Title Page
-
Conducted on
-
Prepared by
-
Location
-
Superintendent Name
-
Project Manager Name
Jobsite Inspection
Job trailer or construction office
-
Does the job have the required safety essentials? AWAIR & RTK Programs?
-
Are weekly toolbox talks being conducted?
-
Are construction barricades and construction signage erected to warn of potential hazards?
-
Is there a heater in the portable toilet?
Concrete/Masonry (Subpart Q - 1926.700)
-
Concrete/Masonry (Subpart Q - 1926.700)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=b82849dbe6eb55c8710eca668249ba2f&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_1700 -
Are all impalement hazards eliminated?
-
Are precautions being taken when employees are exposed to silica? How are you controlling the exposure?
-
Is the guard on the concrete mixer closed?
Confined Space (Subpart AA - 1926.1200)
-
Confined Space (Subpart AA - 1926.1200)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=b82849dbe6eb55c8710eca668249ba2f&ty=HTML&h=L&mc=true&n=sp29.8.1926.aa&r=SUBPART#se29.8.1926_11200 -
Has the atmosphere been tested for toxic gasses? (Carbon monoxide, etc.)
-
Is a permit required before entry into the confined space?
-
Have all employees entering the confined space been trained?
Cranes (Subpart CC - 1926.1400)
-
Cranes (Subpart CC - 1926.1400)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=b82849dbe6eb55c8710eca668249ba2f&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_11400 -
If performing craning operations, is your operator certified?
-
Has a daily inspection been performed on the crane and is there an annual inspection document/sticker available?
-
Is the swing radius of the crane barricaded?
-
Rigging equipment in compliance?
-
Are all other trades out of the area when craning operations are being performed? Area barricaded?
Electrical Safety (Subpart K - 1926.400)
-
Electrical Safety (Subpart K - 1926.400)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=b82849dbe6eb55c8710eca668249ba2f&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_1400 -
Are GFCI's being used on all temporary power and frequently tested?
-
Is temporary panel in compliance? No openings?
-
Are all extension cords in compliance and not exposed to sharp edges and vehicle traffic?
-
Are all temporary lights fully caged to prevent accidental breakage and are they secured properly?
Fall Protection (Subpart M - 1926.500)
-
Fall Protection (Subpart M - 1926.500)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=b82849dbe6eb55c8710eca668249ba2f&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_1500 -
Is there a documented fall protection plan in place for roofing activities and is it being followed?
-
Are all employees exposed to fall hazards of 6' or more protected with fall protection?
-
Are all floor holes 2" or larger covered, labeled and secured?
-
Are employees who are wearing PFAS properly trained in how it works?
-
When guardrails are used for fall protection are they at the right height and capable of withstanding a force of at least 200 pounds?
Fire Extinguishers (Subpart F - 1926.150)
-
Fire Extinguishers (Subpart F - 1926.150)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=b82849dbe6eb55c8710eca668249ba2f&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_1150 -
Are fire extinguishers on site and are they being inspected monthly?
-
Do we have a fire extinguisher for every 3000 square feet of the protected building and located not more than 100 feet from each other?
-
Are fire extinguishers placed by egress/EXIT doors?
Flammable and compressed gas cylinders (Subpart F - 1926.152)
-
Flammable and compressed gas cylinders (Subpart F - 1926.152)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=b82849dbe6eb55c8710eca668249ba2f&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_1152 -
Are approved flammable containers labeled as to contents?
-
Are compressed gas cylinders capped and secured in an upright position?
-
Are LP tanks stored outside when not in use?
HAZCOM - Right to Know (Subpart D - 1926.50)
-
HAZCOM - Right to Know (Subpart D - 1926.50)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=b82849dbe6eb55c8710eca668249ba2f&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_150 -
Are safety data sheets (SDS) readily available for hazardous chemicals?
Housekeeping (Subpart C - 1926.25)
-
Housekeeping (Subpart C - 1926.25)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=50f936778209187a16b413214e3e2095&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_125 -
Housekeeping being conducted and aisles free of debris?
