Substructure
Drainage
-
Drainage runs & manholes installed correctly, correct materials, backfill, and rockers
-
Drainage Paperwork & testing being completed by site team
Services
-
Correct ducts/ services used, backfill and position
-
As-built surveys and Pictures are being completed
Waterproofing & Gas Membrane
-
Correct details from drawings around piles and lapping being completed
-
Site Inspections from supplier and third party gas inspection being conducted
Pre Pours
-
Heave protection installed correctly
-
Reinforcement, placement, concrete cover, cleanliness
As-built
-
Drainage, services, foundations
Superstructure
Slabs & Verts
-
Carpentry - decking install, edge shutters, deck install
-
Reinforcement- placement, cleanliness, concrete cover
-
Cast in's - facade, balcony. brick support
-
Slip form, Finish, clean down and pre pour clanliness
As-built & Finishes
-
Slab Level, edge position, cast ins
-
Cast in, position
-
Slab level and finish within tolerance
-
Soffit (balcony/ carpark) achieves specified finish
-
Handovers being completed in a timely manner alongside the programme