Title Page
-
27 Great West Road Security Handover
-
Personnel on site
-
Handover completed on
-
Handover completed by
-
Document No.
On Coming Shift Handover
-
Is the oncoming shift wearing the correct JLL branded uniform?
-
Are the oncoming shift in possession of their own in date SIA Licence?
-
Have the oncoming shift signed the D.O.B to confirm that they are undertaking the shift?
-
Have the oncoming shift read and understood the previous handover?
-
Are all keys present?
-
Have the requested access passes been created?
-
Is the CCTV Working?
-
Are there any issues with the Access Control System?
Incidents
-
Have there been any incidents on the shift?
If so click the add incident tab
Incidents
-
What was the nature of the incident?
- Slips, Trips & Falls
- Theft
- Fire Alarm Activation
- Floods/Leaks
- Suspicious Persons/Vehicles
- Visitor Disturbance
- Access Control
- Vehicle/Property Damage
- Other
-
Has the incident form been filled out
-
Fill out incident report sheet
-
Input incident report number
-
Attach incident report to the email that you are sending for a handover.
Patrols
-
Fill out the following section when undertaken a patrol
Patrols
-
Control Conducted by;
-
Insert date and time of the patrol.
-
Where have you carried out a patrol?
- External
- Ground Floor
- 1st Floor
- 2nd Floor
- 3rd Floor
- 4th Floor
- 5th Floor
- 6th Floor
- East Stairwell
- West Stairwell
-
Have the bike racks been checked?
-
Upload photos of the bike racks
-
Inspect the bike racks thoroughly, checking the condition of the individual racks.<br><br>Has this been done?
-
Has the Fire Panel been checked?
-
Were there any faults on the fire panel
-
Type what the fault is with the fire panel, raise a job on elogbooks and include the job reference number below.
-
Were any health and safety issues noted? i.e. Fire risks, trip hazards etc
-
Are all doors secure and fire exits closed and unobstructed.
-
Were there any M&E issues, i.e water ingress, lights out etc
-
Confirm below what the issue is insert the job reference once a job has been raised by elogbooks.
-
Are stairwells clear and free of obstruction?
Off Coming Shift Handover
-
All information on patrols, incidents etc are logged in the D.O.B
-
Prep the coffee machine for the next shift
-
Reception desk is clear and tidy
-
All requested access passes made?
-
Reception seating area clear and tidy?
-
All Keys are present?
-
CCTV Checked and working
-
Access Control System is working?
-
Any additional comments
Declaration
-
This section is a declaration that the information provided in the preceding sections is of a true and accurate nature. Should any information be false you are accepting responsibility and may incur disciplinary action should dependent on the level of severity.
-
Tick the box to acknowledge that you understand the declaration statement above.
-
Tick the box to confirm that the information you have provided is of a true and accurate nature.
-
Signed
-
Date and Time of completion