Information
-
MSN SITE RECORDS
General information
-
Client Order Nr / reference
-
Main contractor Order Nr / reference
-
Subcontractor Order Nr / reference
-
Start date / time on site
-
Description of works
- pipe / rising main repair up to 1.5 m deep
- pipe / rising main repair over 1.5 m deep
- internal repair to manhole
- interceptor removal
- manhole replacement
- manhole construction
- flood mitigation works
- schedule 13 exceptional works
- subcontract priced works
- main contractor priced works
-
Any additional information available
-
Location of works
-
Works in highway
-
Road category (details from schedulers / TMA team)
-
Traffic management used
- chapter 8
- give and take
- lane closure
- 2 way lights
- 3 way lights
- 4 way lights
- stop / go
- road closure
- footpath closure
-
Is TMA a road closure
-
Duration of closure ?
-
Has diversion route been agreed with highway authority ?
-
Contact supervisor for guidance
-
Location of diversion route
-
Is the route suitable for the increased traffic volumes and size of vehicle ?
-
Contact supervisor for guidance
-
Are there site specifics ,eg school,bus stops,hospital,industrial estate,pedestrianised area,play park,etc. that will be affected by the increased traffic volume or type of vehicle using route
-
Contact supervisor for guidance
-
Impact of works on highway user
Risks to signing ,lighting and guarding
-
Weather
- wind ( ensure sand bags in place to secure)
- ensure signs clean and visible
-
Traffic
- Traffic too large for diversion route
- traffic speed
- traffic volumes
-
Vandalism
- local school
- pub
- night club
-
Other factors
-
Is TMA remotely controlled STOP / GO board operation
-
Reason stop / go selected
- highway authority specified
- location suited to manual control
- stop / go maintains traffic flow efficiency
- stop / go safest option
- remotely operated stop / go boards cannot be used
-
1. Correct SLG available on site
-
2. Distance between stop / go boards is less than 200m
-
3. Daylight hours and good visibility?
-
4. Unobstructed view of both approaches ?
-
5. Operator is no more than 100m from each board ?
-
6. Traffic flow is less than 800 vehicles per hour ?
-
Are all answers 1. to 6. yes ?
-
Do not use boards . Contact supervisor
-
Is TMA manually controlled STOP / GO board operation
-
Reason manual stop / go selected
- highway authority specified
- location suited to manual control
- stop / go maintains traffic flow efficiency
- stop / go safest option
- remotely operated stop / go boards cannot be used
-
1. Correct SLG available on site
-
2. Distance between stop / go boards is less than 200m
-
3. Both boards are fully illuminated during hours of darkness ?
-
4. Where operators are not in direct line of sight, 2 way radios are in use ?
-
5. Operator is in a position of safety and not inside the safety zone ?
-
6. Are traffic flows less than maximum flows stated in table on page 60 of the red book ?
-
7. For a single operated stop / go board , the site is less than 20m in length?
-
Are all answers 1. to 7. yes ?
-
Do not use boards . Contact supervisor
-
Is TMA a footpath closure
-
Duration of closure ?
-
Location of works
-
Have all alternatives to closing the foot way been considered ?
-
Contact supervisor for guidance
-
Has the work been planned to avoid peak / traffic sensitive times ?
-
Contact supervisor for guidance
-
Describe control measures
- pedestrian walkway of correct width
- pedestrian ramps
- correct signage for pedestrians
-
Describe monitoring arrangements when site unattended
- visual ,PHOTO and physical check of SLG before leaving site
- out of hours site visit
- planned site visits by supervisor
-
Impact of works on highway user
-
Are the works under a permit scheme ?
-
Are the permit conditions in place ?
-
Contact supervisor for guidance
-
Will the highway be temporarily obstructed for short periods
-
Control measures in place
- banksman directing pedestrians as required
- correct additional signage on site and used
- barriers moved and replaced as required
-
Are there site specifics ,eg. Commuter route,school,bus stop,hospital,industrial estate,farm,pedestrians,play-park, etc.
