Title Page
-
Site conducted
-
Audit Title
-
Project Name
-
Conducted on
-
Prepared by
-
Location
QA 001
Fundermax facade
-
undefined
undefined
-
-
Project Number:
-
Issued to:
-
QA Sheet No:
-
Elevation:
-
Level:
-
Comments:
STRUCTURE
-
Handover documentation been issued by Main Contractor?
-
Personnel
- Installer
- A2O
-
Gridlines and datums marked.
-
Personnel
- Installer
- A2O
Storage
-
Store the board material in dry protected conditions, never stacked more than two pallets high<br>
-
Personnel
- Installer
- A2O
Panel/ply sub-straight
-
Check sub-straight is lined in accordance with construction issue drawings and lines through with interfacing finishes <br>
-
Personnel
- Installer
- A2O
-
Check that the composite panel joints / ply edges have been flashed and sealed in accordance with design specification.<br>
-
Personnel
- Installer
- A2O
-
Check composite panels / ply sheets are flush with one another
-
Personnel
- Installer
- A2O
Insulation sheets
-
Insulation sheets correct and installed to design specification.
- Checked
- Hold
-
Personnel
- Installer
- A2O
-
Insulation sheet joints sealed in accordance with design specification.<br>
-
Personnel
- Installer
- A2O
Aluminium Support System
-
Check all aluminium support components are accounted for on delivery, in accordance with schedules
-
Personnel
-
Check all aluminium support components are set out in accordance with A2O design
-
Personnel
-
All aluminium support is fixed in accordance with A2O design to enable full free movement of the support as manufacturers recommendations
-
Personnel
Sika Tack adhesive system
-
Check that all surfaces to be adhered have been primed with Sika Tack primer and that no residue is left on the panel face.
-
Personnel
-
Check that panel setting out is correct and in accordance with design specification.
-
Personnel
-
All interface zones are in accordance with design specification
-
Personnel
Completion
-
Installer Signature:
-
A2O Signature:
-
Client Signature: