Information

  • Project 项目

  • Conducted on 编写日期/时间

  • Document No. 文件编号

  • Prepared by 编制人

  • Location 位置

Site Details 工地信息

  • Project / site Name 项目/ 工地 名称:

  • 本报告模板供各工地质量员,质量主管使用,检查并评估各质量控制项是否符合要求,如有不符合项,用图片,视频和简短文件加以备注

Current site installation status 本周工地安装进度情况

  • Current site activity 本周安装作业内容

  • Photographs 进度照片

Incoming material 来货情况

  • Do you wish to report incoming material condition on this report?<br> 本报告是否包含来货情况

  • Material quality confirm to order<br>来货各质量指标符合订单要求

  • Packing as per requirement<br>包装符合要求

  • Properly storage<br>工地存放合理得当

In process quality control 制程质量控制

  • Cast-in / Bracket installation at this week?<br>本周作业是否包括埋件及牛腿安装?

  • Cast-in at correct position to true grid reference<br>埋件位置符合轴线图要求

  • Cast-in at correct position to slab reduced level<br>埋件垂直标高符合要求

  • Floor bracket in correct orientation<br>地台牛腿安装方向正确,无偏斜

  • Shimming do not exceed 10mm thick between concrete and bracket<br>牛腿和混凝土之间放置的垫片厚度不超过10mm

  • Serrated washers are orientated correctly<br>锯齿垫片正确咬合,定位

  • Spring washer are installed<br>弹垫安装,无遗漏

  • Min of 3 threads are above nut<br>螺栓紧固后,螺母距螺杆头部至少露3牙

  • Steel structure installation at this week?<br>本周作业是否包括结构钢件安装?

  • Steel structure installation as per drawing<br>安装符合图纸节点要求

  • Welding as per detail drawing<br>焊接符合节点图要求

  • Slag removed, weld primed as specified<br>焊渣清除,焊接处按要求做防护

  • Bolts, nuts and washers installed properly<br>螺栓,螺母及垫圈正确安装

  • Stick wall installation at this week<br>本周作业是否包括框架幕墙安装

  • Alum frame installed at right position<br>铝框架安装在正确位置

  • Sealant applied properly at transom / mullion join area<br>框架料连接位置防水胶施打正确

  • Glass setting block correct size, right position<br>玻璃垫块规格符合要求,放置位置正确

  • Glass in correct size and placed right side outward<br>玻璃安装室内外面正确,尺寸正确

  • Sealant applied properly<br>硅胶施打合格

  • Accessories installed correctly<br>配件正确安装

  • Panel installed at this week<br>本周作业是否包括单元板安装

  • Generally panel join gap in alignment<br>单元接缝对齐,符合要求<br>

  • Gutter join sleeve installed properly and correctly sealed<br>顶横料过桥安装合格,防水胶施打正确

  • 4-way join properly sealed and caulked<br>4向交叉点防水胶施打合格,充分固化

  • Bracket properly fixed, panel in the right level<br>牛腿固定合格,单元标高符合要求

  • No visible scratch or damage to coating extrusion and glass<br>喷涂型材和玻璃无目视划伤或损伤<br>

  • External cladding installed at this week<br>本周作业是否包括外墙包板安装

  • Sub-frame installed properly<br>附框安装正确,误差符合公差要求

  • Cladding surface finishing as per requirements<br>面板表面处理符合要求

  • Panel free from scratches/ dent at 3m<br>板片3米间距无目视划伤,凹坑等缺陷

  • Alignment checked to tolerance<br>接缝齐平,进出符合公差要求

  • Sealant applied properly<br>硅胶施打符合要求

  • Canopy / skylight installed at this week<br>本周作业是否包括雨棚,天窗安装

  • Sub-frame installed properly<br>附框安装正确

  • Surface finishing as per requirements<br>表面处理符合要求

  • Panel free from scratched / deformation at 3m<br>板片3米间距无目视划伤,变形等缺陷

  • Alignment checked to tolerance<br>接缝齐平,进出符合公差要求

  • Sealant applied properly<br>硅胶施打符合要求

  • Door panel installed this week?<br>本周作业内容是否包括门单元安装?

  • Door panel installed correctly<br>门单元安装正确,误差符合要求

  • Operation acceptable<br>运行顺畅,功能合乎要求

  • Hardware installed as specified<br>五金件正确安装

  • Panel free from scratches / dent at 3 m<br>单元3米间距无目视划伤,凹坑等缺陷

  • Flashing / interfaces/ silicone complete<br>档板,内饰面及防水符合要求

  • Pelmet, sills & side jambs installed this week?<br>本周作业是否包括窗帘盒,窗台板及收口料安装?

  • Installed at correct position and level<br>材料安装位置,水平符合要求

  • No severs scratch and damage to material<br>材料无严重划伤等缺陷

  • Fire safing installed this week?<br>本周作业是否包括防火层安装

  • Fire safing support installed properly<br>防火封堵底部托板正确安装

  • Fire safing support cleared of debris<br>防火封堵托板上的废渣清除干净

  • Safing insulation type as specification<br>防火棉规格符合要求

  • Fire safing material installed sufficiently<br>防火材料安装密实,符合要求

Field test 现场测试

  • Field water test performed this week?<br>本周是否有进行现场淋水测试?

  • Testing area 测试区域

  • Any water leakage ?<br>有无漏水?

  • Embed test performed this week?<br>本周是否有进行预埋件测试?

  • Testing location 测试位置

  • Pass the test?<br>测试通过?

  • Post-fix anchor testing this week?<br>本周是否有进行后补锚栓测试?

  • Testing location 测试位置

  • Pass the test?<br>测试 通过?

  • Site gutter test this week?<br>本周是否有进行现场排水槽防漏水测试

  • Test area 测试区域

  • Pass the test?<br>测试通过?

  • Lightning protection testing this week?<br>本周是否有进行避雷装置测试?

  • Test area 测试区域

  • Pass the test?<br>测试通过?

  • Weld test this week?<br>本周是否有进行焊接试验<br>

  • Test location 测试位置

  • Pass the test?<br>测试通过?

  • Any other test performed on site this week<br>本周现场是否有进行其他测试

  • Describe test item and result 简述测试项及测试结果

Site Quality problem Founding 工地质量问题发现

  • Quality issue
    质量问题

  • Issue
  • Description 描述

  • Correct action 处理意见

  • Photo 图片

General Comments 总结意见

  • Any further comments or recommendations ? 进一步意见或建议

  • Add any additional relevant photos
    添加其他相关照片

  • photo
  • Description 描述

  • photo 图片

Sign Off 签名

  • Name & Signature of PQM 项目质量经理(签名)

  • Name & Signature of PM 项目经理(签名)

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.