Title Page
-
Job Name and Number
-
Job Name, Pour number and Level
-
Conducted on
-
Inspected by:
-
Other persons conducting inspection:
A pour-check is to be performed, form completed and emailed to pourchecks@americansc.com before any elevated deck pour.
ASC pre pour checklist. All questions require a response. Only check the boxes that apply.
-
Do you have a sealed shoring drawing on site for this pour ?
-
Does this pour have any special requirement for direction of concrete placement ?
-
Have the GC and all parties involved been notified of this requirement ?
Check the box for shoring type.
-
Tables
-
Anthese Truss
-
Are tables built the same as the sealed drawing ?
-
Are all legs dropped and pinned with proper pin ?
-
Are all the pins fully inserted thru both sides of the table leg and truss sleeve ?
-
Are all screws snug ?
-
Are all truss X braces in place and nuts tight ?
-
Are all additional shores on underslings in place and snug ?
-
Are all additional shores secured to prevent tipping ?
-
Have wood post been added under the trusses where the table leg lands in a opening or past the edge of slab ? (2 4X4s or 1 4X6)
-
Have all the tables been inspected for damage from flying previous pours ?
-
Dokamatic Tables
-
Are tables built to match the Doka Assembly drawings ?
-
Are Tables installed the same as the sealed drawing ?
-
Have all the lashing straps and tie downs been installed and snuged on all edge tables ?
-
Have Doka beams been inspected for damage from flying previous pours ?
-
Are all the swivel head wedges tight ?
-
Are all the shores secured in the swivel head ?
-
Are all the shores the capacity shown on the sealed drawings ? (Eurex 20 - Eurex 30)
-
Are all the pins in the shores fully inserted ?
-
Have all the intermediate shores been installed and secured from tipping ?
-
Are all shores snug and plumb ?
-
Are all the pins in the shores fully inserted ?
-
Al-Shor RMD Tables
-
Is shoring installed the same as sealed drawing ?
-
Are all stringer and joist spans within the maximum span allowed shown on the sealed drawing ?
-
Is all cross bracing installed as shown on assembly drawings ?
-
Is the lateral bracing installed on all tables longer than 75' ?
-
Are there (6) M16 X 40 Bolts installed and tight at all Superslim stringers conections ?
-
Are all SS adapters attached to the Super Slim stringer with (2) 19MM pins ?
-
Are all the Al-shor Bases attached to SS adaptor with (2) 1-1/4" X 1/2" Bolts and nuts ?
-
Are all the pins in place top and bottom attaching the Al-shor to the base ?
-
Are all the ledger frames installed and locks in place ?
-
Does the screw jack extension meet the sealed drawing requirements ?
-
Are all screw jacks snug ?
-
Are all additional shores and stringers installed and secured to prevent tipping ?
-
Have all the tables been inspected for damage from flying previous pours ?
-
HI FLYER
-
Are the tables built to match the sealed drawing ?
-
Is any additional shoring installed the same as the sealed drawing ?
-
Are all the column hung jacks located acording to the drawing ?
-
Does the screw jack extension meet the sealed drawing requirments ?
-
Are all 1-1/4" threaded rods SEA Grade 8 or equivalent ?
-
Do all the jacks have two 1-1/4" dia. threaded rods conecting them to the columns ?
-
Are all the washers and nuts installed and tight on the 1-1/4" threaded rods ?
-
Are all the castelite beams properly seated in the screw jack head ?
-
Are all twelve 7/8" bolts at the castelite beam conections in place and tight ?
-
Are web stiffeners installed at all the jack locations ?
-
Are all the Transverse trusses attached to the castolite beams according to the drawing ?
-
Are there 7 on top cord and 7 on bottom cord 7/8" X 12" bolts installed and tight at all the transverse truss splices ?
-
Are there (2) A clamps conecting each joist to castolite truss ?
-
Have all the columns reached 100% of the specified 28 day strength ?
-
Have all the tables been inspected for damage from flying previous pours ?
-
J & S Column Hung System
-
Are tables built and installed the same as the sealed drawing ?
-
Has column concrete reached a minimum of 3000 PSI ?
-
Are the column shores and shims attached to columns or walls as per J&S drawing ?
