Shelving

  • When totally finished go thru the cabinet and visually check that all is done correctly.

  • Take a photo of cabinet so as to ID for reference

  • Screw self tappers into the bottom frame , 2 each side <br>CT Cabinets only. <br>

  • Check shelf layout with plan , ensure shelves are in correct position <br>

Patch Panels and 15 Way Frame

  • Wire 16 Port Patch Panel with 25 pair and 10 pair .<br>Wire the first 6 Ports of the Patch Panel using the 25 pair cable. <br>Wire the last 10 sockets ,using the 10 pair on pair 4&5 only.

  • Install 15 Way Krone Frame

  • Install the wired 16 Port Patch Panel.<br>Run 25 pair / 10 pair around the back of 15 way frame. And terminate back to "B " side.<br>Ensure Velcro is wrapped around sharp edge.

  • Run Cat 5 from 15 Way frame to 3 rd bottom shelf and fit off a Mode 3 Socket . White 2 - Blue 6 ~~~~~~~ White 1 - Orange 5<br>Ensure it is wired to position 27,28,29,30

  • Install all equipment into bare cabinet these include:-<br>2 x 24 Port Panel <br>Shelving <br>Cable Management <br>

  • Ensure that you allow a 3 rd. Patch Panel to make up 72 Port Patch Panel <br>Cover up this position with a Blanking Plate

  • Label 16 Port Patch Panel.

  • Label 2 nd. Patch Panel 25 to 48

  • Make up record book and fit wire and lug ,install on front door.

  • Jumper 15 Way frame as per Record Book.

  • Test all jumper with Tone set

  • Reinstall front door and side doors. <br>

Power Rails

  • Install 2 x 10 Way Power Rails.<br>Make sure these power are installed in the correct position.<br>Ensuring that they clear any equipment :- follow the shelving layout

Miscellaneous

  • Run 3 mtr Pink Patch Lead from the Second bottom shelf to Switch position

  • Make up stainless steel wire for Record book and front door key.

  • Ensure Key Safe is Programed up to Store Number <br>Ensure override key is inside.<br>Attach key safe to bottom cable management.

  • Install earth bar

  • Tape key to front door.

  • Pack with bubble wrap first ,cardboard then shrink wrap.

Final Check

  • Have a final visual check of the cabinet.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.