Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Safety Critical Components - Shall be in good condition or completed prior to work continuing
-
Pre-shift inspection complete
-
Gas monitoring system operational
-
Brake linkage and adjustment current and verified by operator
-
Derrick locking system inspected and flagged
-
SRL and harnesses inspected and in good condition
-
Guy line anchors installed correctly and adjusted
-
Grease inspect traveling blocks
-
Fans/air moving equipment functional and placed correctly
-
No Hydraulic leaks present
-
Energy control in place and filled out
Approach
-
Delineation and site control in place
-
Rig fall lane clear (2-4 and 8-10 o'clock)
-
Is Aera PowerLine Avoidance program adhered to (keyhole diagram 65' double, 35' single Appendix A)
-
Is the general housekeeping around the rig appropriate
-
JSA/CW paperwork filled out correctly
-
Daily/monthly inspection filled out and complete?
-
BOP drill data available?
-
All vehicles 1 ton or greater chocked
Rig cab
-
Housekeeping inside the cab acceptable
-
Breaks and accelerator pedal, free movement and in good condition
-
Doors, mirrors, glass, clean and in good condition
-
Gauges, mounting, operation in good condition
-
Decals, safety warning labels in place and in good condition
-
Look up and live sign hung on steering wheel (or rig mast)
Carrier
-
Free of cracks in welds or beams
-
Is machine guarding in place on all moving equipment
-
Is road gear disengaged and pinned
-
Are battery covers secure and is battery in good condition
-
Spools/drums, at least 3 full wraps, no damage or sharp edges, overall good condition
-
Main scoping rams free of leaks, hoses and fittings secured and in good conditions
-
Hydraulic fluid levels appropriate
-
Weight indicator present and installed correctly per SOP
-
Weight indicator wrapped with impact sleeve
-
Deadman anchor and cable retainer welds free of damage
-
Are leveling jacks pinned (If required) and pads available
-
Kill switches, marked, tested, and operational
-
Are the ground/ bond points checked and can the crew demonstrate
-
Escape rope secured and in good condition (Bowline Knot)
Operators platform/Controls
-
Are stairs and handrails/guards pinned and clipped
-
Sandline Deck secured and level
-
Are controls clearly labeled and accessible
-
Crown Out Floor Out (COFO) in use and demonstrated
Work floor
-
Are floor and railings clean, secure, pinned and clipped
-
Is TIW valve stored on the hanger in the open position
-
Tools stored and in good condition
-
Winch Line(s) in good condition tagged and free of damage
-
Rigging: Braided wire rope/nylon slings tagged and in good condition
-
Tubing rod tongs, oil levels, greased, and showing no damage
-
Tubing and rod tongs door installed and operational
-
Tong hanger and support in good condition
-
Hose and fitting free of leaks and in good condition
-
Two cables on tongs and stiff arm bolted and clipped
-
Proper back-up in good condition and functional
Traveling blocks
-
Bails, links, elevator, Cleve's and hook in good operational condition
-
Block bolts secured with keeper pins
-
Traveling blocks and sheaves, operational and in good condition
Derrick/Mast
-
Manufacturer's specifications plate installed and legible
-
Load guys correctly installed and flagged (check sag of line)
-
Board guys flagged and tensioned appropriately
-
Wind guys flagged and installed correctly (check sag)
-
Rod/tubing boards hinges, cables, secured and in good condition
-
Girts and braces in good condition
-
Ladders secured and in good condition (no major gaps)
-
Derrick hinge points, retainer pins, greased and in good condition
-
Crown sheaves greased and in good operational condition
-
Locking dogs at mast hinge point fully engaged (hand crank or automatic)
Blow out prevention equipment
-
BOP installed and the correct size
-
All bolts installed around wellhead
-
Bolts, rams, rings, related equipment installed and in good condition
-
Is the ground clamp attached and was it checked with an Ohm meter
-
Kill lines, blow down lines, and choke lines, installed, secured and in good condition
-
Accumulator lines marked and in good condition
-
BOP threaded accumulator hose connections secured and in good condition
Hydra-walk trailer
-
Good housekeeping on and around the hydra-walk
-
Wheels, chocks, lights in good condition
-
Securing straps in good condition
-
working deck (located near stairs) free of trip hazards
Pump
-
Are all gauges visible and in good condition
-
Has the relief valve been tested
-
Is the manifold pressure operating within its allowable limits
-
Are the hoses and hobbles in good condition and properly rated
-
Are hammer unions dressed and or replaced to minimize "mushroom" effect
-
Are all guards installed and in good condition
-
Fluid end free of leaks and all bolts and nuts in place
Accumulator Trailer
-
Relief valve operational and tested
-
Manifold pressure within allowable limits
-
Annular pressure within allowable limits
-
Accumulator pressure within allowable limits
-
Hoses inspected and in good condition, leak free
-
Green house gas log present and filled out
-
General house keeping acceptable
-
Controls clearly marked and functioning
-
Daily/monthly trailer inspection filled out and available
-
Nitrogen backup available and ready to use
-
Tires, wheel chocks, tow package, and lights in working order
Return Bin, 500 bbl tank, or Sand-X
-
Is the tank bonded/ grounded to an unpainted metal surface
-
Are hoses and connections secured with strap, pins and in good condition
-
Are there any cracked welds or leaks
-
Are the appropriate signs in place on the tank
-
Has a continuity check been performed
Tool truck
-
Are items properly secured for transport
-
Are the tools/ equipment in good condition
-
Are rigging components, stored or on location, in good condition
-
Are all of the features in place for safe driving (seat belts, lights, horn, etc.)
Miscellaneous
-
General housekeeping of the location acceptable
-
Is the Boatswain's chair, rescue kit, and emergency response materials in good condition
-
Are the Fire Extinguishers on location secured and in good condition
Final assessment
-
Pass/Needs repairs/Fail (no work until issues resolved)
-
Rig operator/supervisor
-
Auditor