Title Page
-
Circle Square, Manchester
Handover of Building to Commence the Works
-
Has the building been inspected and handed over by CBRE
-
Is there anything stopping planned works from commencing
Sign off of Dilapidation report
-
Has the Dilapidation report been received and accepted
Panel Removal
Panel, Cavity barrier and Substructure Removal
Panel reference x
-
Is there any visual damage or poor installation of panel prior to removal.
-
Are the panels dead fixed as per as built drawing X
-
Are the hanging hooks engaged correctly.
-
Is the insulation fixed as per manufacturers recommendations.
-
Is the substructure rails and helping hand brackets fixed as per as built drawing X
-
Are the cavity barriers fixed as per manufacturers recommendation
-
Is the Tyvek breather membrane bonded and sealed as per manufacturers guidelines
-
Are the EPDMs sealed and bonded to substrate adequately
-
Is the Sheathing board structurally sound and all joints sealed
-
Is the area wind and weather tight
-
Are there any other deviation from as built drawings
-
Inspection and Handover
Final Handover
-
Final Handover and acceptance by CBRE