Title Page

  • Job Name & number

  • Job Name and Level

  • Floor Level

  • Conducted on

  • Prepared by

  • Personnel

General Punch List Item. All questions require a responce, YES - NO - N/A

  • Is all ASC material removed from this level ?

  • Has all wood, band iron and ASC's nails been removed from the ceilings ?

  • Has all the form material been removed from inside shafts, blockouts and openings ?

  • Have all nails and anchors for securing formwork been removed and the holes repaired ?

  • Are permanant safety rails and hole covers reinstalled to original condition ?

  • Does this level have any pour backs ?

  • Have the pour backs been poured and stripped ?

  • Has this level been broom cleaned after reshore removal ? (When completed add photos.)

Walls & Column formwork

  • Are the walls visually straight and plumb ?

  • Does the form finish on walls meet a Class B (or required) finish?

  • Has the concrete slurry been removed from the top and bottom of all the walls ?

  • Does this job have sheer walls for the elevator shaft ?

  • Has the slurry between the walls and slab been removed ?

  • Have all the tie holes and flipper pockets been patched ?

  • Do the walls and slab edges inside the shaft match ?

  • Have all nessesary repairs been compleated inside the elevator shaft ?

  • Does this job have concrete walls in the stairways?

  • Has the slurry between walls and the slab been removed ?

  • Do the walls and the slab edges match?

  • Has all miss alignement in stairways been bushed and repaired ?

  • Have the tie holes, flipper pockets, honeycome, and bug holes been patched ?

  • Does this stairway meet a class B or the required finish ?

  • Has the concrete slurry been removed from the top and bottom of all columns ?

  • Does the form finish on columns meet a Class B (or required) finish?

Vertical concrete

  • Did ASC place the vertical concrete ?

  • Have honeycome and bug holes been repaired on all the columns ?

  • Have honeycome and bug holes been repaired on all the walls ?

  • Have all tie holes been patched in the walls ?

  • Is any concrete Architectual, Class A or as cast finish?

  • Does form finish meet the required finish ?

  • Does the concrete align with slab edges or other mateing surfaces as required ?

  • Has the repair been compleated ?

  • Has the repair been approved by GC and or Architect ?

Building Type

  • Is this a turnkey job?

  • Does the finish on the elevated slab meet requirments for elevation and finish ?

  • Have all the PT cables been cut off and the pockets patched ?

  • Is this level a exposed parking deck ?

  • Do the shared columns at the ramp align visualy from level to level ?

  • Have all the fins been removed from the ceilings ?

  • Is the plywood on the deck produceing an acceptablee finish ?

  • Has the concrete seepage from deck pours above been removed ?

  • Does this floor have concrete barrier walls ?

  • Have the barrier walls been poured ?

  • Have all the fins been removed and the tie holes patched ?

  • Do the walls meet the required finish ?

  • Does this level have curbs ?

  • Have the curbs been poured ?

  • Does the top and sides of the curbs meet the required finish ?

  • Does this level have barrier cables ?

  • Are all the barrier cable holes in the correct location ?

  • Have the barrier cable holes been inspected and cleaned out ?

  • Is this level a condo/hotel with exposed ceilings ?

  • Is there a drawing indicating all the exposed areas ?

  • Have the ceiling joints and imperfections been ground to +1/8" - 1/4 " in required areas ?

  • Is the plywood on the deck produceing an acceptable finish ?

  • Does this floor have exposed balconies ?

  • Have all fins and nails been removed ?

  • Has the drip strip and champher been removed from all the balconies ?

  • Has any missing or damaged drip strip or champher been repaired ?

  • Is the plywood on the balconies producing an acceptable finish ?

  • Is this an Amenities level ?

  • Does this level have curbs

  • Have the curbs been poured ?

  • Do the curbs meet the required finish ?

  • Does this level have planter and/or barrier walls

  • Have the planter wall been poured ?

  • Have the fins been removed and tie holes patched ?

  • Do the planter walls meet the required finish ?

  • Did ASC install the Imbeds ?

  • Have the nails and slurry been removed from the embeds ?

  • Is ASC responsible for the layout on the embeds ?

  • Does the embeds installation and location match approved shop drawing ?

  • Has the procedure for repair been submitted to GC and or EOR ?

  • Has the repair or repairs been compleated ?

  • Does this level have poured in place stairs ?

  • Have stairs been formed and poured ?

  • Have all the nails been removed from the stair bed and embeds ?

  • Have the treads and risers been measured for required tolerance ?

  • Do the stairs have required clearance on all sides ? (includind headroom and landings)

  • Has this floor been inspected and signed off by the GC ?

  • Signed of By :

  • Add Comments

  • Add photoes

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.