Title Page

  • Location
  • Names of the Service Team being assessed.

  • Conducted on

  • Prepared by

Manager Section

  • Do all employees and contractors on site have the latest ABB emergency contact information?<br>

  • Have arrangements for welfare of the workers on site been verified? (toilets, potable water, hand washing, clean area for breaks and eating)<br>

  • Was contractor/subcontractor evaluation done per ABB policy?<br>

  • Are ABB OHS requirements agreed by contractor or subcontractor in writing? <br>

  • Are contractors aware of ABB's Code of Practice for Safe Working and have they received a copy of ABB's COP Manual?<br>

  • Does the site supervisor/manager check the working conditions and supervise the behavior of contractor employees?<br>

  • Are all field engineers trained in First Aid/CPR?

  • Are working hours properly controlled to prevent fatigue and is travelling to and from the site considered?<br>

  • Is Risk Assessment(RA), Job Hazard Analysis(JHA) or Job Safety Analysis(JSEA) done properly ? <br>

  • Are hazards and near miss incidents reported properly?<br>

  • Do Service Managers conduct Safety Observation Tours (SOT's) regularly as required?<br>

  • Is PPE monitored and is there a system in place to replace worn or damaged PPE when needed and in a timely manner?

  • Are ABB Expatriate Workers on site and is the host Country HSE organization aware of their presence on site?<br>

Manager Section - Electrical Safety

  • Is a PICW (Person in Charge of Works) in place? Is a PICW assigned for all jobs?<br>

  • Are workers trained in the Seven Steps, ABB’s electrical safety rules, and arc flash for those exposed to electrical risk? <br>

  • Are documented pre-job briefings or STOP Take 5 taking place communicating a safe system of work prior to each shift?<br>

  • Is the project and/or electrical safety champion available from LBU to support project safety?<br>

  • Is electrical competency assessed and monitored where required?<br>

  • Are arc-flash risk assessments that includes incident energy levels, arc-flash boundary calculations, and PPE category ratings availble before the job starts? If not available, has the ABB Matrix for arc-flash PPE been considered and evaluated?<br>

  • Is arc-rated clothing (8cal/cm2 long sleeved shirts and pants or coveralls) worn as standard uniform? <br>

  • Are workers provided with the proper PPE including Electrical Certified Boots (EH) and Voltage-Rated Gloves for those who are exposed to electrical risks?<br>

  • Is dielectrically testing of voltage-rated gloves and sleeves performed at required intervals? (Every 6 months)<br>

  • Do Service Engineers who are exposed to electrical risks have ready access to a voltage detector or device that is rated category III or higher and are these devices calibrated annually?<br>

Field Section Pre-Work

  • Do all employees and contractors on site have the latest emergency contact information?<br>

  • Are evacuation maps and meeting points, emergency contact numbers, required Government/regulatory postings, customer protocols and notices, certifications, required PPE, etc. prominently posted.<br>

  • Are there locations onsite under construction or any facility containing a hazardous environment confirmed with the customer?

  • Have all workers received a site safety induction?

  • Are the roles and responsibilities clearly defined for this worksite?<br>

  • Is a PICW (Person in Charge of Works) nominated to be in control of the work activity and has he/she completed the ABB PICW course?<br>

  • Has ABB/subcontractor risk assessment/method statement, permits to work, PPE, voltage detection devices, etc. been evaluated by the PICW?

  • Is Risk Assessment(RA), Job Hazard Analysis(JHA) or Job Safety Analysis(JSEA) done properly and communicated to all related parties? <br>

  • Have employees and contractors been briefed on safety signs and signals and other site-specific requirements?

  • Is the project manager and/or electrical safety champion available from LBU to support project safety?

  • Are permits to work for confined space working, hot work, sanctions for test where required, etc. available on site where required?

  • Is a first aid kit available at the site?

