Title Page

  • Document No.

  • Audit title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Arrival on site

  • 1. Was the site safe, secure and hoarding closed off from the public?

  • 2. Did you observe good/safe working practices?

  • 3. Were all contractors wearing the correct PPE?

  • 4. Was the site induction suitable and sufficient to identify all hazards and risks?

H&S Folders

  • 5. Is Health & Safety folder(s) on site?

  • 6. Is the front page of the folder(s) signed by the H&S officer?

Contractor H&S Notice Board

  • Does the H&S notice board have the following documents and are they in date and relevant to the Site Manager: (inc photo)

  • 7.Public & Employers liability certificates?

  • 8. Fire action plan?

  • 9. Site rules?

  • 10. Local hospital information and map?

  • 11. Asbestos certificate?

  • 12. Health and Safety policy statement?

  • 13. SMSTS/SSSTS certificate?

  • 14. First Aid certificate?

Contractors Induction

  • 15. Have all contractors signed In/Out correctly in folder?

  • 16. Have all contractors had a site induction and are the forms signed?

  • 17. Have any Toolbox Talks taken place today? If so please specify.

  • 18. Has a young persons risk assessment been completed for anyone under 18 working on site?

  • 19. Have all contractors read the Asbestos report (Pre 2000 build) and Signed to confirm?

H&S Documents

  • 20. Is there a current copy of a relevant CSCS card for every contractor?

  • 21. Do all contractors have a current Asbestos awareness certificate?

  • 22. Are all contractors RAMS in date, relevant and signed?

  • 23. Are all contractors Indemnity insurance certificates present, in date throughout the project and for £10m for Public Liability & £5m Employers Liability?

  • 24. Do all contractors hold relevant and valid certificates to use specialist equipment?

  • 25. Is there an F10 on display if required?

Project Details

  • 26. Has the site Manager/Supervisor been briefed on the project and have copies of the following?

  • 27. Scope of works?

  • 28. Programme of works?

  • 29. Pre-construction phase plan?

  • 30. As built drawing (showing storage area)?

  • 31. Approved Final Signed off drawing?

Specification

  • 32. Is the Brand Specification being followed?

  • 33. Is the current Electrical spec manual in the folder?

Site set up

  • 35. Is there a Daily Hazard board displaying relevant up to date information?

  • 36. Is there a designated assembly point? Specify Location

  • 37. Is the accident book available?

  • 38. Have all contractors Electrical equipment been PAT tested?

  • 39. Are there adequate fire procedures in place including - Fire Bell, Fire signage and Fire extinguishers?

  • 40. Are the Fire extinguishers in date?

  • 41. Is there suitable/sufficient hoarding and signage around any working areas?

  • 42. Is there suitable/sufficient barrier fencing (Dbl Clipped) and signage around the skip? clipped?

  • 43. Is there suitable/sufficient barrier fencing (Dbl Clipped) and signage around the storage area?

MSA Forms

  • 44. Is a Daily Brief/conversation between Site Operations (SOM/Duty Manager) and GC taking place?

Completion

  • 46. Any additional comments?

  • Development Project Manager

  • Site Manager/Contracts Manager

  • On Site Duty Manager

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.