Title Page
-
Conducted on
-
Prepared by
-
Location
Tip Locations: T4 Unprocessed Material (As Dug Main Feed Stock Pile)
-
Has there been any deviation from the development scheme or tipping rules?
-
Any changes in general appearance or shape since the last inspection?
-
Are stockpiles above the 8m-stockpile height limit?
-
If loading from the stockpile has taken place is there still access onto the stockpile?
-
Are there any overhangs?
-
Is there any cracking along the top of the tip?
-
If cracks are present is any water entering them?
-
Is there any ponding of water behind the crest/on top of the tip?
-
Is there any lowering or settlement of the ground behind the crest of the slope?
-
Is there any evidence of bulging on the side slopes?
-
Has there been any slumping/movement at the toe of the tip?
-
Are access ramps too steep or unprotected?
-
Can any movement of the foundation adjacent to the toe of the tip be seen?
-
Is there any unexpected standing water accumulating at the toe of the tip?
-
Is there any uncontrolled discharge of water over the tip slopes causing scour?
-
Is there any water issuing from the tip?
-
Are there any obstructions to drainage blankets, drains, culverts or watercourses?
General
-
Did you note any other points of interest or concern (if yes please give details)?
-
List of Interests or Concerns
-
Any defects requiring Geotechnical Department / Specialist Notification?
-
Details of recommended remedial works / actions
Completion
-
Sign Off