Title Page
-
Audit Title
-
Location
-
Client
-
Conducted on
-
Prepared by
-
AMS Site Supervision
-
Completed on
AMS Safety Program Administration
-
OSHA Postings
-
Emergency numbers / contacts posted
-
Weekly Toolbox Talks
-
First Aid Kits onsite
-
Emergency Action Plan posted
-
Task Hazard Analysis completed for each task / crew
Housekeeping
-
Work area clean and orderly
-
Adequate lighting
-
Cords and leads properly routed
-
Work area clear of slips, trips and fall hazards
-
Stairways / walkways clear
-
Trash picked up
-
Break area / trailer orderly
Working at Heights
-
Fall risk of 6 feet or more? (Including voids, pits and trenches).
-
Proper leading edge protection
-
Guard rails in place where required
-
Wall or roof openings covered or barricaded
-
Floor openings covered or barricaded
-
Fall protection used when needed
Equipment
-
Unsafe or damaged equipment / tool? (Including missing or damaged guards).
-
Incorrect equipment / tool for job? (E.g. Grinding discs for cutting)
-
Unsafe or incompatible attachments used with equipment
-
Untrained or non-certified operators
-
Lack of safe work instructions?
-
Lack of training in safe operation, cleanup and maintenance?
-
Breaks, lights, alarms and signals operative
-
Daily inspections of fork trucks, AWP, lulls, ECT
-
Seat belt worn, lulls, fork truck, etc.
-
Harness and lanyards used in AWP
Hot Work, Welding, Cutting
-
Hot work permits in order
-
Flash back arrestors installed on torch
-
Fire extinguisher on site - inspected
-
Fire watch monitoring the area
-
Weld screens in use
-
Unused cylinders capped
-
Cylinders, hoses, gauges free from damage
-
Spark containment utilized
-
Proper PPE in use
-
Compressed gas cylinders properly stored
Scaffolding
-
Has scaffolding been erected correctly under the supervision of a competent person?
-
Do rolling scaffolds have locking wheels and are locked when used?
-
All scaffolds plumb and level
-
Are scaffolds fully planked?
-
Are toeboards and guard rails in place on scaffolding?
-
Is scaffolding erected on a firm and substantial surface?
-
Adequate sills and base plates
-
Safe access, proper ladder or steps
-
Inspection tag on scaffold
-
Safe Work Load (SWL) exceeded? (Tools, stored materials, number of persons).
Cranes
-
Proper set up including distance to overhead power lines (20 ft)
-
Proper cribbing in place
-
Ground conditions verified (sewers, valts)
-
Lift plan required
-
Lift plan followed
-
Swing radius protected / barricated
-
Operator licensed, crane inspection in cab
-
Signal person qualified
-
Lift area barricaded
Lifting Equipment
-
Loads lifted over persons, close proximity to obstacles incl. 20ft from overhead power lines
-
Rigging properly inspected
-
Hoist, chain fall, come-a-long have current certification
-
Lack of SWL information displayed
-
Unsafe or damaged lifting equipment, including ropes, slings, chains, hooks
-
Riggers certified and qualified
-
SWL of any lifting equipment exceeded
Fall Arrest Equipment
-
Unsafe or damaged harness / lanyard or other fall protection equipment
-
Proper lanyards used
-
Incompatible hooks / equipment
-
Unlabeled or does not meet standards
-
Unsafe or uncertified anchor points
-
Lack of inspection protocol for equipment
-
Lack of or inadequate formal training of employees
Ladders
-
Unsafe or damaged ladders
-
Unsafe positioning of ladders
-
Extension ladders set up with 4:1 ratio
-
Side rails extend 36 inches above landing
-
Step ladders fully open when in use
-
Ladder properly secured
-
Ladder suitable for job? (E.g. Metal ladder used for electrical work / incorrect ladder for job).
-
Damaged ladders removed from jobsite
Excavation
-
Competent person on site
-
Underground utilities marked
-
Water pumped out if present
-
Excavation daily checklist completed
-
Adequate benching, shoring, sloping and or proper trench box
-
Access and egress means provided (not to exceed 25 feet)
-
Spoil set back at least 2 feet
-
Excavation grater than 4 feet if so is a confined space permit completed
-
Excavation properly protected
Confined Space
-
Proper permits filled out
-
Permit posted at entry
-
Entrants and attendant properly trained
-
Supervisor authorized entry
-
Competent person evaluated permit and non-permit spaces
-
Air monitor on site (properly calibrated, properly used)
-
Atmosphere test results documented
-
Energy source locked out
-
Adequate ventilation
-
Rescue plan in place
Hazardous Manual Tasks
-
Inadequate risk controls? (Examples: no job rotation, lighter loads, trolleys, lifting equipment, etc.)
-
Lack of identification hazardous manual tasks
-
Lack of assessment of hazardous manual tasks
-
Lack of training in risk controls and safe lifting / team lifting techniques
-
Unsafe storage location (e.g. flammable near ignition sources, spills could enter storm water drains,etc)
-
Incompatable chemicals stored near each other
-
Safety Data Sheets not accessible on site
-
Lack of emergency procedures for injury / spills/ fire / etc
-
Insufficient or incorrect PPE
-
Insufficient ventilation
-
Excessive quantities stored on site or in vehicles
-
Unsuitable storage containers (unlabeled)
Traffic Management
-
Lack of, or inadequate, Traffic Management Plan (TMP) in place
-
Lack of training in TMP for all persons on site (contractors and visitors)
-
Inadequate controls for TMP (physical barriers, bollards, speed limits, flashing lights, spotters, etc)
Personal Protective Equipment (PPE)
-
ANSI approved safety toe leather boots
-
Hard hats worn
-
Gloves being worn and adequate for the work activity
-
Face shields being used with safety glasses when required
-
Welding hoods being worn in conjunction with safety glasses
-
Eye protection being worn and adequate for the work activity
-
Hearing protection
-
Respirators and masks utilized when needed (welding, silica, chemicals)
-
High visible clothing in use when needed
-
Personal monitors required / worn properly (CO-O2-H2S)
-
Lack of system to issue, inspect, replace and monitor PPE
-
Lack of training in safe use, clean up and inspection of PPE
Work Environment
-
Lack of / or inadequate amenities (toilets, wash area, lunch rooms, etc.)
-
Insufficient lighting
-
Inadequate housekeeping
-
Lack of / or inadequate noise / vibration control
-
Work area barricaded as needed (proper signage)
Electrical Hazards
-
Unsafe electrical cords (damaged, missing ground prong inspected)
-
Contact with underground assets
-
Contact with overhead electrical lines
-
Overloading outlets
-
Cords placed on ground or on metal structures
-
Electrical equipment near water
-
Electrical equipment near flammables
-
Electrical equipment near chemicals that could cause damage
-
Electrical cords / leads that may be damaged from contact with moving machinery parts
-
Lack of Lockout / Tagout (LOTO) procedures for electrical equipment
-
GFCI protection utilized
-
Electrical panels labeled and covered
Environmental Hazards
-
Hazardous waste properly disposed of
-
Lack of / or inadequate Environmental Management Plan (EMP)
-
Lack of / or inadequate dust suppression system
-
Lack of / or inadequate system to prevent contaminants entering storm water drains
-
Lack of water reuse system
Administrative Procedures
-
Lack of / or inadequate Site Safety Plan
-
Failure to obtain permits (SWP, Hot Works, Confined Space, Excavation, etc.)
-
Lack of / or inadequate induction for workers, contractors, visitors
-
Lack of / or inadequate supervisory arrangements
-
Lack of / or inadequate training, licenses, skills, experience
-
Lack of / or inadequate incident notification procedures
-
Lack of / or inadequate routine inspections, monitoring, audits
-
Lack of / or inadequate consultative arrangements
Corrective Actions
-
Enter any corrective actions that will be undertaken
Sign Off
-
Onsite Representative
-
Auditor
-
GC, CM, Site Rep