Information
-
ITS SURVEY DOC
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
RPM Signature
SIGNING IN
-
Have all trades signed in and out of store visitors book
-
Have all trades parked out with designated disabled and parent and toddler spaces
-
Have all trades completed a permit to work
SAYS CHECKOUTS
-
All SAYS area including floor and checkouts installed to drawing dimensions
-
Are SAYS checkouts numbered as per design standard
-
Is all software loaded and working correctly
-
Are all power and data connection completed, working and tested
-
All tri lights working, correctly fixed and clean
-
All branding stickers applied (new lanes only)
-
All branding stickers applied (rebranding only)
-
All shelves securely fitted with scanner returns fitted
-
Skirting's and brackets fitted correctly
-
Floor trunking, correct colour, securely fixed, lid in place
-
Re scan bench fitted correctly, handing, bag holder, de tagger, flair pager
-
Floor trunking, correct colour, securely fixed, lid in place
-
Scanner walls fitted, correct location, correct screen position
-
Power poles, plumb, clean,
-
Lighting rafts, correct position, level, lights work, free from damage.
-
All barrier rails and totems installed correctly, free from dust and damage.
-
Vinyl floor fitted correctly, free from damage, dim strip fitted, clean.
SAYS PRODUCE AREA
-
Installed as per drawing dimensions
-
Boxing out fitted correctly, clean, free from damage
-
Scale plinth fixed to floor, 2x fixings with brown caps ( when fixed to boxing)
-
Scale fitted, branding, waste bin fitted.
-
Are all power and data connection completed, working and tested
-
Power poles, plumb, clean,
-
Cables in copex
SELF SERVICE CHECKOUTS
-
All self service installed to drawing dimensions
-
Are self service checkouts numbered as per design standard
-
Is all software loaded and working correctly
-
Are all power and data connection completed, working and tested
-
All tri lights working, correctly fixed and clean
-
All branding stickers applied (new lanes only)
-
All branding stickers applied (rebranding only)
-
Q This way stickers applied correctly
-
Overnight signage fitted correctly (24hr stores only)
-
All shelves securely fitted
-
Skirting's and brackets fitted correctly
-
SSC surfaces cleaned
-
Floor trunking, correct colour, securely fixed, lid in place
-
Cashtube,Power poles, plumb, clean,
-
Cash tube system fully working and tested
-
Chrome hoops fitted, clean and black caps fitted.
-
Barrier rails fitted correctly, all posts secured, free from dust etc....
TENSATOR RAILS (IF APPLICABLE)
-
Tensator barrier fitted correctly, free from damage, posts secured and floor area free from dust.
MAIN-BANK CHECKOUTS
-
Back to wall kit, colour and installation correct
-
Flair pager installed
-
De-Tagger installed
-
Cashtube working correctly
-
Call lights working correctly
-
Service poles cleaned
CCTV SYSTEM
-
Cameras realigned
-
CCTV presets and bit maps set up correctly
AUTO ONE IN FRONT & COUNTWISE SYSTEMS
-
AOIF Cameras realigned to design specification
-
Countwise cameras realigned or added as per design specification
BUILDING WORKS ( FLOORING, CEILING, WALLS)
-
Flooring repairs completed to an acceptable standard
-
Ceiling works completed to an acceptable standard
FINAL WALK ROUND
-
General work area cleanliness acceptable after handover to store.
-
Access equipment removed from shop floor and store in an acceptable manner
-
Signing out, all trades have signed out of both Visitors and Permit to work books