Introduction
-
Blyth Offshore Demonstrator
-
Conducted on
-
Conducted by
Turbine
Inspection Record
01. PCM 1 Level. - Description of inspection area/component
-
Cable work
-
Check grounding on PCM 1 level and between platform and tower.
-
Transformer condition
-
Floor condition
-
Lighting condition
-
Wall paint condition
-
Other issues PCM 1 level.
02. PCM 2 Level. - Description of inspection area/component
-
Check cabinets, LSI for leaks corrosion on busbars etc.
-
Check cable work.
-
Check cooling water pump and hose/pipe connections for leaks
-
Check grounding on PCM level 2 and between platform and tower.
-
Floor condition
-
Lighting condition
-
Wall paint condition
-
Firefighting system or fire extinguishers condition
-
Other issues PCM 2 level.
03. PCM 3 Level. - Description of inspection area/component
-
Check cabinets, if possible inside as well
-
Check cable work.
-
Check cooling pipes water and air. if present.
-
Check grounding on PCM level 3 and between platform and tower.
-
Floor condition
-
Lighting condition
-
Aux transformer condition
-
Wall paint condition
-
Other issues PCM 3 level.
04. PCM 4 Level. - Description of inspection area/component
-
Visually, check sealing survival kit.
-
PCM crane condition
-
Visually, check conditioning unit.
-
Check grounding on PCM level 4.
-
Floor condition
-
Lighting condition
-
Wall paint condition
-
Other issues PCM 4 level.