Title Page
-
Audit Title
-
Client
-
Conducted on
-
Prepared by
-
Company representative
Previous Project Inspection
-
Has the last job-site inspection been reviewed for this inspection?
-
Outstanding corrective items from last visit been addressed?
General Conditions
-
Perimeter fence in good condition?
-
Traffic control maintained?
-
Project signage posted?
-
Danger and caution tape maintained?
-
Are impalement hazards such as exposed rebar protected?
-
Temporary lighting adequate?
-
Adequate toilet facilities provided?
-
Drinking water and cups supplied?
Housekeeping
-
Appearance of job-site neat and orderly?
-
Passageways and walkways clear?
-
Projecting nails removed or bent over?
-
Ground clean from oil and grease?
Power and Hand Tools
-
Tools and cords in good condition?
-
All mechanical safeguards in place?
-
Right tools used for the job?
-
PPE appropriate for the tools used?
Ladders
-
Ladders secured to prevent movement?
-
Extension ladders extend at least 3 feet above the landing?
-
Ladders are in good condition?
-
Ladders used properly?
Fall Protection
-
Guardrails installed and maintained in good condition?
-
Personal fall arrest equipment in good condition?
-
Fall arrest equipment used properly?
-
Holes guarded and marked?
Scaffolding
-
Scaffolds erected under supervision of a competent person?
-
Scaffold grade lumber used and decking/planks in good condition?
-
Guys, ties and braces in proper intervals?
-
Guardrail system in place?
-
Access ladders in place?
-
Cross bracing in place?
-
Scaffold inspections completed each shift?
Fire Prevention and Protection
-
Fire extinguishers in place for general conditions and hot work?
-
Monthly and annual inspections completed?
-
Use of approved fuel/gasoline containers?
Excavations & Shoring
-
Shoring of adjacent structures adequate?
-
Banks of excavation sloped or shored correctly?
-
Spoil piles at least 2 feet from edge of excavation?
-
Access provided within 25 feet of employees in trenches?
-
Competent person on site?
-
Inspections performed?
Equipment
-
Backup alarms in place or signal person used?
-
Seat belts used in all mobile equipment?
-
ROPS in good condition?
-
Daily inspections performed?
-
Operators trained?
Cranes and Rigging
-
Slings, hooks, shackles etc... in good condition?
-
Outriggers used?
-
Swing radius barricaded?
-
20 foot distance from power lines maintained or lines de-energized?
-
Qualified rigger and signalman used for lifts?
PPE
-
Hard hats used per standard and company policy?
-
Safety glasses used per standard and company policy?
-
Proper hand protection in place?
-
Proper footwear?
-
Hearing protection used?
-
Respiratory protection used?
Electrical
-
GFCI's used and tested on all 110 outlets?
-
All extension cords 3 wire type and in good condition with ground pins?
-
All power panels labeled?
-
All panels have fronts and covers remain closed?
Welding and Cutting
-
Fire extinguisher at site of welding and cutting?
-
Use and storage of cylinders acceptable?
-
Welding screens in place where required?
-
Proper PPE being utilized?
-
Housekeeping acceptable?
Stairways
-
Treads and landings acceptable?
-
Handrails installed?
-
Temporary lighting in stairways adequate?
-
Housekeeping around stairways acceptable?
Aerial Lifts
-
Operators trained!
-
Equipment in good condition?
-
Gates and guardrails acceptable?
-
Lifts used properly?
Material Handling
-
Material stacked, racked, etc....?
-
Materials stored proper distance from floor openings?
Powder Actuated Tools
-
Employees trained and have card in their possession?
-
Proper eye and face protection used?
-
Misfired cartridges properly disposed of?
-
Hearing protection used?
-
High noise signage posted in area?
Administration
-
First aid kits available and maintained?
-
SDS sheets available for review?
Other Observations
-
Project employee/supervision concerns?
-
Follow up/pre-planning items
-
Issues/Comments