-
Control measures in place
- banksman directing pedestrians as required
- correct additional signage on site and used
- barriers moved and replaced as required
-
Will pedestrians,cyclists,horse riders be affected by the works? Do they have safe access through the works at all times ?
-
Control measures in place
- banksman directing pedestrians as required
- correct additional signage on site and used
- barriers moved and replaced as required
-
Will the site layout change during the works ?
-
Risks during changeover
-
Control measures in place
- banksman directing pedestrians as required
- correct additional signage on site and used
- barriers moved and replaced as required
Risks to signing ,lighting and guarding
-
Weather
- wind ( ensure sand bags in place to secure)
- ensure signs clean and visible
-
Traffic
- Traffic too large for diversion route
- traffic speed
- traffic volumes
-
Vandalism
- local school
- pub
- night club
-
Other factors
-
Control measures frequency of site inspection / visit
- next working day
- daily
- twice daily
- every 6 hours
- every 3 hours
- continuous
-
Any additional information available
-
PTD Required before start on works
-
PTD Signed
-
DO NOT START WORKS CALL SUPERVISOR FEEDBACK WITH PHOTO TO PROVE ATTENDANCE
-
Grid ref X
-
Grid ref Y
-
Address
-
Postcode
-
County
- Derbyshire
- Nottinghamshire
- Leicestershire
- Warwickshire
- Worcestershire
- Gloucestershire
Daily risk assessment
-
Is this first job of working day
-
COMPLETE VAN CHECKS BEFORE MOVING ON
-
Items checked and in working order / fit for use
- oil
- water
- fire extinguisher
- first aid kit
- hand cleaning facilities
- gloves
- tyre / wheel check
- tow bar
- lights
-
Are any items requiring attention
-
Items requiring attention
- oil
- water
- fire extinguisher
- first aid kit
- hand cleaning facilities
- gloves
- tyre / wheel check
- tow bar
- lights
-
Details of requirements and actions taken
-
Is vehicle safe to operate
-
DO NOT USE VEHICLE CONTACT MANAGEMENT FOR GUIDANCE AND INSTRUCTION
-
Do works involve use of plant and tools ?
-
Plant used
- P. power saw
- D. hand held breaker
- GD. gas detector
- TR. trench rammer
- K. kango breaker
- HB. hydraulic breaker
- ERB. electric road breaker
- G. generator
- M. microwave
- SP. submersible pump
- PP. petrol pump
- TRP. tripod and winch
- TP. plant trailer
- TT. tipping trailer
- RR. road roller
- T. transit van
- LS. lifting sling
- CS. chain sling
- DC. drop chain
- DL. d link
- GR 4" grinder
- LB line burner
- WP wacker plate
- MD mini excavator
- RT ratchet straps
- EL extension lead
- FE fire extinguisher gauge
-
Plant nr
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
-
Plant used
- P. power saw
- D. hand held breaker
- GD. gas detector
- TR. trench rammer
- K. kango breaker
- HB. hydraulic breaker
- ERB. electric road breaker
- G. generator
- M. microwave
- SP. submersible pump
- PP. petrol pump
- TRP. tripod and winch
- TP. plant trailer
- TT. tipping trailer
- RR. road roller
- T. transit van
- LS. lifting sling
- CS. chain sling
- DC. drop chain
- DL. d link
- GR 4" grinder
- LB line burner
- WP wacker plate
- MD mini excavator
- RT ratchet straps
- EL extension lead
- FE fire extinguisher gauge
-
Plant nr
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
-
Plant used
- P. power saw
- D. hand held breaker
- GD. gas detector
- TR. trench rammer
- K. kango breaker
- HB. hydraulic breaker
- ERB. electric road breaker
- G. generator
- M. microwave
- SP. submersible pump
- PP. petrol pump
- TRP. tripod and winch
- TP. plant trailer
- TT. tipping trailer
- RR. road roller
- T. transit van
- LS. lifting sling
- CS. chain sling
- DC. drop chain
- DL. d link
- GR 4" grinder
- LB line burner
- WP wacker plate
- MD mini excavator
- RT ratchet straps
- EL extension lead
- FE fire extinguisher gauge
-
Plant nr
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
-
Plant used
- P. power saw
- D. hand held breaker
- GD. gas detector
- TR. trench rammer
- K. kango breaker
- HB. hydraulic breaker
- ERB. electric road breaker
- G. generator
- M. microwave
- SP. submersible pump
- PP. petrol pump
- TRP. tripod and winch
- TP. plant trailer
- TT. tipping trailer
- RR. road roller
- T. transit van
- LS. lifting sling
- CS. chain sling
- DC. drop chain
- DL. d link
- GR 4" grinder
- LB line burner
- WP wacker plate
- MD mini excavator
- RT ratchet straps
- EL extension lead
- FE fire extinguisher gauge
-
Plant nr
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
-
Plant used
- P. power saw
- D. hand held breaker
- GD. gas detector
- TR. trench rammer
- K. kango breaker
- HB. hydraulic breaker
- ERB. electric road breaker
- G. generator
- M. microwave
- SP. submersible pump
- PP. petrol pump
- TRP. tripod and winch
- TP. plant trailer
- TT. tipping trailer
- RR. road roller
- T. transit van
- LS. lifting sling
- CS. chain sling
- DC. drop chain
- DL. d link
- GR 4" grinder
- LB line burner
- WP wacker plate
- MD mini excavator
- RT ratchet straps
- EL extension lead
- FE fire extinguisher gauge
-
Plant nr
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
-
Plant used
- P. power saw
- D. hand held breaker
- GD. gas detector
- TR. trench rammer
- K. kango breaker
- HB. hydraulic breaker
- ERB. electric road breaker
- G. generator
- M. microwave
- SP. submersible pump
- PP. petrol pump
- TRP. tripod and winch
- TP. plant trailer
- TT. tipping trailer
- RR. road roller
- T. transit van
- LS. lifting sling
- CS. chain sling
- DC. drop chain
- DL. d link
- GR 4" grinder
- LB line burner
- WP wacker plate
- MD mini excavator
- RT ratchet straps
- EL extension lead
- FE fire extinguisher gauge
-
Plant nr
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
-
Plant used
- P. power saw
- D. hand held breaker
- GD. gas detector
- TR. trench rammer
- K. kango breaker
- HB. hydraulic breaker
- ERB. electric road breaker
- G. generator
- M. microwave
- SP. submersible pump
- PP. petrol pump
- TRP. tripod and winch
- TP. plant trailer
- TT. tipping trailer
- RR. road roller
- T. transit van
- LS. lifting sling
- CS. chain sling
- DC. drop chain
- DL. d link
- GR 4" grinder
- LB line burner
- WP wacker plate
- MD mini excavator
- RT ratchet straps
- EL extension lead
- FE fire extinguisher gauge
-
Plant nr
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
-
Plant used
- P. power saw
- D. hand held breaker
- GD. gas detector
- TR. trench rammer
- K. kango breaker
- HB. hydraulic breaker
- ERB. electric road breaker
- G. generator
- M. microwave
- SP. submersible pump
- PP. petrol pump
- TRP. tripod and winch
- TP. plant trailer
- TT. tipping trailer
- RR. road roller
- T. transit van
- LS. lifting sling
- CS. chain sling
- DC. drop chain
- DL. d link
- GR 4" grinder
- LB line burner
- WP wacker plate
- MD mini excavator
- RT ratchet straps
- EL extension lead
- FE fire extinguisher gauge
-
Plant nr
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
-
Are any items defective in any way
-
Plant used
- P. power saw
- D. hand held breaker
- GD. gas detector
- TR. trench rammer
- K. kango breaker
- HB. hydraulic breaker
- ERB. electric road breaker
- G. generator
- M. microwave
- SP. submersible pump
- PP. petrol pump
- TRP. tripod and winch
- TP. plant trailer
- TT. tipping trailer
- RR. road roller
- T. transit van
- LS. lifting sling
- CS. chain sling
- DC. drop chain
- DL. d link
- GR 4" grinder
- LB line burner
- WP wacker plate
- MD mini excavator
- RT ratchet straps
- EL extension lead
- FE fire extinguisher gauge
-
Plant nr
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
-
ISOLATE IN STORE CABIN , RAISE DEFECT WITH MANAGER AND COLLECT REPLACEMENT
-
Plant used
- P. power saw
- D. hand held breaker
- GD. gas detector
- TR. trench rammer
- K. kango breaker
- HB. hydraulic breaker
- ERB. electric road breaker
- G. generator
- M. microwave
- SP. submersible pump
- PP. petrol pump
- TRP. tripod and winch
- TP. plant trailer
- TT. tipping trailer
- RR. road roller
- T. transit van
- LS. lifting sling
- CS. chain sling
- DC. drop chain
- DL. d link
- GR 4" grinder
- LB line burner
- WP wacker plate
- MD mini excavator
- RT ratchet straps
- EL extension lead
- FE fire extinguisher gauge
-
Plant nr
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
-
ISOLATE IN STORE CABIN , RAISE DEFECT WITH MANAGER AND COLLECT REPLACEMENT
-
Plant used
- P. power saw
