Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • Date & time

Responsibilities

  • Has the PTW authoriser been nominated by the Project Manager?

  • Is this appointment in writing?

PTW Register

  • Is their a PTW register?

  • Is the PTW register used / current?

PTW Training

  • Are all persons responsible for implementing AR624 trained in its use?

PTW Authoriser

  • Is the PTW authoriser controlling, coordinating, completing, monitoring and reviewing the PTW system?

  • Is the permit authoriser approving the authority to work?

PTW Holder

  • Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?

  • Is the PTW retained at the work location?

  • Have all parties signed onto the PTW?

  • Is the PTW closed out within 7 days?

AR 608A Confined Space permit

  • Does the project meet the permit requirements for confined spaces?

  • Is the PTW retained at the work location?

  • Have all parties signed onto the PTW?

  • Is the PTW closed out within 7 days?

  • Has the worker received confined space training?<br><br><br>

AR610A Ground Penetration Permit

  • Does the project meet the permit requirements for Ground Penetration?

  • Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?

  • Is the PTW retained at the work location?

  • Have all parties signed onto the PTW?

  • Is the PTW closed out within 7 days?

AR615B Working at Height Permit

  • Does the project meet the permit requirements for Working at heights?

  • Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?

  • Is the PTW retained at the work location?

  • Have all parties signed onto the PTW?

  • Is the PTW closed out within 7 days?

  • Are the workers trained in working at height?<br>

  • Is their a rescue plan in place?<br>

AR618C Lift Permit

  • Does the project meet the permit requirements Lifting?

  • Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?

  • Is the PTW retained at the work location?

  • Have all parties signed onto the PTW?

  • Is the PTW closed out within 7 days?

AR618D lift Plan

  • Does the project meet the permit requirements Lifting?

  • Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?

  • Is the PTW retained at the work location?

  • Have all parties signed onto the PTW?

  • Is the PTW closed out within 7 days?

AR618G Use of Workbox Permit

  • Does the project meet the permit requirements Lifting?

  • Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?

  • Is the PTW retained at the work location?

  • Have all parties signed onto the PTW?

  • Is the PTW closed out within 7 days?

AR620A Isolation Permit

  • Does the project meet the permit requirements for Isolation

  • Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?

  • Is the PTW retained at the work location?

  • Have all parties signed onto the PTW?

  • Is the PTW closed out within 7 days?

AR624C Hot Works Permit

  • Does the project meet the permit requirements for Hot Works?

  • Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?

  • Is the PTW retained at the work location?

  • Have all parties signed onto the PTW?

  • Is the PTW closed out within 7 days?

AR624D Work Near Power Lines Permit

  • Does the project meet the permit requirements for Working near Power Lines?

  • Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?

  • Is the PTW retained at the work location?

  • Have all parties signed onto the PTW?

  • Is the PTW closed out within 7 days?

AR624E Work on or near Water Permit

  • Does the project meet the permit requirements for Working on or Near Water?

  • Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?

  • Is the PTW retained at the work location?

  • Have all parties signed onto the PTW?

  • Is the PTW closed out within 7 days?

AR624F Demolition Work Permit

  • Does the project meet the permit requirements for Demolition?

  • Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?

  • Is the PTW retained at the work location?

  • Have all parties signed onto the PTW?

  • Is the PTW closed out within 7 days?

AR624G Use of Explosives Permit

  • Does the project meet the permit requirements for Explosives?

  • Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?

  • Is the PTW retained at the work location?

  • Have all parties signed onto the PTW?

  • Is the PTW closed out within 7 days?

AR624H Batter Assessment Permit

  • Does the project meet the permit requirements for Batter Assessment?

  • Is the PTW holder gathering the information and completing the PTW in conjunction with the PTW Authoriser?

  • Is the PTW retained at the work location?

  • Have all parties signed onto the PTW?

  • Is the PTW closed out within 7 days?

Other Items / Issues

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.