Title Page
-
Conducted on
-
Job Name and Number
-
Job Name, Pour number and Level
-
Inspected by:
-
Other persons conducting inspection:
Checklist
All questions require a response. Only check the boxes that apply.
-
Verify dimensions of slab edge are correct
-
Verify all blockouts including handrails at balconies (if any) are correct
-
Verify all embeds are installed per shop drawings and contract documents
-
Verify all keyways and DBRs are correct and installed
-
Verify deck is clean
-
Check grade of shoring
-
Verify PT and Rebar is installed per approved documents
-
Verify layout for dowels are correct
-
Verify rebar and PT are chaired properly and not burning before concrete pour
-
Verify all PT has 3" clear spacing from all openings and drains
-
Check PT sheathing for tears (if repairs have been made, verify correct tape and procedure has been used)
-
Verify all crack bars are installed around all openings that require it
-
Verify slab depressions are in the correct location and at the right depth per construction documents
-
Shoring inspection complete
-
Check PT pockets before and after pour, after pour to be clean and free of all debris
-
Mix design to be used/verified:__________