-
Are all threaded rods and nuts the required 150 KSI 1-7/16" ? ( Lefthanded thread)
-
Are all nuts tight so that no gap can be seen between the shim, shore and concrete ?
-
Are the thrust washers in place between lift pad and adjustment screw ?
-
Are all the adjustment screws snug and at the proper elevation ?
-
Are all additional shores on the I beams in place per the sealed drawing ?
-
Is the center line of the I beam and center line of the adjusting screw aligned within +/- 1/2" ?
-
Are all assembly bolts in place and tight ?
-
Have the tables been inspected for damage to I beams and joist from previous pours ?
-
Hi Load Frames
-
Does scaffold layout match the sealed drawing ?
-
Is scaffold visually plumb ?
-
Are all scaffold braces installed and locking pins locked ?
-
Are all tie downs, lateral braces and lacing shown on the sealed drawing installed ?
-
Are hitch pins and rivets installed if required ?
-
Does the screw jack extension meet the sealed drawing requirement ?
-
Are all the stringers centered and secured in the J head or U head ?
-
Are baseplates supporting all scaffold ?
-
Doka Shoring
-
Is shoring installed the same as sealed drawing ?
-
Are all shores in place, snug, and plumb?
-
Are all the pins in the shores fully inserted ?
-
Is the shore spaceing within the maximum allowed shown on the sealed drawing ?
-
Are all the shores for special conditions installed ?
-
Are all the intermediate shores secured to prevent tipping ?
-
Has all braceing shown on the sealed drawing been installed ?
-
Al Shor
-
Is shoring installed the same as sealed drawing ?
-
Are all the ledger frames installed and locks in place ?
-
Are AL-Shor Pins in place ? (if required)
-
Are all screw jacks snug ?
-
Does the screw jack extension meet the sealed drawing requirements ?
-
Are the AL-Shor frames installed on a sloping surface ?
-
Is the slope less than the maximum allowable slope ? (5 deg)
-
Have braces been installed to nurtalize lateral loads ?
-
ULMA System ( ENKOFLEX and ALUPROP )
-
Is shoring layout installed the same as sealed drawing ?
-
Are all Aluprop shores in place and snug ?
-
Are all shores visually plumb ?
-
Are all prop joint connectors in place and installed properly ? (if required)
-
Are all the bracing frames installed and at the proper height and spacing ?
-
Are the bracing frames the correct size as shown on the sealed drawing ?
-
Are all the Aluprop inner tube extensions within the requirements on the sealed drawing ?
-
Stick with Ellis Shores
-
Is the shore spacing the same as the sealed drawing ?
-
Do all shores have the proper lap with the top a minimum of 2" below the clamp ?
-
Are all the shores in place, snug, and plumb?
-
Do all the shores have 2 nails above the clamps ?
-
Have the extra shores been added under beams and in all the required areas ?
-
Have all shores been checkes for cracks, splits and bows ?
-
Is all X bracing in place at the pour bulkhead and building perimeter ?
-
Is any lacing required ?
-
Is lacing installed at the location and in the direction shown on the sealed drawing ?
-
Is the lacing nailed securely to all the Ellis Shores ?
-
Hybrid System
-
Has all additional shoring been installed as shown on the sealed drawing ? (If required)
-
Are all truss the feet fully bearing on beam ledge?
-
Are all the slider wedges tight ?
-
Have all the trusses been inspected for bent or broken webbing ?
-
Are all braces installed on the pre-cast column or beams ? (If required)
-
Are all the erection bolts loose ?
-
Have the offsets in the table tops been corrected ?
-
Have all filler plates been secured and chaired down ?
-
Are all the embeds blockouts and inserts installed and location verified ?
-
PERI SKY DECK
-
Is the shoring installed the same as the sealed drawing ?
-
Are all the shores in place, snug, and plumb?
-
Are all the intermediate shores secured to prevent tipping ?
-
Are all the shores for special conditions installed ?
-
Has all bracing shown on the sealed drawing been installed ?
-
Are all perimeter chains installed, anchored properly and snug ?
-
Do the deck panel sizes match the sealed drawing ?
-
PERI Multiflex
-
Is the shoring installed the same as the sealed drawing ?
-
Are all the shores in place, snug, and plumb?
-
Are all the pins in the shores fully inserted ?
-
Are all the intermediate shores secured to prevent tipping ?
-
Are all the shores for special conditions installed ?
-
Have all MRK or PRK frames been installed as shown on the sealed drawing ?
-
Are all tie downs, braceing and laceing that are shown on the sealed drawing installed ?
-
Special shoring conditions ( Cantilevers, Openings and Ramps )
-
Is this special shoring condition shown on the sealed drawing ?
-
Are there any cantilevered steel beams or whalers ?
-
Are all cantilevered beams tied down according to the sealed drawing ?
-
Does all the tie down material match the sealed drawing ?
-
Is all the tie down material in place and tight ?
-
Is concrete being poured over any stairway or previous slab opening ?
-
Are the beams across the opening the same size and material shown on the sealed drawing ?
-
Does the spacing match the sealed drawing ?
-
Is this pour on a ramp ?
-
Do all shores have wedges installed to give full bearing on slab below ?
-
Do stringers and joist have wedges installed to provide full bearing ?
-
Are any shores on mud-sills ?
-
Does the mud-sill design match the sealed drawing for size and material used ?
-
Are all the mud-sills centered under shore leg and bearing completely on dirt or gravel ?
-
Is compaction and bearing enough for the leg load ?
-
Are all mud-sills in good sound condition ?
-
Have efforts been made to prevent runoff from washing under mud-pads during heavy rains ?
Stringers and Joist
-
Stringers
-
Are the stringers used the type shown on the sealed drawing ?
-
Are stringer installed in the same direction shown on the sealed drawing ?
-
Does the stringer spacing and spans match the sealed drawing ?
-
Are all the stringers centered in the heads ?
-
Are the stringers properly secured to the shoring ?
-
Are all cantilevers equal to or less than the maximum allowed on the sealed drawings ?
-
Joist
-
Are the joist used the type shown on the sealed drawing ?
-
Does the joist spaceing and spans match the sealed drawing ?
-
Are all cantilevers equal to or less than the maximum allowed on the sealed drawings ?
RESHORES
-
Do you have a Sealed Reshore drawing on site for this pour ?
-
Does the reshore grid match the sealed drawing ?
-
Is the reshore required leg to leg ?
-
Have you verified that the reshore is located leg to leg ?
-
Do the shores used have the rated capacity listed on the sealed reshore drawing ?
-
Are all the shores snug and plumb ?
-
Have spring clips been used on all the post shores ?
-
Are the correct number of reshore levels installed ?
-
Have the lower level reshores been rechecked ?
-
Have all the levels supporting formwork reached required strength ?
-
Are the perimeter reshores secured to prevent falling from the building ?
-
Are any reshores on mudsills ?
-
Does the mud-sill design match the sealed drawing for size and material used ?
-
Are all the mud-sills centered under shore leg and bearing completely on dirt or gravel ?
-
Is compaction and bearing enough for the leg load ?
-
Are all mud-sills in good sound condition ?
-
Have efforts been made to prevent runoff from washing under mud-pads during heavy rains ?
-
Are all outriggers reshored for (3) floors ?
Check the box for Reshore Type. Only check the boxes that applies.
-
Steel Post Shores
-
Are all the pins in the shores completely inserted ?
-
Ellis Shores
-
Do all Ellis Shores have 2 nails above the clamps ?
-
Have the Ellis Shores been inspected for splits, cracks and bows ?
-
Is any lacing required ?
-
Is lacing installed at the location and in the direction shown on the sealed drawing ?
-
Is the lacing nailed securely to all the Ellis Shores ?
-
Scaffold
-
Are all the towers located as shown on the sealed reshore drawing ?
-
Are all scaffold braces installed ?
-
Do all heads have stable blocking between the head and concrete ?
-
Does the extension on the screws meet maximum extension requirments ?
-
Shoring left in for reshore
-
Was this shoring left in place because of concrete strength or PT issues ?
-
Has a new reshore plan been designed for this condition ?
-
Has a new sealed drawing been done for this condition ?
-
Has the reshore been installed exactly by the new sealed drawing ?
-
Have all the additional reshore levels been installed and inspected ?
-
Has this new reshore design been inspected by a qualafied person ?
-
Has the shoring load been released and re snuged ?
-
Is all shoring includeing any added shores still in place ?