Title Page
-
Location
L-2 Sheet
-
DATE:
-
TECHNICIAN:
PROJECT
-
Job Name:
-
Job Number:
-
Job Location:
-
Installing Contractor:
UNIT INFORMATION
-
Manufacturer:
-
Type:
-
Model #:
-
Lower Serial #:
-
Upper Serial #:
-
Equiptment Tag:
-
Equiptment Rated Voltage:
-
Main Pwr: UPS Pwr: Lighting and Recp. Pwr:
-
Max Breaker Size:
(Step 1) INSTALLATION
-
Check unit exterior for visual damage. Dents, scratches, broken hardware
-
Unit properly supported
-
Ensure equipment is level
-
Access doors are operable and sealed
-
Cabinet doors checked for proper adjustment
-
Ensure no labels are missing, incluiding exterior Arc Flash labeling
-
Inspect for scratches, dents, and rust on exterior of equipment. Note and report all damage
-
Inspect for scratches, dents, and rust on interior of equiptment. Note and report all damage
-
Unit is properly anchored to concrete pad per seismic specification
-
Top section is set, with all split brackets bolted and torqued per install guide
-
Top/bottom section split surfaces properly sealed per install guide
-
Lifting lugs have been removed from top and bottom sections
-
All compartments are free from any sign of mold or water intrusion
-
Duct connections are properly mounted and sealed
-
Verify interior of unit is clean and is clear of debris, dirt and loose hardware
-
Verify Electrical and Control Cabinets are Clean, Vacuum cabinet and top of components
-
Insulation undamaged on evaporative cooler (Leave Drain line coverings until level 3 is complete)
-
Verify all shipping materials and covers have been removed (Leave Drain line coverings until level 3 is complete)
-
Drain/Supply lines are properly routed and secured to unit
-
Check Light Switch for damage
-
Check Receptacle damage
-
Verify Megnahelic gauge, verify scale and calibrate to ZERO
-
Verify Outdoor Air sensor is brought out into outdoor air plenum and installed
-
Verify labels on Receptacle, Light switch and magnehelic
-
Verify control cabinet door devices are labeled
-
480 VAC circuits have been properly routed/terminated by others
-
UPS 120 VAC circuits have been properly routed/terminated by others
-
Light/Recp. 120 VAC circuits have been properly routed/terminated by others
-
Note all devices installed by others and completion of install (If Applicable)
-
Outdoor Air Sensor 1 and 2
-
Return Air Actuator 1 Thru 4
-
Outdoor Air Actuator 1 Thru 4
-
All factory defects and missing parts completed and installed
Mixed Air Compartment Lower Section
-
Verify Pre filters are 2" DEEP PLEATED FILTER MERV 8
-
Verify Final Filters are a 22" DEEP BAG FILTER MERV 13
-
Air filters in proper condition/Verify installed correctly
-
Filter rack is secure with no loose hardware
-
Verify tubing routed and secured properly, not kinked
-
Area around media in M/A compartment sealed properly
-
Verify all media is in place and correct direction
-
Verify M/A Temp sensor routed and secured properly
-
Verify all Junctions and devices are labeled
-
Desiccant bags/Protective floor matting has been removed
-
Verify Area is floor is clean and free of debris
Mixed Air Compartment Upper Section
-
Verify Pre filters are 2" DEEP PLEATED FILTER MERV 8
-
Verify Final Filters are a 22" DEEP BAG FILTER MERV 13
-
Air filters in proper condition/Verify installed correctly
-
Filter rack is secure with no loose hardware
-
Verify tubing routed and secured properly, not kinked
-
Area around media in M/A compartment sealed properly
-
Verify all media is in place and correct direction
-
Verify M/A Temp sensor routed and secured properly
-
Verify all Junctions and devices are labeled
-
Desiccant bags/Protective floor matting has been removed
-
Verify Area and floor is clean and free of debris
EVAP Compartment Lower Section
-
Verify all plumbing connections are properly installed and tight
-
Verify showerheads are adjusted properly
-
Verify showerhead hardware is secured with no loose components
-
Remove dropstop and inspect front of media for damage,proper alignment
-
Install all winterized components
-
Set Topaz ball float to proper height and adjust mounting as needed
-
Set HL,OL, and LL to designed height per spec
-
Verify drain valve/actuator position,210VDC is correct and B side of actuator used
-
Verify Fill/Flush valve/actuator position is correct and B side of actuator is used
-
Verify Overflow installed correctly and adjust as needed
-
Verify stage valves have been adjusted properly per spec
-
Verify factory installed lower pump FSB is installed and routed and secured
-
Verify Upper exterior access door is bolted shut
-
Check backdraft dampers for proper operation and adjust weights as needed
-
Check for any binding in between the actuator and the Bypass damper. Verify all damper hardware is tight. Ubolts, damper jack shaft, etc
-
Manually operate Bypass dampers, Verify they close completely and spring return CLOSE
-
Manually spin fans, verify they spin freely with no resistance
-
Verify UV return line extends into sump a minimum of 8 inches
-
Verify circuit setter for UV light is adjusted per spec
-
Verify proper installation of Drain and fill valves/actuators
-
Check sump pan for debris and clean as necessary
-
Access doors for top and bottom checked for proper adjustment
-
Ensure all multi port block connectors are connected, and undamaged
-
Verify all components are labeled
-
Flow control valves
-
Circuit 1, 2, 3, 4
-
Flow proving switch
-
Constant Flow Valves
-
UV Light
-
Fill control valve
-
Drain control valve
-
Flush control valve
-
Float level sensors
-
MultiPort connectors
-
Spot leak detector
-
Remove desiccant bags and protective floor mats
-
Verify Area and floor is clean and free of debris
EVAP Compartment Upper Section
-
Verify all plumbing connections are properly installed and tight
-
Verify showerheads are adjusted properly
-
Verify showerhead hardware is secured with no loose components
-
Remove dropstop and inspect front of media for damage,proper alignment
-
Install all winterized components
-
Set Topaz ball float to proper height and adjust mounting as needed
-
Set HL,OL, and LL to designed height per spec
-
Verify drain valve/actuator position,210VDC is correct and B side of actuator used
-
Verify Fill/Flush valve/actuator position is correct and B side of actuator is used
-
Verify Overflow installed correctly and adjust as needed
-
Verify stage valves have been adjusted properly per spec
-
Verify factory installed Upper pump FSB is installed and routed and secured
-
Verify Upper exterior access door is bolted shut
-
Check backdraft dampers for proper operation and adjust weights as needed
-
Check for any binding in between the actuator and the Bypass damper. Verify all damper hardware is tight. Ubolts, damper jack shaft, etc
-
Manually operate Bypass dampers, Verify they close completely and spring return CLOSE
-
Manually spin fans, verify they spin freely with no resistance
-
Verify UV return line extends into sump a minimum of 8 inches
-
Verify circuit setter for UV light is adjusted per spec
-
Verify proper installation of Drain and fill valves/actuators
-
Check sump pan for debris and clean as necessary
-
Access doors for top and bottom checked for proper adjustment
-
Ensure all multi port block connectors are connected, and undamaged
-
Verify all components are labeled
-
Flow control valves
-
Circuit 1, 2, 3, 4
-
Flow proving switch
-
Constant Flow Valves
-
UV Light
-
Fill control valve
-
Drain control valve
-
Flush control valve
-
Float level sensors
-
MultiPort connectors
-
Spot leak detector
-
Remove desiccant bags and protective floor mats
-
Verify Area and floor is clean and free of debris
Supply AIr Section Lower
-
Interior access ladder splice plates installed and properly torqued
-
Access ladder is properly mounted to unit and functions as designed
-
Exterior access door is bolted shut with supplied hardware
-
Walkway grating is secure with no loose hardware
-
Pressure tubing for top and bottom has been connected and routed properly
-
Check for any binding in between the actuator and the SA damper. Verify all damper hardware is tight. Ubolts, damper joiner plates, etc
-
Manually operate Supply air dampers, Verify they close completely and spring return OPEN
-
Verify Supply air damper actuators are labeled
-
Fan motors Record the following:
-
Quantity: Model#: Voltage/PH/Hz: HP: RPM: FLA:
-
Connect Upper DP tubing between upper and lower level
-
Perform a leak test on DP tubing to ensure pressure holds Upper Pre filter
-
Perform a leak test on DP tubing to ensure pressure holds Upper Final filter
-
Perform a leak test on DP tubing to ensure pressure holds Lower Pre filter
-
Perform a leak test on DP tubing to ensure pressure holds Lower Final filter
-
Verify Temperature sensor Installed and labeled
-
Verify Humidity Sensor installed and labeled
-
Verify all connectors are tight on Molex or phoenix block and labeled
-
Verify All cables connecting to the molex or phoenix block are labeled
-
Access doors for top and bottom checked for proper adjustment
-
Fan protective screens are secure with no loose hardware
Supply AIr Section Upper
-
Interior access ladder splice plates installed and properly torqued
-
Access ladder is properly mounted to unit and functions as designed
-
Exterior access door is bolted shut with supplied hardware
-
Walkway grating is secure with no loose hardware
-
Pressure tubing for top and bottom has been connected and routed properly
-
Check for any binding in between the actuator and the SA damper. Verify all damper hardware is tight. Ubolts, damper joiner plates, etc
-
Manually operate Supply air dampers, Verify they close completely and spring return OPEN
-
Verify Supply air damper actuators are labeled
-
Fan motors Record the following:
-
Quantity: Model#: Voltage/PH/Hz: HP: RPM: FLA:
-
Verify Temperature sensor Installed and labeled
-
Verify Humidity Sensor installed and labeled
-
Verify all connectors are tight on Molex or phoenix block and labeled
-
Verify All cables connecting to the molex or phoenix block are labeled
-
Access doors for top and bottom checked for proper adjustment
-
Fan protective screens are secure with no loose hardware
Lower and Upper Section Interconnects
-
Verify proper Labeling of Inteconnect Whips
-
120VAC Lighting Circuit Connected
-
120VAC UV Light Cicuit connected
-
480VAC Sump Pump Circuit connected
-
480VAC Supply fan Circuit connected
-
Humidity 420ma circuit complete
-
Supply 420ma temp sensor complete
-
Purge Relay 24VAC coil set connected
-
SF 712 COMM set connected
-
SF712 Speed set connected
-
Molex blocks 47 sets connected
-
Route interconnects along tray to panel and secure properly
-
Supply motors have been Ohm'd out with MP in open position
CONTROLS CABINET
-
Verify all components are installed in the Controls cabinet
-
Check/Tighten all screw terminals
-
Tug test all wires in controls panel
-
Check that all devices are in place and labeled
-
Verify all drawings are located in cabinet
-
Verify Dip switches on controllers are set correctly Refer to Controls Drawing
-
Ensure all devices "installed by others" have been installed, wired correctly and labeled
-
Remove all desiccant bags, shipping material inside and debris metal shavings, screws, etc
MAIN POWER CABINET
-
Verify all components are installed in the power cabinet are correctly sized
-
Verify Main disconnect line side cables are terminated and torque marked
-
Check/Tighten all screw terminals
-
Tug test all wires in electrical panel
-
Proper grounding installed for components and unit
-
Check that all devices are in place and labeled
-
Set pump motor overloads and record setting
-
Verify Main disconnect selector rod does not interfere with operation of opening or closing the door when disconnect is OPEN or CLOSED
-
Motor Protectors have been set for proper load protection
-
Ensure all devices "installed by others" have been installed, wired correctly and labeled
-
Remove all desiccant bags, shipping material inside and debris metal shavings, screws, etc
-
SIGN OFFS
-
Technician:
-
Signature:
-
Date Complete:
-
Document Version 1.4
INTERNAL USE ONLY
IWO FORM INCLUDED WITH UNIT
-
Completed
-
Comments(Ie. Parts Arrival/Ordered Date, Date work completed)
ITEMS LISTED ON FORM
-
YES OR NO
ADDITIONAL HARDWARE NEEDED THAT ISN'T LISTED
-
Completed
-
Comments(Ie. Parts Arrival/Ordered Date, Date work completed)
IF ADDITIONAL PARTS ARE NEEDED, PLEASE LIST HERE AND COMPLETE AN NCR
-
YES OR NO