Title Page
-
Report Number
-
Report date:
-
Prepared by:
-
Location:
-
Client:
-
Instalation type:
-
Peak Power (kWp):
-
Nominal Power (kWn):
-
PV modules number:
-
Inverter number:
VISUAL INSPECTION
PV Modules
-
General visual inspection of solar modules
-
Thermographic recording
-
PV Modules Cleaning
GENERAL INSTALATION - ELETRICAL
-
DC and AC wiring check
-
Checking ground connections
-
Equipment status
GENERAL INSTALATION - MECHANICS
-
Properly sealed and watertight cable entry
INVERTERS
-
Checking connections and tightness on the cables
-
Cable Gland check
-
Visual inspection of the equipment
-
Thermographic recording
PV Distribution Board (QGPV)
-
Equipment and assembly as stipulated in the project
-
AC Cut Check
-
Checking the AC Connection Bus
-
Checking Protection Fuses (if applicable)
-
Testing Protections
-
Retightening of all Connection Points
-
Thermographic recording
OTHER
-
All Cables and Equipment are Correctly Labeled
-
Production Counter is Working Correctly
-
Consumer Meeter is Working Correctly
-
Monitoring System is Working Correctly
-
Router is Working Correctly
MEASUREMENTS
INVERTERS
-
DC CURRENT (A)
-
DC VOLTAGE (V)
-
Isolation (ohm)
PV Distribution Board (QGPV)
-
AC CURRENT (A)
-
AC VOLTAGE (V)
-
Isolation (ohm)
-
Earth Measurements (ohm)
CONCLUSION
-
OBS.
-
End of Audit
-
Team members: