Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Asbestos
-
There is a demolition/construction plan which identifies, assesses and controls all risks relating to the disturbance or removal of asbestos in accordance with the relevant legislation and state requirements.
-
Asbestos survey prepared by a suitably qualified person.
-
Project risk assessment, asbestos management plan, assess and determine appropriate controls to mitigate the risk associated with disturbance or removal of asbestos (where applicable).
-
An asbestos management plan (AMP) has been established and implemented.
-
Asbestos register that identifies material location, type, quantity, condition and associated risks.
-
Any workers removing asbestos materials are appropriately licensed.
-
A procedure that identifies the requirement for a removal licence, or other similar competency and/or training requirements based on jurisdictional requirements and/or relevant material type and quantity to be removed.
-
Sub-contractor licence and/or certificate records.
-
Training /licence records of workers engaged in asbestos removal.
-
Safe system of work are designed in accordance with the requirements for handling, removing and disposal of asbestos containing materials.
-
Asbestos procedures that adequately address safe removal, handling, transport and disposal of bonded and friable materials - as a minimum, in accordance with relevant legislation, standards and codes of practice.
-
Asbestos air monitoring procedures and records.
-
Implementation of PPE, clothing, de-contamination and containment management procedures.
-
Asbestos clearance certificate.
-
Transport and disposal certificates.
-
Adequate monitoring processes and critical response procedures.
-
Building structure and materials have been identified and considered prior to commencement of demolition/construction.
-
A procedure that identifies a requirement to arrange a survey by suitable qualified persons of the building or structure to identify asbestos containing materials prior to any potential disturbance.
-
Asbestos register or similar.
-
Asbestos survey reports.
-
Engineering survey as required.
-
There are controls in place to prevent inadvertent asbestos contact with members of the public and other workers in the vicinity.
-
A procedure that identifies a process for managing risk of exposure to members of the employees, public or client.
-
Removal process incorporates enclosure and negative extraction where necessary.
-
Warning signage and placards installed.
-
Materials have been disposed off within a restricted area and contained.
-
There is an effective system of air filtering/monitoring and personnel decontamination in accordance with relevant legislation and regulatory requirements.
-
Asbestos procedures that adequately address an effective system of air filtering/monitoring and personnel decontamination in accordance with relevant legislative and regulartory requirements.
-
A removal inclosure under negative air pressure is installed for large scale friable removal activities.
-
Initial and daily continuos air monitoring shall be utilised to test the effectiveness of the enclosure.
-
Decontamination of removal tools is performed.
-
Change rooms, dirty decontamination and clean decontamination units have been installed.
-
Air monitoring results.
-
Clearance certificates.