Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
Materials for work. / Details for work?
-
Does the material match material/submittals?
-
Does the foreman have the job site notebook in the immediate area? If no, stop work and get it for reference as needed.
-
Are the materials needed, in the right qualities for the work to be performed?
-
Are materials in good condition?
-
Does installer have a copy of detail drawing?
-
Does the drawing match the location and situation?
Site preparations
-
Is subbase ready?
-
Is dewatering in place? If no and needed check no. If no and not needed check NA.
-
Is area dry for proper installation of product?
Forms
-
Are forms installed in a manner that waterproofing can be installed properly?
-
Does the foreman/crew understand what side of the form the waterproofing goes on?
-
When ready, can the forms be removed without damaging the waterproofing?
Membrane installation
-
Is membrane laid out the right way up?
-
Is membrane overlapped 6” at the lateral seams?
-
Is the membrane overlapped 6” at the ends of the rolls?
-
Are lateral seams being rolled by manufactures roller after sealed together?
-
Are overlapping ends of rolls being primed with primer prior to gluing?
-
Are over lapping ends being rolled with manufactures roll after gluing?
-
Are overlapping area sticking as required? Test an area.
Steel / utility install before concrete pouring
-
Are all precautions being taken to protect membrane? Either by material or work practices.
-
Are damaged areas being reported so the can be repaired before concrete pouring?
-
Are damaged areas being repaired?
-
Are all pipe or steel penetration areas installed so a seal can be done for waterproofing?
Concrete pouring
-
Is waterproofing ready for concrete before pouring? Repairs, install properly,
-
Have you walked the entire pour area? Take pictures
Form removal
-
Have formers been removed so as to not damage waterproofing?
-
Are repairs done to damaged areas of the membrane?
-
Is the area going to be protected to prevent any damage to waterproofing? I.e. backfilling , water damage?
-
Who is responsible for protecting the area? Who was it handed off to?
-
Are the tie in ends in good condition for future tie ins?
-
Will the product be covered, before 60, to protect it from sun and weather damage?