. not standing on top step and not over reaching to complete task (platform ladders recommended)<br>
-
Photo
Void Protection (High Risk)
-
Is void protection in place with compliance certificate (note the void protection is to be installed prior to installation of 1st floor walls and flooring)
-
Is the void trap door cover down whilst works occurring on 1st floor
-
Does the void protection provide safe access to upper level (configured correctly - minimise low clearance hazard
-
Photo
Hanging Bracket Scaffold
-
Scaffold has clearly identified and usable access and egress points to required work zone
-
Is the scaffold certificate in place and signed off (eg. scaff tag)?
-
Are the mid rails, top rails and lap boards of the scaffold in place?
-
Are scaffold decks clear of debris?
-
Photos
Trades
-
Have all persons on site completed an induction (check that all people on site have signed the sign in book/Epass
-
Do trades/suppliers on site, have a SWMS and is the trade operating in accordance with their SWMS
-
Does the trade have an adequate first aid kit and is first aid trained
-
Are all trades working sun smart
-
Photo
Electrical Tools & Equipment
-
Site Meter Box RCD tested monthly and main fuse locked & door closed (must be tested prior to first use or on installation)
-
Date last tested
-
If a generator is used, it should have an RCD fitted and not used indoors or in confined space
-
Electrical equipment (leads and tools) tested & tagged every 3 months and in date
-
Are electrical leads exiting through the bottom of the meter box
-
Are electrical leads raised up where practicable
-
Are leads to be no longer than 35 metres in length and in good working condition and heavy duty (no exposed wires and not double up)
-
Equipment has required guarding in place (eg. Drop saw/circular saw)
-
Drop saw and grinders have blade guard in place and blades in good condition (no missing teeth or chipped/broken cutting disk)
-
Mitre/Drop saw has dust extraction in place
-
Photo
Plasterers
-
All working at height risks are managed for plaster delivery eg: team lift via internal void, crane lift from external window/doors, plaster lifter in use
-
Where stilts are used, is area clean and free from trip hazards with a seat readily available
-
Internal housekeeping maintained during rough in and stop up
-
Does all sanding equipment have adequate dust control measure in place and are personal using appropriate PPE eg: dust mask, eye protection
-
Photo
Dangerous Goods or Hazardous Substances (High Risk Work)
-
Does the contractor have a Material Safety Data Sheet or Safety Data Sheet onsite with all products used as part of works eg. glues, resins, sealants, paints etc
-
Is there a MSDS or SDS on site for any products that my be stored overnight eg. glues, resins, sealants, paints etc
-
Photo
Items of Plant & Trenches (High Risk Work)
-
Does the work require an operator with a licence/certificate of competency (Excavators, skid steer, forklift, crane, boom pumps, spotters, riggers...)<br>
-
Is there a pre-start checklist & SWMS completed for the item of mobile plant
-
Warning devices operational (reverse beepers, flashing lights, horn)
-
Does the plant look fit for purpose or use eg: Earthmover quick hitches secured/pinned
-
Open screw pile holes and piers that are left unattended have covers preventing entry and identified on builders site sign
-
Large exposed trenches have fencing/barrier in place, trenches in minimum excess of 1.5m deep have been battered back and/or shored
-
Soil pile located minimum 1m from edge of trench or angle or repose which ever is greater
-
Is the site secured (pad locked, secured fencing) where exposed pier holes or trenches are left overnight
-
Photo
PPE - Personal Protective Equipment
-
The following PPE on site was not complied with:
-
Hi-visibility vest
-
Hat
-
Sunscreen
-
Hearing Protection
-
Sun Protective Clothing
-
Hard Hat
-
Safety Boots
-
Dust Mask
-
Eye Protection
Safety Chat with Contractors on Site - list points raised
-
Comments
-
Contractor present during discussion
-
Have you eliminated all potential risks from any other hazards identified on site that my affect work tasks
-
Supervisor completing Site Audit