Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Site Personnel
General
-
Did the Auditor find the Boiler House secure?
-
Is the Boiler House functionally adequate?
-
Does the Boiler House provide adequate security to inhibit interference by unauthorised personnel?
-
Comment
Occupational Health & Safety
-
Does the Boiler House provide a safe working environment?
-
Is the Boiler House acceptable to the OH&S Committee?
-
Does the Auditor consider that all platforms, stairs, walkways, and ladders conform to AS1657?
-
Is the Boiler clearly marked as a Confined Space fireside and waterside?
-
Is there clear space to provide safe access, operation and maintenance to all equipment?
-
Is there the required access and clear space for all electrical panels?
-
If the noise level is above exposure standard is there a procedure in place to minimise sound levels?
-
Is Hearing Protection signage in place?
-
Is PPE available?
-
Is there adequate ventilation for the Boiler's operation and safety and comfort of the operators?
-
Are all accessible hot surfaces adequately guarded or insulated and signed?
-
Is all machinery correctly guarded with guards in place?
-
Is signage in place on all removable machine guards requiring Isolation prior to removal?
-
Is signage in place on all removable machine guards warning of entanglement hazard?
-
Is signage in place on all removable machine guards warning plant starts automatically?
-
Is there adequate PPE considering heat, steam and chemical hazards?
-
Is there adequate permanent lighting for the normal operation of the Boiler and it's Auxiliaries, including any necessary outside facilities?
-
Is there emergency lighting in place?
-
Is emergency portable (Torch) lighting available?
-
Comment
Fire Fighting Equipment
-
Is there adequate and suitable fire fighting equipment available considering the fuel and hazard risks?
-
Is there an operating maintenance program for the fire fighting equipment in place?
-
Is the fire detection equipment adequate?
-
Is the equipment and the general maintenance/ housekeeping of the Boiler House done in a manner conducive to fire prevention?
-
Is there adequate Emergency Exit signage in place?
-
Do the Exit Doors comply with the Building Code of Australia?
-
Is the Boiler House kept in a clean and tidy condition, with equipment properly adjusted and maintained to facilitate a safe working environment?
-
Comment
Regulatory
-
Does the Boiler House have adequate communications available, including outside call access to Emergency Services?
-
Is the Emergency Shutdown Procedure clearly displayed?
-
In the opinion of the Auditor, does the electrical installation comply with AS3000?
-
Is the Main Isolator on the electrical supply lockable?
-
Are all cables and switchgear legibly labelled?
-
Is all single insulated wiring enclosed in panels, ducts or conduits, and all double insulated wiring suitably protected from damage?
-
Are all motors fitted with lockable isolators?
-
Does the Facility have on site electrical schematics which include wiring marking?
-
Does the Facility have on site technical data sheets for the electrical components?
-
Comment
Boiler House
-
Does the Auditor consider that the Boiler House generally complies with AS3892?
-
Are all floors fire resistant?
-
Are all floors adequately drained for steam and water and directed away from Boiler and supports?
-
Is there a minimum clearance for any explosion relief devices, and is it adequately signed or protected so that personnel would not be injured if it operates?
-
Is the Boiler House within operational temperature limits?
-
Are the flues designed to withstand wind and earthquake forces?
-
If a common flue is used, is a partition installed?
-
With the best knowledge of the Facility, would the Boiler House comply with all Council requirements?
-
Has there been any additions or alterations to the Boiler House since its original erection?
-
Comment
Components
-
Does the Auditor believe that the components in the steam plant have been well maintained and operated?
-
Comment
Boiler/s & Fittings
-
Does the Auditor consider that the Boiler complies with the relevant Australian Standards?
-
Does the Auditor consider that all valves and fittings (including flanges) are appropriate for the intended use and pressure rating?
-
To your knowledge, if the Boiler has been altered, modified or repaired by welding, has the work been carried out under supervision of an inspector in accordance with AS3788?
Safety Valves
-
Are Safety Valve seals intact?
-
Are exhausts vented clear to atmosphere in s safe manner?
-
Are the Safety Valve exhausts drained to a safe place?
-
Can the Hand Easing Gear be operated safely if required?
-
Are the Safety Valves checked regularly to ensure they have not been tampered with and the seals are in place?
-
Add response here
-
Comment
Gauge Glasses
-
Are the Gauge Glasses well lit and visible for the operating position?
-
Are Protective Safety Shields in place for Gauge Glasses the require them?
-
Are the Protective Safety Shields made of hardened glass?
-
Are the Gauge Glasses marked with the operation and alarm points?
-
Comment
Pressure Gauge
-
Is the Pressure Gauge of a suitable range for the Boiler Pressure?
-
Is the Pressure Gauge marked with the correct safe working pressure?
-
Has the Pressure Gauge been correctly fitted with a siphon?
-
Has the Pressure Gauge been calibrated?
-
Does the Pressure Gauge appear to be working correctly?
-
Can the Pressure Gauge be seen from the operating position?
Blowdown
-
Are the Blowdown Valves in a safe position for operation?
-
Does the Boiler Blowdown terminate in a safe manner?
-
Is a Blowdown Tank employed?
-
Is the Blowdown Tank of suitable design?
-
Is Automatic Blowdown fitted?
-
Does the Automatic Blowdown terminate in a safe manner?
Feed Pumps & Controls
-
Is the Boiler fitted with two Feed Pumps?
-
Is the Boiler of Unattended or Limited Attendance design?
-
Do the Feed Pumps change over as per AS2593?
-
Can each Feed Pump be individually isolated?
-
Is/are the Feed Water Pump/s protected by an inline suction strainer?
-
Is there a regular cleaning schedule suitable for the installation?
-
Are Feed Pumps protected to prevent cavitation, vapour lock or overpressure due to low flow?
-
Is this achieved by a relief system?
-
Is the Pressure Relief Valve set to the correct pressure above Boiler Pressure?
-
Is there sufficient flow to avoid cavitation, vapour lock and overpressure?
-
Does the relief system return to the Feed Water Tank?
-
Does the Feed Water Check Valve hold?
-
Is a Feed Water Control Valve fitted?
-
Is its operation checked on a regular basis?
-
Is it fitted with a Manual By-pass Valve and Isolation Valves?
-
Does the Feed Water Control Valve fail safe to the 'Open' position?
-
Comment
Sootblowers
-
Are Sootblowers fitted?
-
Is there adequate provision for isolation of Sootblowers?
-
Can the Sootblower's steam supply be adequately drained before operation?
-
Are the alignment of Sootblowers checked at the time of Boiler Inspection?
-
Is there a procedure clearly displayed for operation and time of use for the Sootblowers?
-
Comment
Air Heater
-
Are Air Heaters fitted?
-
Are differential pressures recorded regularly and confirmed to be within operation limits?
-
Are differential temperatures recorded regularly and confirmed to be within operation limits?
-
Is Gas Outlet Temperature maintained above 'Dew Point'?
-
Comment
Draft Fans (FD - ID)
-
Are the Draft Fans inspected at the time of Boiler Inspection?
-
Do the Operators regularly check the fans for abnormal vibration indicating out of balance situations?
-
Do the Operators regularly check the fan vanes and dampers for correct operation?
-
Comment
Dampers, Ducting and Winbox
-
Are Dampers, Ducting and Windbox checked regularly by the Operators to ensure correct operation, no leakages and appropriate operation?
-
Comment
Grate
-
Is a Firing Grate employed?
-
Indicate the type of Grate
-
Is the Grate cleaned regularly?
-
Are moving/actuating components inspected for wear and clinker build-up regularly?
-
Is the dumping mechanism for emergency shutdown checked for operation regularly?
-
Comment
Economiser
-
Is an Economiser employed?
-
Is there an Economiser Safety Valve fitted?
-
Is the Economiser Safety Valve serviced at the time of Boiler Inspection?
-
Are water differential temperatures recorded regularly by Operators and confirmed to be within operational limits?
-
Is the Economiser inspected at time of Boiler Inspection?
-
Comment
Stack & Ducting
-
Is the Stack and Duct Work regularly inspected?
-
Are Stack Stays fitted?
-
Are Stays checked they are secure at both ends and correctly tensioned?
-
Where the Stack is considerably higher than the surrounding structure, is there Lighting Strike protection fitted?
-
Comment
Controls & Instrumentation
-
Is there a system of instrument checking and calibration that covers all critical instruments on the boiler?
-
Is there a system in place to prevent alteration to the control system?
-
Are control loops checked for correct operation on a regular basis?
-
Comment
Feedwater System
-
Is the incoming feed water tested?
-
What type of Water Treatment plant is installed?
- Water Softener
- Demineralisation
- Reverse Osmosis
- Desalination
-
When was the Water Softener last serviced?
-
Is the water in the feed tank heated?
-
Is the feed tank size appropriate?
-
Is the feed tank mounted high enough to prevent feed pump cavitation?
-
Is there a Deaerator included as part of the Feed Tank?
-
Is the Deaerator operational?
-
Is the Deaerator inspected in conjunction with the Boiler?
-
Is there adequate access to the Feed Tank (and Deaerator if fitted) fo cleaning and inspection?
-
Is the Feed Tank inspected annually and cleaned out if required?
-
Comment
Steam Distribution System
-
Does the Steam Distribution System meet the requirements of AS4041 in the following:
- Design Compliant
- Design Non-Compliant
- Installation Compliant
- Installation Non-Compliant
- Manufacture Compliant
- Manufacture Non-Compliant
- Insulation Compliant
- Insulation Non-Compliant
-
Are Pressure Reducing Stations installed to good industry standards?
-
Is all equipment downstream of Pressure Reducing Stations rated for the upstream pressure or protected by adequately sized relief valves?
-
Has the Steam Distribution System been inspected in the last five years?
-
Enter the date of the last Steam Distribution System inspection.
-
Can major steam users be adequately isolated?
-
Does the isolation of one user isolate other users?
-
Are there adequate condensate drains to ensure the steam traps are operating correctly and to allow safe steam plant start-up?
-
Do all steam traps and drains operate?
-
Is there a planned testing and maintenance system in place for steam traps/pumps?
-
Select the frequency.
-
Stipulate the frequency.
-
Has there been any alterations or additions to the Steam Distribution System since installation?
-
Have alteration and additions been considered for total stress on the system?
-
Have alterations and additions requiring welding been performed by suitably qualified personal?
-
Have alterations and additions been documented setting out the design, welding procedure notification, Non-Destructive Testing results etc?
-
Is pipe work adequately labelled and colour coded with flow direction, pressure and contents?
-
Is all pipe work free from apparent mechanical damage?
-
Is there a steam system warming valve?
-
Does the Steam Distribution System seem to be adequately maintained?
-
Comment
Steam Consumers
-
Are all Pressure Vessels connected to the Steam Distribution System registered? (If required)
-
Are all Pressure Vessels inspected in accordance with AS3788 by a qualified inspector at the frequency required?
-
Are all Pressure Vessels operating within their design limits with respect to Pressure and Temperature?
-
Can all equipment be isolated for both safety and maintenance?
-
Are there exposed sections of plant, in the contact zone, that are operating at temperatures above 50 degrees Celsius?
-
In the opinion of the Auditor is all steam equipment installed, maintained and operated in accordance with good engineering practices?
-
Comment
Chemical Treatment System
-
Is there a suitable water treatment program in place for the boiler?
-
Is there a reputable feed water treatment company represented on site?
-
Are standard tests being carried out on Boiler Water, Feed Water, Softened Water, Condensate Return?
-
Are boiler attendants conducting the tests?
-
Is there a laboratory on site that confirms water tests?
-
Does the Chemical Treatment Company audit water tests?
-
At what frequency is auditing occurring?
-
Is there adequate stocks of all boiler chemicals on site considering lead time for delivery and normal usage levels?
-
Is chemical storage suitable?
-
Is chemical storage dry?
-
Is chemical storage well ventilated?
-
Is chemical storage safe?
-
Is chemical storage adequately signed?
-
Are the chemicals listed within the site's Dangerous Goods Register?
-
Are Safety Data Sheets located with the chemicals?
-
Are chemical drums fit for purpose?
-
Are chemical drums marked with the chemical name and strength?
-
Is there a written procedure on the correct method to make-up any chemicals?
-
Comment
Documentation
-
Pressure Vessels
Pressure Vessel
-
Name the Pressure Vessel
-
Registered Number
-
Serial Number
-
What is the frequency of inspection?
-
Frequency
-
Last Inspection
-
Is the history of each Pressure Vessel available including the Manufacturer's Data Sheet?
-
Are all appropriate inspection certificates available?
-
Are copies of all Boiler Attendant's Licences held on file and are they all in date?
-
Is the Boiler of Unattended or Limited Operation?
-
Is the Registration suitably endorsed?
-
Is the Registration displayed in the Boiler House?
-
Is there a current Log Book available in the Boiler House?
-
Does the Log Book meet the requirements of AS3873?
-
Is the Log Book being filled-out correctly?
-
Are all water tests being logged?
-
Are there Operations Manuals in the Boiler House?
-
Are there current Process & Instrumentation Drawings available?
-
Are there current Electrical Drawings & Schematics available?
-
Are Maintenance Schedules clearly documented?
-
Are there comprehensive maintenance history records of alterations and repairs available?
-
Are all Protection Device test records available?
Operation and Work Practice
-
Are there consistent minimum safety standards available and enforced for the control of all work associated with steam equipment by both employee and contractors?
-
Do only qualified Boiler Attendants Start-up, Operate and Shut Down steam plant?
-
Are other Operators adequately trained to use the steam plant?
-
Do other Operators understand the importance of communicating with the Boiler Attendants before altering Steam demand?
-
Are there regular house keeping inspections by the Services Engineer?
-
Are all logs/records analysed by the Services Engineer?
-
Are all out of normal parameters/problems highlighted to the Services Engineer?
-
Is there a formal documented procedure to report and follow up of plant defects?
-
Is this system effective to ensure that appropriate corrective action is taken in the appropriate time frame?
-
Are there pre-printed check sheets (daily & weekly) used to direct operators
-
Comment
Modifications, Alterations & Repairs
-
Is there an established formal, documented procedure for authorising and recording changes to the system (controls, flow arrangement, equipment etc.)?
-
Is this system strictly followed?
-
When components (piping, valves, vessels, materials, etc.) are repaired/replaced, are they actually checked and documented to ensure that they meet the appropriate specification for intended service?
-
Are Welders tested and certified prior to carrying out welding operations on the system?
-
Is all welding carried out on the system accompanied by documentation?
-
Select the documentation provided.
- Welding Personnel & Qualification
- Weld Location
- Welding Procedure Qualification
- Non-Destructive Testing
-
Is there a documented procedure for isolation, draining, flushing, and testing/inspection the system prior to commencing work on the system and after completion of work?
-
Does this procedure include provision for X-ray testing, welds pressure testing, leak testing?
-
Is a Hot Work Permit system, with provision for after inspection, established and strictly followed for welding, grinding and open flame work?
-
Are electrical and mechanical lockout procedures strictly followed when it is required to carry out maintenance or modification to the system?
-
Comment
Boiler Efficiency
-
Is Flue Gas tested regularly and the combustion system adjusted to provide efficient combustion?
-
Is fuel consumption tracked and reviewed against steam product to monitor efficiency?
-
Does the Auditor consider the boiler is operating efficiently?
-
Comment
Qualifications & Training
-
Are all boiler attendants certified for the appropriate boilers?
-
Do all personnel responsible for working with the steam system have appropriate training?
-
Are all Boiler Attendants trained for the boiler they are using?
-
Is there ongoing training for boiler room staff?
-
Are all the operators of major steam consumers trained in the use of steam and their equipment?
-
Has the maintenance staff been trained for minor breakdowns?
-
Is the Boiler of Unattended or Limited Attendance status?
-
Do maintenance staff hold the appropriate qualifications as per AS2593?
-
Have the Boiler Attendants been provided with detailed duty statements?
-
Have all Boiler Attendants and maintenance staff been trained in the use of fire-fighting equipment?
-
Comment
Inspection & Maintenance
-
Is the Boiler House inspected regularly (daily) by the Service Engineer?
-
Is there a Third Party inspection of the Boiler to AS3788 annually?
-
For Unattended and Limited Attendance boiler installations is there a maintenance contract in place in accordance with AS2593?
-
Are all inspection intervals adequate for the conditions the plant is operating under?
-
Have all modifications to steam pressure equipment (if any), been carried out in accordance with Australian Standards and the appropriate regulatory authority?
-
Comment
Contractors
-
Are Contractors used for work on the system?
-
Are the Contractors carefully checked for competence and experience prior to hiring?
-
Is there a single company representative on site who has control of all liaisons with the Contractors that work on steam plant?
-
Comment
Other Vessels
-
Are there other pressure vessels on site?
-
Select the vessels on site.
- Air Receivers
- Refrigeration Vessels
- LPG Vessels
- Other
-
Enter type of Other Vessels.
-
Are all vessels being inspected by a qualified independent inspector in accordance with AS3788?
-
Are records of inspection available?
-
Do all vessels appear to be installed and operated in accordance with legislative requirements?
-
Comment
General Comments and Summary
-
General Comments
-
Auditor