Information
-
Project Name
-
Project Number
-
Project Team
-
Business Area
-
Conducted on
-
Previous Wick Safety Limited Inspection Date
-
Further Wick Safety Limited Inspections required
Previous Report Date:
-
Have all previous reports internal/external been closed out
Audit Completion
-
Wick Safety Overview
-
Wick Safety Consultant
-
Project Representative:
Site safety
-
Access equipment/ scaffolding/ edge protection
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Clear Routes/Walkways/Housekeeping/Materials
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Plant, Machinery & Lifting Equipment/ Appliances (Test Certification)
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Fire appliances/fire alarm systems/drills/signage
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Others (electricity, confined spaces, lighting levels)
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Construction Manager close out section<br>Signature<br>Date
Public/Visitors/Operatives
-
Protection/Appearances
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Trip/Slip/Fall Hazard
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
PPE/RPE
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Road Street Works Management (is adequate control in place for deliveries)
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Has site been CCS registered (date)
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Construction Manager close out section<br>Signature<br>Date
Welfare/Health
-
Are there additional handwashing / hand sanitizer stations and signage indicating the locations?
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Is there an enhanced cleaning regime in place?
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Are social distancing rules being followed: at least 2 meters apart
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Is the Area project screening protocol in place? - 3 stage questionnaire and temperature checks for all subcontractors / visitors arriving on site
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Is respiratory protection (P3 type, face fitted) available
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Suitability/Cleanliness (offices, toilets, welfare facilities) (CDM 15 Requirements)
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
HAVS Control/ Manual Handling
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Notices/Posters
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Accidents
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Have any hazards/ Near Misses been recorded (QR Poster Reporting)
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
COSHH/Noise/Dust
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Asbestos
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Construction Manager close out section<br>Signature<br>Date
Management
-
RAMS
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Safety Records/Statutory Registers/Permits to Work
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Safety Reviews/Safety Tours/Communication/ Training Certification<br>
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Site Security/Site Entry/Safety Visible/Corporate Image<br><br>
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Environmental Issues/SWMP/Waste Disposal/Spill Kit
-
Action Code
- BP
- OBV
- A
- B
- C
- D
-
Construction Manager close out section<br>Signature<br>Date
Supply Chain
-
Mechanical
-
Electrical
-
Fire Alarm
-
Partitioners
-
Decorators
-
Client Direct
-
Other
Guideline to the scoring matrix
-
BP= Best practice (share within business)
A=. Same Day.
B=. Within 24hrs.
C=. Within 3 days.
D=. Within 7 Days.
Obv= Observation
Guide to scoring
10. = 'Best practice' approach to H&S. Going above & beyond company policy, taking initiative / lead to promote H&S
8. = Meets company policy
1-7 = Concerns
0. = Uncontrolled Risks/No Safe System of Work (SSOW)
80 - 100. Excellent approach to health and safety
70-80. Good safe systems of work and meets Company Expectations
60-70. Site just set up/ A better proactive approach to H&S required
<60. Standards below Company requirements