Title Page

  • Conducted on

  • Prepared by

  • Sales Order Number & Line

  • Part Number

  • Part Revision Number

Commercial

Commercial Section 1

  • Is this PN a full repeat that is quoted for?

  • Check all Raw material purchasing description specs match the customer BOM

  • Confirm signature

Commercial Section 2

  • Has the part revision been changed since last manufactured?

  • Have you linked the new revision BOM?

  • Have the new revision drawings been linked to the part?

  • Have you linked any new drawings that may have been added to the BOM?

  • Have you checked if the raw material parts have the latest revision specifications attached?

  • Are the customer BOM and drawings linked to the part? Are the latest specifications downloaded?

  • Is the BOM structure and parts lead time checked and OK?

  • Cross check Javelin raw material start size against component drawing

  • Confirmation Signature

  • Cross check Raw material purchasing description specs against BOM

  • Confirmation Signature

  • Updated part costs in line with estimated/quoted costs?

  • Are Hold / Witness / PPM / MPS points required?

  • Are Outwork processes identified?

  • Is this purchase order for SLB with a new or specific end customer?

  • Are there any additional quality requirements within the IP's, BOM or LPI specification? (Inclusive but not restricted to LPI Fluorescent solvent removable method only and specific penetrant that may need to be used)

  • Add additional quality requirement to the Quality table and add the detail to the master routing/work instruction

  • Are Quality tables populated?

  • Is NDE Technique Sheet BHGE parts required?

  • Has this order been acknowledged?

  • Does the part number on Javelin match the part number on the customer PO?

  • Is the Commercial Review Complete?

  • Confirmation Signature

Quality

  • Does the part have a thread?

  • Define method of inspection?

  • Are quality checks complete?

  • Confirmation Signature

Production

  • Have route narratives and work centres been checked and amended? Check if final grinding operations are added for any dimensions that have grinding allowance. Have you aligned setting and labour times?

  • Please confirm production section is considered complete

  • Confirmation Signature

Final Production sign off and WO Created

  • Works Order Number

  • Technical Review complete and accepted

  • Confirmation Signature

  • Notes / Comments

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.