- D. hand held breaker
- GD. gas detector
- TR. trench rammer
- K. kango breaker
- HB. hydraulic breaker
- ERB. electric road breaker
- G. generator
- M. microwave
- SP. submersible pump
- PP. petrol pump
- TRP. tripod and winch
- TP. plant trailer
- TT. tipping trailer
- RR. road roller
- T. transit van
- LS. lifting sling
- CS. chain sling
- DC. drop chain
- DL. d link
- GR 4" grinder
- LB line burner
- WP wacker plate
- MD mini excavator
- RT ratchet straps
- EL extension lead
- FE fire extinguisher gauge
-
Plant nr
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
-
ISOLATE IN STORE CABIN , RAISE DEFECT WITH MANAGER AND COLLECT REPLACEMENT
-
Do works involve working at height
-
Control measures required
- drag box / sheets extended 1m above ground level
- covers / fencing in place around open manholes
- 1m fencing to be used as additional edge protection
- fall prevention measures required ( harness and winch / fall arrest device)
-
Do works involve excavation<br>
-
Control measures required
- trench support as required / in place
- excavation battered / stepped back to safe angle of repose
- excavation to be inspected prior to each entry by competent person
Pre excavation checklist
-
Risk assessments suitable for work
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Public utility records available
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Pre or construction drawings available
-
CAT and genny function check completed
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
CAT And genny in calibration
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
CAT and genny survey completed to mark services complete with photo to confirm
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Suitable insulated tools available
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
No mechanical dig or use of picks, bars / spikes to be used within 500 mm of known services
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
PPE worn as per risk assessment
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Signing / lighting / guarding to company standards
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Are measures to protect public suitable
-
DO NOT START WORKS SPEAK TO SUPERVISOR
Permit to dig
-
CAT serial number
-
Genny serial number
-
Operatives trained and competent with use of CAT and genny
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Can operatives read and understand service drawings
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Are operatives aware of safe digging techniques
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Has risk assessment been completed
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
water mains present
-
Has utility been marked and location photographed
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Gas mains present
-
Has utility been marked and location photographed
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Electric mains present
-
Has utility been marked and location photographed
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Street lighting present
-
Has utility been marked and location photographed
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Telecom cables / ducts present
-
Has utility been marked and location photographed
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Other fibre optic cables / ducts present
-
Has utility been marked and location photographed
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Overhead services / obstructions present
-
Are protection measures required
-
Protection measures required
- goalposts erected
- sleeving installed by utility company
- additional Banksman position to control operations
-
Are protection measures in place
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
IF EXCAVATION OVER 1.2 m DEEP OR GROUND CONDITIONS DICTATE NON STANDARD APPROACH AND THE FOLLOWING ITEMS NOT IN PLACE OR CARRIED OUT NO WORKS TO PROCEED
1. Ensure excavation assessment / inspection report is completed as part of works records
2. Ensure adequate trench support or benching is in place
3. Ensure adequate edge protection is in place
Excavation assessment / inspection report