Field Section Pre-Work II

  • Has the PICW reviewed and discussed drawings, single line diagrams, schematics, OEM specifications ?<br>

  • Has PICW checked for an arc-flash risk assessment that includes incident energy levels, arc-flash boundary calculations, and PPE category ratings? If not available, has the ABB Matrix for arc-flash PPE been considered and evaluated?<br>

  • Is arc-rated clothing (8cal/cm2 long sleeved shirts and pants or coveralls) worn as uniform? <br>

  • Are workers provided with the proper PPE including Electrical Certified Boots (EH) and Voltage-Rated Gloves for those who are exposed to electrical risks?<br>

  • Is dielectrically testing of voltage-rated gloves and sleeves performed at required intervals? (Every 6 months)<br>

  • Is PPE monitored and is there a system in place to replace worn or damaged PPE when needed and in a timely manner?<br>

  • Do Service Engineers who are exposed to electrical risks have ready access to a voltage detector or device that is rated category III or higher and are these devices calibrated annually?<br>

  • Are documented pre-job briefings or STOP Take 5 taking place communicating a safe system of work prior to each shift?

  • Is electrical competency assessed and monitored where required?

Field section - Job In Progress

  • Do Service Managers conduct Safety Observation Tours (SOT's) regularly as required?<br>

  • Are ABB Expatriate Workers on site and is the host Country HSE organization aware of their presence on site?<br>

  • Is contractor/subcontractor working safely as required by ABB?<br>

  • Are all employees properly equipped and wearing required PPE including electrical and arc-flash PPE? <br>

  • Are all workers competent to carry out assigned tasks? Evidence verified, i.e. certifications?<br>

  • Has the person responsible for the electrical installation been identified and engaged?<br>

  • Is the PTW properly completed, employees and contractors signed on, was the person in control of the electrical equipment identified and consulted, and was the PTW walked down prior to commencing work?<br>

  • Is Permit-to-Work procedure followed strictly?<br>

  • Are working hours properly controlled on site to prevent fatigue and is travelling to and from the site considered?<br>

Field Section - Job In Progress II

  • Is general housekeeping on site acceptable?<br>

  • Are flammable, explosive, combustible, poisonous and hazardous substances kept in safe place and preventive measures implemented to avoid fire, explosion and leakages when delivering, storing, and using to minimize pollution to the environment?<br>

  • Are there any hazardous wastes from ABB activities at this worksite ? If "yes", Are hazardous wastes stored at appointed place or disposed by a licensed vendor?<br>

  • Is hot work done safely? (fire extinguisher, away from flammables/combustibles, safety watch, hot work permits...)

  • Are electrical tools and equipment were inspected and used on site safe? (i.e. no defective tools used, GFCI, RCD, or ELCB utilized for all temporary power supplies)<br>

  • Is all relevant electrical work performed safely? (7 Steps followed, approach distances identified and demarked, trained and competent, PTW, lockout/tagout, watchmen etc.)<br>

  • Is working at heights operations done safely and is equipment properly inspected? (full body harness, proper working platform, mobile elevated work platform, proper ladder or scaffold, etc.)<br>

  • Is crane operation safe? (Trained, inspected pre-use and annually, tagline used, clear of people, proper signaling, overhead lines considered and delineated, etc.)<br>

  • Is there any confined space operations done safely? (i.e. entry permit, atmospheric monitoring, attendant, rescue plan, communication, etc.)<br>

  • Are testing/commissioning activities carried out properly (i.e test area defined, warning lights, barriers, risk assessment, competent persons)?<br>

  • Does the site supervisor/manager check the working conditions and supervise the behavior of contractor employees?<br>

Control of Contractors

  • Are adequate competent HSE Advisers allocated to the site?<br>

  • Contractors have been instructed and trained in the site risks and hazards and understand and are implementing any necessary control measures?<br>

  • Evidence of competence of contractors for any high risk activities (i.e. electrical work) is present on site?<br>

  • Does PICW ensure that HSE compliance to ABB minimum standards are adhered?

  • Is there a prequalification process for all contractors that includes checking safety programs, injury history, training and competency, insurance liability policy and indemnity, government inspections, fines and penalties, etc.?<br>

  • A process of audit/inspection is in place to check contractors arrangements and compliance to ABB Standards?<br>

  • Contractors have been provided with ABB minimum HSE requirements?<br>

  • Is contractor performance evaluated on an annual basis?<br>

Overall Assessment and Closeout

  • What is one thing ABB could do to make your job safer?

  • Where do you think the next accident will happen?

  • Additional Manager Comments

  • Additional Comments from Service Engineers?

  • Signature of Assessor

  • Select date

  • Pictures?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.