Information
-
Client
-
Jobsite Name
-
Location
-
Foremen
-
Job description:
-
Conducted on
-
Prepared by
-
Other
-
Item(s) in compliance or to show a positive safety effort?
Access / Egress
-
Extension/Straight Portable Ladders
Ladder
-
Add media
-
Ladder extends 3' over landing
-
In good safe working condition. Proper ladder for the job.
-
Ladder set up at proper angle (4:1)
-
Ladder tied off securely
-
3 points of contact maintained while climbing
-
Fixed Ladders
Fixed Ladder
-
Add media
-
Fall protection or cage available if 24' in height or greater
-
If cage or well is used, landing platform is provided at maximum of 50'
-
Inside of cage or well is free of obstructions
-
Minimum clearance between ladder and obstruction behind is 7"
-
Ladder in good repair, no visible damage
-
Step Ladders
Step Ladder
-
Add media
-
Stepladders in good repair. No visible damage to rails, rungs, or spreader
-
Ladder used in an open a-frame position
-
Proper ladder size used. Climbing on top of stepladder, or on first rung from the top, is prohibited
-
Stairways
Stairs
-
Add media
-
Metal pan stairs are filled with with suitable material or barricaded to prevent access
-
Stairways with four or more risers, or rising more than 30" in height (whichever is less) have stair rails provided on each unprotected edge
-
Handrails are provided between 30" and 37", have at least 3" clearance between the handrail and structure behind, and are constructed so as to provide an adequate handhold
-
All railings are free from projection hazards such as nails, surfaced to prevent injuries or snagging of clothing
Fall Protection
-
No fall from height exposures present. Typically ground work, high parapet walls (39" or greater), or similar structure is present which eliminates fall from height exposure.
-
Warning Line Systems
-
Add media
-
Warning lines completely enclose the roof area
-
Warning Lines Six or 10 feet back
Warning Lines or Stancions
-
Warning lines kept minimum of 6' from edge of roof, or minimum of 10' from edge of roofs with mechanical equipment in use
-
Well maintained, a minimum of 34" off the working surface, a maximum of 39"
-
Stanchions utilized are designed to resist, without tipping over, a force of at least 16 lbs applied horizontally 30" above the walking / working surface
-
Employees adhering with requirement and remaining inside warning lines unless using a different fall protection system
-
Points of access connected to work area by access path formed by two lines. When not in use, a warning line is run across the path to fully enclose the work area
-
Guardrails
-
Guardrails
Guardrails
-
Add media
-
Proper height: Top rail 39-45 inches above the walking working surface. Cable deflects 3" or less and does not sag below 39" with 200lbs of force applied. Midrails installed midway between top rail and walking / working surface
-
Guardrail system properly installed capable of withstanding 200lbs of force
-
Standard toe boards installed if exposure below exists
-
Guardrails surfaced to prevent injury. No protruding nails
-
Safety Monitoring System
-
Add media
-
Safety monitor in audible & visual distance, on same working level and performing monitoring duties only
-
Safety monitor educated to recognize fall hazards and aware of items that he/she should be looking for
-
Monitor used in conjunction with warning line, except for on roofs that are <50' in length or width
-
Employees ensuring a safety monitor is present prior to going outside warning lines or working on an unprotected roof
-
Personal Fall Arrest Systems
-
Add media
-
Add Harnesses, Anchors, Raptors, Lanards, SRDs
Fall Equip
-
Harness, rope, lanyard, etc., in good condition
-
Anchorage points of suitable strength to support fall or restraint (5,000lbs arrest, 1,000lbs restraint). Roof anchors properly installed.
