Title Page

  • Circle Square, Manchester

Handover of Building to Commence the Works

  • Has the building been inspected and handed over by CBRE

  • Is there anything stopping planned works from commencing

Sign off of Dilapidation report

  • Has the Dilapidation report been received and accepted

Panel Removal

Panel, Cavity barrier and Substructure Removal

Panel reference x

  • Is there any visual damage or poor installation of panel prior to removal.

  • Are the panels dead fixed as per as built drawing X

  • Are the hanging hooks engaged correctly.

  • Is the insulation fixed as per manufacturers recommendations.

  • Is the substructure rails and helping hand brackets fixed as per as built drawing X

  • Are the cavity barriers fixed as per manufacturers recommendation

  • Is the Tyvek breather membrane bonded and sealed as per manufacturers guidelines

  • Are the EPDMs sealed and bonded to substrate adequately

  • Is the Sheathing board structurally sound and all joints sealed

  • Is the area wind and weather tight

  • Are there any other deviation from as built drawings

  • Inspection and Handover

Final Handover

  • Final Handover and acceptance by CBRE

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.