Ladders (Subpart X - 1926.1053)
-
Ladders (Subpart X - 1926.1053)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=50f936778209187a16b413214e3e2095&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_11053 -
Are step ladders in good condition and being used for their designed purpose? Opened up and not leaning against a wall?
-
Are extension ladders in good condition and if used for access, do they extend at least 3' and are they secured?
Machine Guarding (Subpart I - 1926.300)
-
Machine Guarding (Subpart I - 1926.300)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=50f936778209187a16b413214e3e2095&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_1300 -
Are machine guards in place on all rotating/reciprocal tools and equipment?
-
Are all hand tools free from visible defects and in good condition?
Motor Vehicles & Equipment (Subpart O - 1926.600)
-
Motor Vehicles & Equipment (Subpart O - 1926.600)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=50f936778209187a16b413214e3e2095&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_1600 -
Are all employees exposed to or working adjacent to moving motor vehicles wearing at least a class 2 high visibility garment?
-
Are daily inspections being conducted on ALL motorized equipment and are operators trained and authorized by their employer?
-
If an aerial lift basket is used on a construction forklift, is it the right size (does not exceed more than 10" of the wheelbase), secured and fall protection provided?
-
Is the equipment current with annual inspection?
-
Are chains across gate in scissor lifts?
-
Seatbelt being worn?
-
Is audible alarm working?
PPE (Subpart E - 1926.95)
-
PPE (Subpart E - 1926.95)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=50f936778209187a16b413214e3e2095&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_195 -
Is PPE being worn and in compliance with site and OSHA requirements?
Scaffolding (Subpart L - 1926.450)
-
Scaffolding (Subpart L - 1926.450)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=50f936778209187a16b413214e3e2095&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_1450 -
Has the scaffold been erected/dismantled by a competent person?
-
Have all the employees working on the scaffold had user training? Are they aware of the hazards?
-
Is the scaffold bearing on baseplates and mudsills and is it level?
-
Are ALL of the open sides and ends of the scaffold barricaded for fall protection?
-
As a best practice, is the scaffold tagged "ready for use" or "not ready for use"?
Silica (Subpart Z - 1926.1153)
-
Silica (Subpart Z - 1926.1153)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=50f936778209187a16b413214e3e2095&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_11153 -
Has exposure to silica been controlled and monitored?
Stairways (Subpart X - 1926.1050)
-
Stairways (Subpart X - 1926.1050)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=50f936778209187a16b413214e3e2095&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_11050 -
Is there a handrail or stair rail along each unprotected side or edge?
-
Are stairs with 4 or more risers or rising more than 30" equipped with a handrail or stair rail?
-
Is the temporary handrail at least 3"from the wall?
-
At points of access higher than 19", is a step, walkway or ramp being used?
Steel Erection (Subpart R - 1926.750)
-
Steel Erection (Subpart R - 1926.750)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=50f936778209187a16b413214e3e2095&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_1750 -
Has a site specific steel erection plan been developed and being followed?
-
Has a site specific SEQUENCING plan been developed and is it being followed?
-
Are all other trades out of the area and is the area barricaded while performing steel erection?
-
Has a fall protection plan been developed and discussed with erection crew?
Trenching/Excavating (Subpart P - 1926.650)
-
Trenching/Excavating (Subpart P - 1926.650)
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=1&SID=50f936778209187a16b413214e3e2095&ty=HTML&h=L&mc=true&r=SECTION&n=se29.8.1926_1650 -
Is there a competent person on site while performing trenching/excavating?
-
Is there adequate cav-in protection for employees working in trenches/excavations greater than 5' in depth?
-
Is there an access/egress ladder in the trench/excavation (4' or deeper) and is it within 25' of the workers?
-
Are the spoil piles back at least 2' from the face of the excavation?
-
Are all audible alarms in operation on earthmoving equipment and loud enough to hear?