-
Harness & lanyards worn and adjusted properly. Lifelines installed properly, slack removed, pendulum effect and free fall distance considered and controlled
-
Anchorage connectors such as cross arm straps utilized to wrap units / structures. No wrapping of lifelines / lanyards and hooking them back to themselves
-
Skylight and Hole Protection
-
Skylight and Hole Protection
Skylight or Hole
-
Add media
-
Skylight / holes protected by guardrail, cover, net, or personal fall arrest system is used
-
Hole covers capable of withstanding twice the intended load. "Hole" or "Cover" painted atop the cover
-
Hoist Area
-
Hoist Area Fall Protection
Hoist Area
-
Add media
-
Hoist, Rope, and all components in Good condition
-
Guardrails or PFAS utilized in hoisting areas (areas where material / debris / equipment is being brought up to or removed from roof)
-
Employees using PFAS in hoist areas set them up for fall restraint
-
Other
-
Item(s) in compliance or to show a positive safety effort?
Electrical Safety
-
GFCI
-
Add media
-
GFCI in Use?
-
GFCI Functions Properly?
-
Extension Cords, Tool Cords & Power Lines
Cord or Tool
-
Add media
-
Cords and tools in good condition. Damaged cords / tools tagged out of service or rendered inoperable
-
All cords protected from damage (not exposed to vehicular traffic or crushing damage from doors or windows, etc.)
-
All ladders and equipment at least 10' from electrical lines
Temporary Electric Panel
-
All openings effectively closed?
-
Are breakers labeled properly?
-
No circuits ran on floors?
-
Other
-
Item(s) in compliance or to show a positive safety effort?
Fire Prevention
-
No smoking near flammables
-
Fire Prevention
Extinguisher or Can
-
Extinguishers in place, charged and in work area. Clear of obstruction. No more than 100' from employees, no more than 50' from flammables
-
Proper flammable safety cans in use
-
Other
-
Item(s) in compliance or to show a positive safety effort?
General Safety
-
First aid kits available onsite
-
Someone available onsite with a current First Aid Training certificate.
-
SDS available onsite for all chemicals, chemicals properly labelled
-
Are portable toilets set up away from vehicle and equipment paths?
-
Weekly tool box talks conducted
-
General housekeeping efforts kept up
-
All materials and debris secured daily. Public protected from falling / flying objects
-
General precautions taken to protect property from damages
-
Intakes covered or turned off when chemicals used
-
Other
-
Item(s) in compliance or to show a positive safety effort?
Hand and Power Tools
-
Hand and Power Tools
Tool
-
Add media
-
Hand and power tool in good repair. Damaged equipment tagged out of service or rendered inoperable
-
Power tools have proper machine guards in place
-
Hand tools used for the task they are designed for. No prying items with a utility knife
-
Utility knife blades kept sharp, cuts made away from body. Retracted or fully sheathed when not in use
-
Other
-
Item(s) in compliance or to show a positive safety effort?
Material Handling
-
Add media
-
Proper lifting techniques observed. Team lifts or mechanical equipment used when lifting heavy objects
-
Material handling equipment in good condition
-
Debris removed of promptly and safely. Chute provided when over 20'.
-
Crane Safety
-
Other
-
Item(s) in compliance or to show a positive safety effort?
-
Add media
-
Operators licensed / certified
-
Rigging in good condition. Capacities legible. Inspected prior to use with no visible damage.
-
Qualified rigger / signal person used
-
Outriggers fully deployed, pads/cribbing used on soft surfaces
-
Daily inspection of crane performed. Must be documented at least once per month and available on crane
-
Work zone established. Elevated visual aids in place to ensure crane maintains minimum approach distance from overhead power lines
-
Motorized or Mechanized Roofing Equipment
Equipment, buggy, etc
-
Add media
-
All Guards in place
-
starter recoil assembly in place<br>
-
Brakes and safety devices work
-
Forklift Safety
Forklift
-
Add media
-
Operator certified. License available and current (not more than 3 years old)
-
Daily inspection completed. All critical safety elements in good repair (back up alarm, windows & mirrors, boom angle indicator, load chart available, tires in good repair, etc)
-
Seatbelt worn at all times
-
Safe speeds maintained
-
Other
-
Item(s) in compliance or to show a positive safety effort?
Personal Protective Equipment
-
Personal Protective Equipment
PPE
-
Eye protection worn when hazard exits and per policy
-
Hard hats worn when hazard exits and per policy
-
Proper gloves worn when handling tear off debris, when handling sharp metal, and when handling chemicals requiring glove usage
-
Proper work attire worn (boots, pants, sleeved shirts, long sleeve shirts if handling hot asphalt)
-
Other
-
Item(s) in compliance or to show a positive safety effort?
Scaffolding
-
Supported Scaffold
Scaffolds
-
Add media
-
Guardrails and toeboards on all open sides of work area
-
All components in good condition, properly assembled
-
Work platform fully decked with proper overhang / cleating of planks
-
Safe access onto scaffold available
-
Competent person onsite - daily inspections conducted
-
All employees using have user training
-
Scaffold kept a safe distance (10' minimum) from overhead powerlines unless lines have been de-energized or other acceptable safeguards implemented
-
Falling object protection adequate if exposure below exists. Toe boards in place, or netting used if material stacked higher than toe boards
-
Other
-
Item(s) in compliance or to show a positive safety effort?
-
Aerial Lift
Operator or Lift
-
Add media
-
All employees using have received user training
-
Inspections performed prior to operating. No dropoffs, depressions, holes, etc. surrounding the equipment that can be driven into
-
Guardrails in proper working condition. Safety chains latched closed on scissor lifts. Swing gates shut on boom lifts
-
Proper fall protection in place when working from boom lift. Retractable lanyard or other restraining device used. Harness worn properly
-
Equipment kept a safe distance from overhead powerlines (minimum of 10' unless power lines are de-energized or other acceptable safeguard is implemented)
-
Other
-
Item(s) in compliance or to show a positive safety effort?
Specific Roof Systems Hazards
-
Modified Bitumen - Torch Applied System
Torches Tanks
-
Add media
-
Torch set up properly, in good working order. Stand in place. Connections and fittings leak checked prior to use
-
All sparks or open flame controlled and kept away from roof openings which could suck flame into structure
-
No torching to combustible surfaces
-
BUR - Kettle Safety
Kettle
-
Add media
-
Propane tanks upright, in good condition and kept 10' from kettle & building
-
Kettle operator has face shield, long sleeves, proper fire extinguisher, spray bottle to check for leaks?<br>
-
Kettle area flagged / barricaded
-
Is kettle level?
-
Thermometer on kettle working or is probe or infrared thermometer being used?<br>
-
Proper temperature maintained. Ground man present and aware of temperature and flashpoint
-
Is hot pipe properly supported or NOT deflecting or bending
-
Kettle lid closed when not being loaded
-
Other
-
Item(s) in compliance or to show a positive safety effort?
Trenching/Excavation
-
Trench/Excavation
-
Competent Person onsite and trained
-
Spoil Pile At Least 2 feet back
-
Water being pumped out if present
-
Proper Access and Egress Provided
-
Above ground and sub surface installations protected, supported, or removed.
-
Is there proper protection from cave in if over 5 feet or if cave in hazard exist Shielding/Shoring/Sloping/Bencing
-
Excavation Daily Checklist Completed
-
Utility Lines Properly located and marked
-
Are walkways over trench six feet above ground have proper guardrail in place.
-
Other
-
Item(s) in compliance or to show a positive safety effort?
Jobsite Grading
-
Acceptable: Jobsites which have no serious violations of federal requirements, or safety policies and have recognizable hazards controlled at the time of the inspection.<br><br>Needs Improvement: Jobsites in which violations occurred which may be serious in nature but the inspector does not believe them to be done intentionally or egregiously.<br><br>Unacceptable: Jobs in which egregious safety violations exist and are to believe to have been known by those involved.
Follow-up
-
Corrective Actions taken onsite to correct noted deficiencies:
Sign Off
-
On site representative
-
Auditor's signature