Title Page

  • Weekly Plant Room Checks

  • JAR Tapestry Building

  • Conducted on

  • Prepared by

  • Location

DAILY WALK ROUND SHEETS

  • INSTRUCTIONS:
    -------------------------------------
    1) Start by selecting the Day of the week.
    2) Answer each item with the following:

    • ISOLATED
    • UNDERGOING MAINTENANCE
    • STANDBY
    • HAND OFF
    • RUNNING
    • FAULT
    • AUTO
    • OUT OF ORDER

    3) Fill out required fields and answer other questions as needed.
    4) To add a Corrective Measure, click on the paperclip icon then choose "Add Action". Provide a description, assign it to a member, set priority and set the due date.
    5) Complete the audit by providing a digital signature.
    6) Share your report by exporting as PDF, Word, Excel or Web Link.

    NOTE: Audit should be done on a daily basis

DAILY WALK ROUND SHEETS

  • WEEK NO

  • Day of the Week:

P2

  • LV SWITCHGEAR

  • LIGHTING CHECK

P3

  • CWB PUMP NO 1 (9B)

  • CWB PUMP NO 2 (9B)

  • CWB PUMP NO 3 (9B)

  • UV PANEL

  • LIGHTING CHECK

  • LEAKS

P4

  • UV PANEL

  • EXTRACT FAN<br>

  • LIGHTING CHECKS<br>

  • LEAKS

P5

  • MCC PANEL

  • LTHW P PUMP NO 1<br>

  • LTHW P PUMP NO 2<br>

  • LTHW SEC PUMP NO 1

  • LTHW SEC PUMP NO 2<br>

  • LTHW BUFFER VESSEL NO 1

  • LTHW BUFFER VESSEL NO 2

  • LIGHTING CHECK

  • LEAKS

GENERATOR

  • LIGHTING CHECK

P7

  • SPRINKLER

  • LIGHTING CHECK

  • LEAKS

CAR PARK

  • SUMP PUMP NO 1

  • SUMP PUMP NO 2

  • ENGINEER'S NAME AND SIGNATURE

  • COMMENTS:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.