-
Depth of excavation Less than 500 mm deep score 0 Low risk 500 - 1200 mm deep score 1 Medium risk 1200 - 1600 mm deep score 2 High risk 1700 - 3000 mm deep score 3 If depth needs to increase beyond that originally planned then excavation support must be reviewed
-
Depth of excavation risk score A
-
Nature of ground Low risk score 1 Good ground, no recent disturbance ,soil moist earth or drained clay,one soil type consistent throughout. Medium risk score 2 Good ground, well compacted but possibly disturbed recently, soil type gravelly,shingle or dry sand,one soil type consistent throughout High risk. score 3 Poor ground,not well compacted,soil type dry earth,gravel with sand,wet sand or wet clay,more than one soil type If not possible to determine the soil type assume worst case scenario
-
Nature of ground. B
-
Ground water presence Low risk score 1 Ground water level below planned excavation depth Medium risk score 2 Ground water level encroaching at bottom of excavation High risk. score 3 Ground water level higher than excavation depth In addition to ground water also need to consider other factors such as proximity of watercourses or heavy rains (especially where it can run off land or down roads)
-
Ground water presence. C
-
Surcharge (side loadings) Low risk. score 1 No side loads anything likely to impact trench is far enough away Medium risk. score 2 Some surcharge , but deemed acceptable for depth of dig High risk. score 3 Side loadings likely to affect integrity of excavation Traffic particularly HGV's,traffic volumes,plant and equipment and spoil affect surcharge CONSIDER INCREASING DISTANCE BETWEEN TRAFFIC AND SIDES OF EXCAVATION
-
Surcharge (side loading) possibility. D
-
Personnel entering the excavation Low risk. score 1 Personnel entering the excavation at thigh height Medium risk. score 2 Personnel entering the excavation at chest height High risk. score 3 Personnel entering the excavation above head height Where personnel are entering into excavation below 500 mm enter a zero score
-
Personnel entering excavation. E
-
Total risk score A + B + C + D + E
-
Total risk score range
-
Site team to review need for excavation support Monitor conditions as work progresses
-
Advice required from competent person on need for excavation support / benching Monitor conditions as works progress
-
Excavation support required Monitor conditions as works progress
-
Can works be carried out safely ( if NO then name person informed and any actions taken)
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Responsible person
-
CAT SURVEY RECORD
-
Is it necessary to enter a confined space<br>
Confined space - permit to enter
-
Reason to enter
- sewer repair
- interceptor removal
- internal manhole repair
- manhole construction
- man entry for inspection
- man entry to remove object
- man entry to assist other contractor
- flood mitigation
- exceptional sewer relay
- exceptional rising main relay
- exceptional manhole cover replacement
-
Known and potential hazards
- gases
- services
- sewage
- flooding
-
Are all operatives confined space trained
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Have all operatives and any subcontractors received pre entry briefing on specific hazards and control methods
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Is a non entry rescue procedure in place
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Entry date
-
Equipment requirement checklist
- full body harness
- tripod / hoist
- signing and guarding
- ladder
- fall protection
- ventilation fan or air mover
- fire extinguisher
- self contained breathing apparatus
- air purifier
-
PPE Requirement checklist
- gloves leather
- gloves impervious
- gloves chemical
- gloves (needle stick protection )
- goggles
- face mask
- general work boots
- Wellington boots
- head protection
- gas monitor
-
Electrical isolation of work area required
-
Has isolation been completed
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Are specialist communication systems required
-
Has communication been established
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Is additional lighting required
-
Has lighting been established
-
DO NOT START WORKS SPEAK TO SUPERVISOR
-
Responsible person
-
Pre entry set up record
-
Are slips and trips possible
-
Control measures required
- all debris and materials to be cleared from designated walkways
- agreed area in place for material storage
- all spillages to be cleared immediately
-
Are public in close proximity of works
-
Control measures required
- all areas protected with double fencing
- fencing double clipped and placed to ensure it does not enter public areas
- resident letters distributed
- courtesy boards displayed
-
Overhead services (including sheathed / protected cables)
-
Control measures required
- apparatus owner required to attend site (if within 6m of overhead cables)
- goalposts / bunting required
- height restrictions in place on plant
-
Underground services
-
Control measures required
- cable drawings on site
- calibrated cable avoidance tools used to locate services prior to digging
- apparatus owner required to attend site
-
Works on the highway
-
Control measures required
- traffic management in place to highways requirement & chapter 8
- NRSWA Trained personnel on site
-
Substance spillage
-
Control measures required
- spill kit on site
- environment agency contact details in file
- drip trays used
-
Use of hazardous substances
-
Control measures required
- COSHH assessments on site with suitable and sufficient PPE
- Correct fuel storage in place
- Area assessed and clear of syringes / suspected asbestos containing materials
-
Works near water
-
Control measures required
- Life vest required (if within 2m of watercourse)
- life ring in place
- Edge protection in place
- Safety line required downstream
- Enviro - tags in place to monitor for contamination
-
Plant operation
-
Control measures required
- Trained personnel on site
- Plant inspected before use
- Banksman required for reversing operations / plant movements
- Quick hitch inspected and register completed
-
Works on live electrical equipment
-
Control measures required
- Trained personnel in place
- All live equipment isolated
- Permit to isolate issued prior to works commencing
-
Does work involve use of gas burner or asphalt mixer
HOT WORK PERMIT CHECKLIST All items must be in place
-
Ensure all items are in place
- trained person uninvolved with works to provide continuous watch
- combustible materials removed from work area
- floor area cleared of debris
- equipment for hot work has been checked and is in good repair
- gas cylinders properly secured
-
The following operatives have read , understand and agree to follow procedures of work detailed in this assessment
-
Have there been any visitors to site
-
All visitors to sign that they have read and understood the briefing
-
Visitor 1
-
Visitor 2
-
Visitor 3
-
Have there been any client instructions given
-
Instructions given
-
Pre start photos
WORK FEEDBACK
-
Were any other utilities services encountered in excavation ?
-
Gas
-
Depth
-
Number
-
Water
-
Depth
-
Number
-
Electric LV
-
Depth
-
Number
-
Electric HV
-
Depth
-
Number
-
Street lighting
-
Depth
-
Number
-
Sewerage
-
Depth
-
Number
-
Telemetry
-
Depth
-
Number
-
BT
-
Depth
-
Number
-
Traffic signals
-
Depth
-
Number
-
Finish date / time
-
Crew on site
- msn 1
- msn 2
- msn 3
- msn 4
- msn 5
- msn 6
- msn 7
- msn 8
- msn 9
- msn 10
- msn 11
- msn 12
-
Are works on a transferred sewer , manhole or cover
-
Description of works
- pipe / rising main repair up to 1.5 m deep
- pipe / rising main repair over 1.5 m deep
- internal repair to manhole
- interceptor removal
- manhole replacement
- manhole construction
- flood mitigation works
- schedule 13 exceptional works
- subcontract priced works
- main contractor priced works
-
Is essential additional information available
-
Contact supervisor for guidance
-
Is job a manhole cover replacement
-
Type of damage
- missing cover
- cracked / damaged cover
- polished surface
- rocking cover
- cover too low
- cover too high
- surfacing defective around cover
-
Manhole cover size
- 450 dia
- 600 dia
- 450 x 600
- 600 x 600
- 600 x 750
- 675 x 675
- 750 x 750
- 600 x 900
- 675 x 1220
- 900 x 900
- other
-
Size if not listed
-
Depth of cover
-
Work type
-
Manhole cover type
-
Is job a pipe or rising main repair
-
Cause of damage
- Collapse
- Blockage
-
Sewer type
-
Pipe size
- 75
- 100
- 150
- 200
- 225
- 250
- 275
- 300
- 325
- 350
- 375
- 400
- 425
- 450
- >450
-
Pipe material
- Clay
- Concrete
- MDPE/HDPE
- PVC
- Ductile
- Cast Iron
- Steel
- Fibre Glass
- Brick
- Asbestos
-
Length of repair
-
Is job an interceptor removal
-
Location of manhole
-
Removal type
-
Is job a manhole construction
-
Manhole construction
- mono section 600 x450
- mono section 750 x 600
- mono section 1200 x 750
- cast in situ
- 900 Pcc ring
- 1050 Pcc ring
- 1200 Pcc ring
- 1500 Pcc ring
- 1800 Pcc ring
- 2100 Pcc ring
- 2400 Pcc ring
- brick
-
Is job an internal repair
-
Repairs carried out
- re channel
- re bench
- pointing
- brickwork missing
-
Is job a flood mitigation job
-
Type of mitigation installed
- internal non return valve
- non return valve in new chamber
- sealed manhole cover
- vehicle floodgate
- pedestrian floodgate
- soak away and associated diversion of flows
- air brick replacement
- non return gulley installation
- re profile drive
-
Is job a schedule 13 item
-
Detail work type
- sewer repair
- interceptor removal
- internal manhole repair
- manhole construction
- man entry for inspection
- man entry to remove object
- man entry to assist other contractor
- flood mitigation
- exceptional sewer relay
- exceptional rising main relay
- exceptional manhole cover replacement
-
Is job a subcontract priced contract
-
Detail work type
- sewer repair
- interceptor removal
- internal manhole repair
- manhole construction
- man entry for inspection
- man entry to remove object
- man entry to assist other contractor
- flood mitigation
- exceptional sewer relay
- exceptional rising main relay
- exceptional manhole cover replacement
-
Is job a main contractor priced contract
-
Detail work type
- sewer repair
- interceptor removal
- internal manhole repair
- manhole construction
- man entry for inspection
- man entry to remove object
- man entry to assist other contractor
- flood mitigation
- exceptional sewer relay
- exceptional rising main relay
- exceptional manhole cover replacement
Reinstatement details
-
Reinstatement type
-
Length of reinstatement
-
Width of reinstatement
-
Thickness of surfacing
-
Depth of repair carried out
-
Surfacing material
- HRA
- SMA
- 10mm
- 6mm
- grass verge
- grass lawn
- PACO Patch
- hardcore
- Soil
- unmade
- concrete
- block paving
Customer satisfaction record
-
Is job on private
-
Is customer available to answer a few questions regarding works carried out
-
Was a pre start visit arranged ?
-
Were all appointments kept ?
-
Was the work completed on time
-
Was the work clearly explained ?
-
Were all staff polite and courteous at all times ?
-
Was the work carried out safely ?
-
Is all the area we have worked in left in good order ?
-
We're any complaints dealt with promptly ?
-
Would you recommend this company ?
-
Any other comments you would like recording
-
I confirm that the afore mentioned works were carried out with our full agreement and to our satisfaction
-
Reason for not signing
-
Additional information
Waste disposal details
-
Was any waste disposed of offsite
-
Method of waste disposal
Tankering / Overpumping details
-
Was any Tankering or Overpumping carried out
-
Tanker type 1
-
Tanker size
- 2000 gal
- 3000 gal
- 4000 gal
-
Nr of tankers
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
-
Hrs used
-
Tanker type 2
-
Tanker size
- 2000 gal
- 3000 gal
- 4000 gal
-
Nr of tankers
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
-
Hrs used
-
Tanker type 3
-
Tanker size
- 2000 gal
- 3000 gal
- 4000 gal
-
Nr of tankers
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
-
Hrs used
-
Pump 1 type
-
Pump size
-
Nr of pumps
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
-
Hrs used
-
Pump 2 type
-
Pump size
-
Nr of pumps
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
-
Hrs used
-
Pump 3 type
-
Pump size
-
Nr of pumps
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
-
Hrs used
Location plan / photos / sketch ( as required)
-
Site address
-
Location and general feedback photos
-
Draw sketch plan (if needed)