Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Project
-
Customer Service Area
-
Viscose/Job #:
-
VPL Manager Responsible:
-
Activity being undertaken:
General
-
Risk assessment completed & offered for review prior to allowing access to site
-
Hazardous Substance Register completed and related MSDS's on site
-
Plant & Equipment Register complete and on site
-
Measuring & Test Equipment Calibration Register complete and on site
-
Incident Report Register on site and up to date
-
VPL/Chorus ID Current and Available
-
PPE selected and used adequate for activity and environmental hazards present.
-
SWMS available, and current, for all high risk construction activities
Worksite Management
-
General work site set up
-
Vehicle parked safely
-
Manhole guards/ safety barriers / signage adequate and in place
-
Work area (incl footpaths & roadway) clear and free from debris, rubbish and obstruction.
-
Slips / trips hazards managed
-
Unattended excavations backfilled, plated or fenced.
Traffic Management
-
Does work site conform to approved TMP? Including unattended sites
-
Evidence of TTM training - TC/STMS on site
-
Pedestrian & vehicular traffic flowing freely & Safely
Electrical Safety
-
Electrical equipment tested & tagged (leads, RCD , power tools)
-
Appropriate use of and site set up (RCD plugged direct into 230v supply, leads protected)
-
EPR mat in use if in EPR Zone
Environmental Management
-
Global Tree Consent available on site
-
Site Specific Tree Plan on site and signed off by Authority
-
Noise / dust management
-
Spill response plan understood
-
Spoil containment & removal (including stock piles) managed
-
Stormwater sediment traps & gutter guards for water run-off in place
-
Concrete waste managed
-
Sediment Laden water management (Pump to grass or sucker truck)
Fibre Jointing
-
Set up - lighting
-
Set up - ergonomics
-
Sharps & off cuts managed
Customer Premises
-
Dog hazard adequately identified & managed
-
Work area neat and tidy
-
Internal power / gas located prior to drilling walls, floors and ceiling
-
Step ladder adequate for work
-
Confined ceiling / under floor hazards identified and managed
Work At Heights
-
Is the ladder appropriate for the job and in good condition?
-
Is the ladder in a safe working position and secured top and bottom (4:1)
-
Is ladder adequately supervised
-
Evidence that the pole been tested
-
Are safe clearances being observed
Hot Work
-
LPG bottle secured, if applicable
-
Use of flame retardant blanket / protection
-
Access to water (for immediate response to burn injury )
Confined Space Entry
-
Evidence of Confined Space Training
-
Evidence of Risk Assessment, Confined Space Entry training, First Aid training & Emergency Plan (Permit)
-
Standby person in use and Confined Spaces trained?
-
Barriers in use and adequate
-
Type 4 Gas Detector being used correctly & calibrated
-
Harness system in good condition, tag current and in use as required by emergency response plan
Asbestos
-
Asbestos Identified and Managed
-
Disposal process understood and adhered to
Excavation and Drilling
-
Excavation and drilling permit completed and available
-
Close approach consent obtained and available (when excavating near electrical poles)
-
All requirements of permit/s compliant
-
For excavation deeper than 1.5 meters, department of Labour notified
-
Adequate ground support system in place
-
Documented daily inspection of all ground support systems, for excavations over 1.5 meters available on site.
-
Spoil located a safe distance from the excavation
Plant Management
-
Operator holds required endorsement
-
Plant Prestart inspection completed and available for reference.
-
Plant has been inspected and approved for use on VPL Sites
-
Close proximity permit available on site when working within 4 meters of overhead lines
-
Suitable no-go zone established and maintained from plant
-
Required Corrective/Preventative Actions:
-
Agreed date of completion:
-
Person inspecting:
-
Person being inspected: