Title Page

  • Location

Untitled Page

  • Technician End of Day Report

  • FM.0595.006

  • Page 1 of 1

  • DATE:

  • JOB #:

  • Site Location:

  • Number of Units Started

  • Number of Deficiencies

  • Commissioning vs Issue Resolution

  • Technician Name

  • Time In:

  • Average hours per unit start up

  • Time Out:

  • Total hours spent on startup

  • Total hours spent on deficiencies

  • Time In:

  • Average hours per unit deficiencies

  • Time Out:

Activities Examples of activities are in itallics. If unsure of where to put your time, reach out to your Project Manager

  • Job#

  • Time (Hours)

  • Details: ENSURE DETAILS CORRESPOND TO THE TIME AND ACTIVITY FOR THAT ROW Include building and cell/pod where work was completed, number of units completed for Cx activities that day, notes on what was done & who was talked to, issue details outside of those listed in the QAQC Report

  • Site Meetings Daily Cx meetings, Orientation, Safety Meetings, Stretch & Flex

  • Installation / FOK Coordination of CAHU deliveries, observing unloading & installation of "First of Kind" units

  • Level 2 Cx Level 2 Inspections; Red/Yellow tag signing,

  • Site location (building, cell/pod, MZ, unit location)

  • Level 3 Cx Level 3 checklist, Start up of unit; Green tag signing (no issue fixing)

  • Site location (building, cell/pod, MZ, unit location)

  • Level 4 Cx Time spent being available to Cx Agent (no issue fixing)

  • Site location (building, cell/pod, MZ, unit location)

  • Wait Time Waiting on power/water/access to units; Weather delays, Site Stand Downs, Approval of AHAs

  • Assisting Client / Other Vendors Load Banking, Assisting another vendor in troubleshooting

  • Site location (building, cell/pod, MZ, unit location)

  • SilentAire Meetings SA Conference calls, PM site visits, Toolbox / MCS meetings (internal meetings)

  • Acquiring Materials Going to and from store/locker to get materials; Purchasing of materials, Parts order forms

  • SilentAire Issues Fixing factory issues identified after shipment, during inspection or commissioning; Fixing Compass issues

  • RMA Activities Notifying Quality of RMA components; Packaging RMA parts for shipment; Arranging pick up of RMA parts

  • Travel Time Hotel to/from site time, Home to/from site location

  • Paperwork (EOD) & Issue Closeout Writing EOD reports; Closing out Latista issues

  • Other Travel between sites, warranty work,

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.