Information

  • MEP Job Number

  • Location

  • Principal Contractor

  • MEP Site Supervisors

  • Prepared by

  • Date of Audit

Default Section

1. - Safety Documentation

  • 1.1 - Previous Inspection Records - Are these Present, Actioned and Filed with a close out form

  • Priority

  • 1.2 - Watkins HSEQ files - Are these on site, in order, completed and available to all operatives.

  • Priority

  • 1.3 - First Aid Provision - Is the First Aid box in the office, is it fully stocked and being managed?

  • Priority

  • 1.4 - Watkins Sub Contractor Audit - Is there a current Sub Contractor order on Evision, for those working currently on site

  • Priority

  • 1.5 - Watkins RAMS - Are these in place for all Watkins workplace activities currently being completed on site?

  • Priority

  • 1.6 - Sub Contractor Rams - Do all previous and current Watkins Sub Contractors on site, have a copy of their RAMS, signed by the operative, with Signed Approval from the HSEQ Department Attached.

  • Priority

  • 1.7 - Weekly Friday Pack - Has the most recent "Weekly Pack" been completed with relevant information attached

  • Priority

  • 1.8 - COSHH Assessments - 1.) Are these present for substances in use and briefed to operatives. - 2.) Are substances stored in suitable locations as outlined in COSHH assessments

  • Priority

  • 1.9 - HSEQ Notice Board - Is this displayed in a convenient location, with all relevant documents updated

  • Priority

2. - Site Conditions

  • 2.1 - Welfare Facilities - Are these suitable and sufficient for the volume of operatives on site

  • Priority

  • 2.2 - Cable management - Trailing leads and cables

  • Priority

  • 2.3 - Access / Egress / Footpaths Clear and suitable around all the site

  • Priority

  • 2.4 - Holes Voids & Trenches

  • Priority

  • 2.5 - Lighting levels adequate - 1.) Walkways and Pedestrians routes. - 2.) Plots and Work areas

  • Priority

  • 2.6 - Segregation of site Vehicles from Pedestrians with a current Traffic Management Plan in action

  • Priority

  • 2.7 - Housekeeping - 1.) Watkins Plots and Work areas are tidy and clear. - 2.) Principal Contractors site is clear and tidy

  • Priority

3. - Electrical

  • 3.1 - Electrical Safety Procedure: Is The Consumer Unit Live? (If yes go to question 3.2, if no mark as N/A)

  • Priority

  • 3.2 - Safe Isolation Lockout Procedure - Has the Watkins Procedure been implemented (Padlock, Stickers and Signage) - If NO, contact HSEQ Department immediately.

  • Priority

4. - Storage & Materials

  • 4.1 - Management of Watkins storage area and materials

  • Priority

  • 4.2 Management of Principal Contractor's Storage and Materials

  • Priority

5. - Plant & Equipment

  • 5.1 Working & Heights - As outlined in Watkins SSOW, is the working at heights equipment being used, suitable for the task in hand and been inspected on a 7 day period?

  • Priority

  • 5.2 Cutting Stations - Are in good working order, and have functioning lights, extraction and accessories attached

  • Priority

  • 5.3 - Rotating & Welding Machines - Are these in good working order and have. - 1.) Suitable Guards and Barriers attached. - 2.) Foot Pedal Activation. - 3.) Drip Trays or suitable COSHH control as outlined in RAMS. - 4.) Those using the machine are competent to do so. - 5.) Instruction Manuals are available to review. - 6.) PAT testing/Inspection/Maintenance is evident.

  • Priority

  • 5.4 - LOLER - Any equipment under this Reg ( Strops / Slings / Pallet trucks ect.) have been examined and inspected with appropriate tagging/certification in place

  • Priority

  • 5.5 - Principal Contractor Working At Heights protected? (Scaffold/Platforms/Lift Shafts)

  • Priority

  • 5.6 - Watkins work equipment is being used as per manufacturers guidance, and those in operation trained to do so?

  • Priority

6. - Fire & Emergency

  • 6.1 - Principal Contractor. - Fire Protection/Prevention Equipment suitably positioned across site, and emergency procedure's/fire plan is in place

  • Priority

  • 6.2 - Watkins. - Fire Protection/Prevention Equipment. - 1.) Hot Works permit is being completed by operatives. - 2.) 2x Fire Extinguishers are in the working area. - 3.) Work areas are free from hazardous or Combustible Material

  • Priority

7. - Occupational Health & Safety

  • 7.1 - Site - Noise - Suitable Control (Use the Noise Application)

  • Priority

  • 7.2 - Watkins - Dust - Are those creating or working with dust, using the correct tool attachments and have suitable "Respiratory Protection Equipment" on, with valid "Face Fit" certificate in place

  • Priority

8. - Individual Behaviour Safety Assessment

  • Name of individual

  • Trade

  • Employment Status

  • 8.1 - Watkins Induction completed

  • Priority

  • 8.2 - CSCS/ECE/JIB Skills Card available on site and relevant for trade

  • Priority

  • 8.3 - Is The P.P.E Appropriate For the Task Being Carried Out

  • Priority

  • 8.4 - Operative has signed RAMS and is working in accordance with them

  • Priority

  • 8.5 - Has the operative got the relevant competencies for the task being completed? (Manual Handling, Face Fit, Abrasive Wheels, etc)

  • Priority

9. - High Risk Activities

  • 9.1 - Are there any High Risk Activities currently being completed? (Roof works, Gas installation, Confined Spaces, etc)

  • Has HSEQ Department been notified?

  • Priority

  • 9.2 Are there any future lifts planned? If Yes, when is this planned for?

  • Priority

  • Audit Information Good Practice
  • Any Watkins operative, area or working procedure that shows good practice towards health and safety on site?

  • Information on the good practice witnessed.

  • Photo's of Good Practice

  • Any further issues
  • Further Issue. -

  • Priority

  • Watkins Supervisor

  • Watkins Project Engineer

  • I confirm that all matters requiring attention have been brought to the notice of, and discussed with the Site Supervisor/Foreman:-

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.