Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Tender Stage
-
Was a copy of AR601A forwarded to the contractor in the tender documents?
-
Did the project team ensure that the contractor conducted a project risk assessment for his works?
-
We're abigroup requirements AR503D included in the tender documents?
-
Was the contractor then vetted for their ability to comply with these requirements?
-
Is the evidence of tender evaluation documented on AR503A record of tender interview?
Sub Contract Preparation Stage
-
Did the contractor have an approved Work Health and Safety Management Plan in place prior to works?
-
Was it reviewed by the appropriate Engineer / Foreman using the pre contract checklist?
Contractors Work Health and Safety Project Plan
-
As a minimum the contractors WHSPP must contain the following information
-
The sequence of activities to be carried out
-
The ways in which the identified risks must be reduced to an acceptable level
-
How to monitor compliance with the safe system of work
-
How changes and modifications introduced
-
Inspection and test plans
-
Applicable SWMS
-
The plant and equipment to be used
-
Information on handling, storage and use of hazardous substances And dangerous goods
-
Manual handling
-
Plant and equipment
-
High risk activities
Prior to works
-
Prior to works a Safety Kick off meeting must be held (and documented) explaining the following
-
How compliance with Abigroup system will be achieved ie fall prevention, site logistics and emergencies
-
Documentation outlining safe methods of work
-
Establish performance monitoring, supervision and incident reporting and management protocols and procedures
-
-
Was the contractors SWMS been reviewed using the checklist prior to works?
-
Are high risk activities signed off by the PM?
-
Is an approved copy of the SWMS available at the workface?
-
Has all abigroup information been provided to the contractors supply chain?
Construction Stage
-
After the subcontractor has commenced on site, the relevant Superintendant or Engineer for the works must administer the following disciplines:
-
Have any new works of changes been addressed by a new risk assessment?
-
Are new revisions of the SWMS reviewed using the SWMS Checklist
-
Are all workers trained in the contents of the SWMS<br>
-
Are their documented contractor inspections of plant and equipment and the works on a daily basis
-
Monitoring any new plant and equipment coming onto site and it's documentation
-
Has a subcontractor audit been carried out within the first 4 weeks of starting the project?
-
Has the sub contractor been audited at least 3 monthly whilst on the project?
-
Is their a sub contractor audit schedule?
Sub contractors inspections and observations
-
Does the sub contractor undertake daily inspections of their work areas using the abigroup daily inspection checklist?
-
Are weekly sub contractor safety meetings being held?
-
Do the sub contractors carry out daily inspections of plant and equipments?
-
Does the. On tractor have plant and equipment registers?
-
Does the contractor provide third party certification of all plant and equipment prior to operation on site?
Sub contractor coordination meetings
-
Are daily pre work briefings being held by the contractor where high risk activities are being carried out?
-
Are sub contractor coordination meetings held weekly?
-
Do the meetings review the sub contractors performance?
-
Do the meetings cover SWMS compliance?
-
Do the meetings cover PTW compliance?
-
Are the meetings recorded with actions etc?
-
Are monthly sub contractor meetings held?
-
Do these meetings review performance?
-
Do these meetings review high risk activities?
-
Do these meetings plan for future works?
-
Do the meetings review compliance to abigroup system?
Health Monitoring
-
Has the sub contractor established a health monitoring program?
-
Has this program been audited for compliance at least each quarter?
-
Select date
-
Add signature